Electric cooperativeGraham County Electric Cooperative Inc. interconnection application
Graham County Electric Cooperative Inc. is an electric cooperative serving 8,585 customers in Arizona (EIA-861, 2025). Gridpol files Graham County Electric Cooperative Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Arizona’s interconnection rule (A.A.C. R14-2-2601 through R14-2-2628 (Title 14, Ch. 2, Article 26)) applies to Graham County Electric Cooperative Inc.. Levels, timelines and documents below come from that rule; Graham County Electric Cooperative Inc.’s own form and portal are confirmed on the first project.
Graham County Electric Cooperative Inc. at a glance
Graham County Electric Coop Inc
TypeElectric cooperative
EIA utility ID7456
Customers8,585 (EIA-861, 2025, short form: all customer classes)
Net-metered residential customersnone reported
Service territory1 county in Arizona
Documents Graham County Electric Cooperative Inc. asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Interconnection agreementRequired by the state rule
- Final inspection sign-offRequired by the state rule
- Single-line diagram (one-line)Required by the state rule Gridpol prepares this.
- Site plan / site layoutRequired by the state rule Gridpol prepares this.
- Inverter spec sheetRequired by the state rule
- Other utility-specific documentRequired by the state rule
Documents required by the Arizona rule. Graham County Electric Cooperative Inc. may ask for more on its own form; we confirm on the first project.
Arizona interconnection rule
Arizona Corporation Commission (ACC)
Interconnection ruleA.A.C. R14-2-2601 through R14-2-2628 (Title 14, Ch. 2, Article 26) – Interconnection of Distributed Generation Facilities · source
Applies toGenerating facilities operating in parallel with the distribution system of an ACC-jurisdictional utility (public service corporations: IOUs such as APS, TEP, UNS Electric, and electric cooperatives; cooperatives may use Commission-approved Interconnection Manual timelines per R14-2-2627). Not SRP or municipal utilities (not ACC-jurisdictional).
Application formUtility-specific application 'on a form provided by the Utility, or according to a format provided by the Utility' (R14-2-2614); utility Interconnection Manuals required (R14-2-2628).
TimelinesCompleteness review 7 calendar days (applicant has 30 days to cure). Level 1 review 14 days, Level 2 review 21 days. Interconnection agreement sent within 7 days of approval; site inspection within 7 days of request; approval/failure notice within 3 days after inspection and signed documents; re-inspection within 14 days; application may be deemed withdrawn if not interconnected within 180 days of approval (R14-2-2614, -2617, -2618, -2621). Non-exporting storage and inadvertent-export systems <=20 kW exempt from R14-2-2614 application requirements; Expedited process in R14-2-2623.
FeesApplication/processing, additional-review, inspection and metering fees only if contained in a Commission-approved tariff (R14-2-2614, -2617, -2618, -2621). Customer pays required utility facility/equipment modifications.
InsuranceUtility shall not require general liability insurance as condition of interconnection, nor a particular insurer (R14-2-2607); exception: RUS-financed utilities (cooperatives) may require liability insurance to the extent needed for RUS obligations.
External disconnectIf required by the utility, customer installs a visual-open, manually operated, load-break disconnect switch isolating all ungrounded conductors (gang-operated for multi-phase); utility may add requirements in its Interconnection Manual (R14-2-2624). Inspection checks 24-hour utility access to disconnect (R14-2-2621).
Export compensationNet billing – A.A.C. R14-2-2301 et seq. (Net Metering rules, eff. 2009); ACC Decision No. 75859 (Jan. 3, 2017)
Decision 75859 replaced retail net metering for new customer-generators of ACC-regulated utilities with an export rate initially set by the Resource Comparison Proxy (RCP) methodology, changes limited to 10%/year; existing NEM customers grandfathered. Exact implementation is utility-tariff specific (APS, TEP, UNSE RCP riders). Details from secondary summaries; decision text not retrieved.
Electric cooperatives are bound by Article 26 but may substitute timelines via Commission-approved Interconnection Manuals and must use best reasonable efforts to meet deadlines (R14-2-2627). SRP and municipal utilities are not ACC-regulated and follow their own interconnection and export-rate policies.
- Ariz. Admin. Code Title 14, Ch. 2, Art. 26 (LII): https://www.law.cornell.edu/regulations/arizona/title-14/chapter-2/article-26 (retrieved 2026-11-13)
- R14-2-2614 Application requirements: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2614 (retrieved 2026-11-13)
- R14-2-2617 Level 1 Super Fast Track: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2617 (retrieved 2026-11-13)
- R14-2-2607 Insurance: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2607 (retrieved 2026-11-13)
- R14-2-2624 Disconnect Switch Requirements: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2624 (retrieved 2026-11-13)
- R14-2-2627 Electric Cooperatives: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2627 (retrieved 2026-11-13)
Other utilities in Arizona
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.