Home › Utilities › Arizona › UniSource Energy Services
Investor-owned utilityUniSource Energy Services interconnection application
UniSource Energy Services is an investor-owned utility serving 95,288 residential customers in Arizona (EIA-861, 2025). Applications: PowerClerk (UniSource Energy Services PowerClerk). Gridpol files UniSource Energy Services interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from UniSource Energy Services’s official sources (see below). Fees and review timelines not stated on page.
UniSource Energy Services at a glance
UNS Electric, Inc (UNS Energy (Fortis))
TypeInvestor-owned utility
EIA utility ID19728
Residential customers95,288 (EIA-861, 2025)
Net-metered residential customers11,315 (EIA-861, 2025)
Service territory2 counties in Arizona
How to applyPowerClerk – UniSource Energy Services PowerClerk · official link
Who submitsSolar installers must submit on customer's behalf via PowerClerk (installer login only; New Installer Packet to renewables@ address). Customer signs Interconnection Agreement.
Export compensationNet billing – Resource Comparison Proxy (RCP) export rate
Rate locked at application date (resets annually 1 Oct) for 20-year term; TOU or Demand TOU plan required.
Documents UniSource Energy Services asks for
- Interconnection application formInterconnection Application in PowerClerk with drawings (DG Drawing Checklist) Gridpol prepares this.
- Interconnection agreementCustomer signs; Level 1 via DocuSign, Level 2/3 by e-sign/email
- Photos (meter, main panel, equipment)As-built photos after installation
- Other utility-specific documentNotice of (Installation) Completion / Installer System Commissioning Form
- Other utility-specific document (when applicable)Modification Request Form for major changes; Landlord Authorization; Meter Socket Adapter Signature Form
- Final inspection sign-offInstaller secures permits, inspections and clearances
How the UniSource Energy Services process runs
- Installer submits application in PowerClerk
- Utility Renewables review and approval (no construction before approval)
- Customer signs Interconnection Agreement
- Installer obtains permits/inspections; schedule power kill in PowerClerk if needed
- Submit completion notice/commissioning form + photos
- Utility sets production/billing meter and leaves door hanger granting PTO
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | ≤20 kWac |
| Level 2/3 | >20 kWac |
Storage, EV and stamps
Battery storage
Battery systems per SR-710 Distributed Energy Storage Systems (single-phase).
Common issues the utility lists
- Missing material kit components -> meter set rejection
- Construction before approval
- More than one DG meter socket
- Major modification without approved Modification Request
- Wrong installation type (expansions must be flagged)
- No electrical inspection release for power kill
- Site access issues / electrician absent at power kill
- Missing #1 label on main service disconnect
Gridpol’s pre-submission check covers these before we file.
Sources
- UniSource Residential Interconnection Application Process: https://www.uesaz.com/residential-interconnection/ (retrieved 2026-11-13)
Other utilities in Arizona
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.