Home › Utilities › Arizona

Arizona

Arizona interconnection applications

42 electric utilities serve Arizona (EIA-861, 2025): 6 investor-owned utilitys, 14 public power districts, 10 electric cooperatives, 2 state power authoritys, 7 municipal utilitys, 3 federal power agencys. Together they serve 3,158,829 residential customers; 333,870 residential customers were on net metering at year-end 2025.

Largest utilities in Arizona

APSProcess verified

Investor-owned utility · 1,287,097 residential customers · Arizona

Applications: PowerClerk – APS Interconnection (PowerClerk)

Interconnection process and documents →
SRPProcess verified

Public power district · 1,074,095 residential customers · Arizona

Applications: PowerClerk – SRP Interconnect (PowerClerk)

Interconnection process and documents →
TEPProcess verified

Investor-owned utility · 416,268 residential customers · Arizona

Applications: PowerClerk – TEP PowerClerk

Interconnection process and documents →
UniSource Energy ServicesProcess verified

Investor-owned utility · 95,288 residential customers · Arizona

Applications: PowerClerk – UniSource Energy Services PowerClerk

Interconnection process and documents →
Trico Electric Cooperative Inc.State rule applies

Electric cooperative · 53,721 residential customers · Arizona

Applications: PowerClerk – PowerClerk

Interconnection process and documents →
Sulphur Springs Valley E C Inc.State rule applies

Electric cooperative · 46,398 residential customers · Arizona

Interconnection process and documents →
Mohave Electric Cooperative, Inc.State rule applies

Electric cooperative · 41,741 residential customers · Arizona

Interconnection process and documents →
Navopache Electric Cooperative, Inc.State rule applies

Electric cooperative · 42,295 residential customers · Arizona

Interconnection process and documents →
Electrical District No3 Pinal CountyState guidance

Public power district · 32,951 residential customers · Arizona

Interconnection process and documents →
Navajo Tribal Utility AuthorityState guidance

State power authority · 38,553 residential customers · Arizona

Interconnection process and documents →
City of MesaState guidance

Municipal utility · 15,507 residential customers · Arizona

Interconnection process and documents →
USBIA-San Carlos ProjectState guidance

Federal power agency · 12,018 residential customers · Arizona

Interconnection process and documents →

Export compensation among the researched Arizona utilities: Net billing. Rules differ by utility – see each utility page.

Arizona interconnection rule

Commission

Arizona Corporation Commission (ACC)

Interconnection rule

A.A.C. R14-2-2601 through R14-2-2628 (Title 14, Ch. 2, Article 26) – Interconnection of Distributed Generation Facilities · source

Applies to

Generating facilities operating in parallel with the distribution system of an ACC-jurisdictional utility (public service corporations: IOUs such as APS, TEP, UNS Electric, and electric cooperatives; cooperatives may use Commission-approved Interconnection Manual timelines per R14-2-2627). Not SRP or municipal utilities (not ACC-jurisdictional).

Application form

Utility-specific application 'on a form provided by the Utility, or according to a format provided by the Utility' (R14-2-2614); utility Interconnection Manuals required (R14-2-2628).

Timelines

Completeness review 7 calendar days (applicant has 30 days to cure). Level 1 review 14 days, Level 2 review 21 days. Interconnection agreement sent within 7 days of approval; site inspection within 7 days of request; approval/failure notice within 3 days after inspection and signed documents; re-inspection within 14 days; application may be deemed withdrawn if not interconnected within 180 days of approval (R14-2-2614, -2617, -2618, -2621). Non-exporting storage and inadvertent-export systems <=20 kW exempt from R14-2-2614 application requirements; Expedited process in R14-2-2623.

Fees

Application/processing, additional-review, inspection and metering fees only if contained in a Commission-approved tariff (R14-2-2614, -2617, -2618, -2621). Customer pays required utility facility/equipment modifications.

Insurance

Utility shall not require general liability insurance as condition of interconnection, nor a particular insurer (R14-2-2607); exception: RUS-financed utilities (cooperatives) may require liability insurance to the extent needed for RUS obligations.

External disconnect

If required by the utility, customer installs a visual-open, manually operated, load-break disconnect switch isolating all ungrounded conductors (gang-operated for multi-phase); utility may add requirements in its Interconnection Manual (R14-2-2624). Inspection checks 24-hour utility access to disconnect (R14-2-2621).

Export compensation

Net billing – A.A.C. R14-2-2301 et seq. (Net Metering rules, eff. 2009); ACC Decision No. 75859 (Jan. 3, 2017)
Decision 75859 replaced retail net metering for new customer-generators of ACC-regulated utilities with an export rate initially set by the Resource Comparison Proxy (RCP) methodology, changes limited to 10%/year; existing NEM customers grandfathered. Exact implementation is utility-tariff specific (APS, TEP, UNSE RCP riders). Details from secondary summaries; decision text not retrieved.

Not bound by the rule

Electric cooperatives are bound by Article 26 but may substitute timelines via Commission-approved Interconnection Manuals and must use best reasonable efforts to meet deadlines (R14-2-2627). SRP and municipal utilities are not ACC-regulated and follow their own interconnection and export-rate policies.

LevelUp toCriteria / review / fee
Level 1 Super Fast Track (R14-2-2617)20 kWInverter-based, Certified Equipment only, must pass screens R14-2-2615(A),(E),(F) · 14 calendar days after completeness notice · No additional-review fee unless in Commission-approved tariff
Level 2 Fast Track (R14-2-2618)2000 kWMaximum capacity < 2 MW (strictly less), must pass screens R14-2-2615(A)-(J); failures may go to Supplemental Review (R14-2-2620) · 21 calendar days after completeness notice · Only per Commission-approved tariff
Level 3 Study Track (R14-2-2619)>= 2 MW or failed Level 1/2/Supplemental screens; optional scoping meeting, feasibility, system impact and facilities studies (45 days each) · Each study 45 days after signed agreement/payment · Customer pays study costs (good-faith estimates) and required upgrades

All 42 utilities in Arizona

Residential customers in Arizona per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited