Investor-owned utilitySCE interconnection application
SCE is an investor-owned utility serving 4,627,247 residential customers in Arizona, California, Nevada (EIA-861, 2025). Applications: PowerClerk (SCE Interconnection Online Application System). Gridpol files SCE interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from SCE’s official sources (see below). Fees and official review timelines not stated on page; check SCE Application Checklist and Rule 21 timelines on first project.
SCE at a glance
Southern California Edison Co (Edison International)
TypeInvestor-owned utility
EIA utility ID17609
Residential customers4,627,247 (EIA-861, 2025)
Net-metered residential customers734,452 (EIA-861, 2025)
Service territory1 county in Arizona, 16 counties in California, 1 county in Nevada
How to applyPowerClerk – SCE Interconnection Online Application System · official link
Who submitsContractor usually submits on customer's behalf; customer authorization via Form 14-796 (Customer Information or Act on a Customer's Behalf). Customer signs interconnection agreement.
Export compensationNet billing – Net Billing Tariff (NBT)
Rate schedules NBT, NBT-V, NEM-ST (legacy), Rule 21
Documents SCE asks for
- Interconnection application formGenerating Facility Interconnection Application (GFIA) Form 14-957, completed in PowerClerk Gridpol prepares this.
- Single-line diagram (one-line)SCE simplified SLD templates: PV <30 kW; AC-coupled PV <30 kW + battery inverter <10 kW; DC-coupled PV <10 kW (or <30 kW with ≤10 kW max continuous output) Gridpol prepares this.
- Interconnection agreementNBT/NEM ≤10 kW: Form 14-923; NBT/NEM renewable: Form 16-344; multiple tariff: 14-773
- Customer signatureResidential (existing single-family): customer-initialed/signed pages of CA Solar Consumer Protection Guide; CSLB disclosure docs; Customer System Size Acknowledgment (≤30 kW)
- Letter of authorization / designated agent form (when applicable)Form 14-796 Act on a Customer's Behalf
- Final inspection sign-offAHJ final inspection job card with AHJ seal, site address and inspector signature
- Load calculation (when applicable)Load Justification Form when system sized above historical usage
- Other utility-specific document (when applicable)Customer Project Information Sheet (CPIS); Material Modification Notification Worksheet 14-987 for changes; Inspection Report 14-903 for ≥30 kW on change of service
How the SCE process runs
- Contractor/customer completes GFIA in SCE PowerClerk and uploads documents
- SCE reviews application
- Install and obtain AHJ final inspection; upload job card
- Sign interconnection agreement
- SCE issues Permission to Operate (PTO) - energize only after PTO
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Simplified residential (≤30 kW) | 30 kW | Simplified SLD templates and CSSA form apply |
| NBT/NEM agreement 14-923 | 10 kW | |
| >1 MW forms | Forms 14-971/972/973/974 for >1 MW |
Storage, EV and stamps
Battery storage
Paired storage uses AC- or DC-coupled simplified SLD templates (battery inverter <10 kW for AC-coupled template); larger configurations require full SLD.
Sources
- SCE - Submit documents (NEM/NBT): https://www.sce.com/residential/generating-your-own-power/net-energy-metering/submit-documents (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.