APS is an investor-owned utility serving 1,287,097 residential customers in Arizona (EIA-861, 2025). Applications: PowerClerk (APS Interconnection (PowerClerk)). Gridpol files APS interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from APS’s official sources (see below). Guide dated Oct 2021 (file 2024); fees, review timelines and current export rate not confirmed.
APS at a glance
Arizona Public Service Co (Pinnacle West Capital)
TypeInvestor-owned utility
EIA utility ID803
Residential customers1,287,097 (EIA-861, 2025)
Net-metered residential customers190,456 (EIA-861, 2025)
Service territory14 counties in Arizona
How to applyPowerClerk – APS Interconnection (PowerClerk) · official link
Who submitsInstallers apply in PowerClerk; customer authorizes via Authorization Form signed by APS customer of record and property owner (DocuSign). Customers can view/initiate via aps.com.
Export compensationNet billing
Not confirmed from APS page in this research.
Documents APS asks for
- Interconnection application formPowerClerk application Gridpol prepares this.
- Letter of authorization / designated agent formAuthorization Form (DocuSign)
- Interconnection agreementSigned by customer of record and system owner (DocuSign)
- Site plan / site layoutShow SES/meter, inverter(s), utility disconnect, lock-boxes, walls/gates, North arrow; no copyrighted drawings Gridpol prepares this.
- Three-line diagramThree-line diagram for inverter systems (one-line acceptable for residential single-phase load-side connection) Gridpol prepares this.
- Customer signatureConsumer Acknowledgement (A.R.S. §44-1763) and Disclaimer (rooftop solar)
- Other utility-specific document (when applicable)Executed contract (residential buy/finance/lease) incl. total system cost incl. permit
- Battery spec sheet (when applicable)Battery spec: DC voltage, Ah, efficiency, UL listings
- Final inspection sign-offGreen tag/permit clearance; if AHJ doesn't inspect: notarized APS Letter-in-Lieu of Electric Clearance
- Other utility-specific document (when applicable)CT enclosure approval; UL field inspector letter + sticker photo for taps
How the APS process runs
- Installer submits PowerClerk application with required documents
- APS reviews: requests revisions or approves - system may be built
- Installer uploads final docs (green tag/clearance, CT approval, UL letter)
- APS reviews final docs and schedules inspection/meter set; verifies field matches diagrams
- APS grants PTO (door hanger + email) or lists items to fix
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Pre-application recommended | ≥500 kW-AC aggregate | |
| >1 MW | control schematics, relay settings, sequence of operations |
Storage, EV and stamps
Battery storage
Energy storage systems must submit battery specification sheets; governed by APS Interconnection Requirements manual.
PE stamp
Commercial: one-line/three-line stamped by AZ-registered electrical PE. Residential: only when APS requires in writing (or AHJ-issued building permit accepted). – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Illegible applications or not meeting Interconnection Requirements manual
- Copyrighted/proprietary/confidential drawings not accepted
- Field conditions not matching approved diagrams at meter set
Gridpol’s pre-submission check covers these before we file.
Sources
- APS Interconnection Application Process Guide: https://www.aps.com/-/media/APS/APSCOM-PDFs/Residential/Service-Plans/Understanding-Solar/InterconnectionApplicationProcessGuide.pdf (retrieved 2026-11-13)
Other utilities in Arizona
- SRP1,074,095
- TEP416,268
- UniSource Energy Services95,288
- Trico Electric Cooperative Inc.53,721
- Sulphur Springs Valley E C Inc.46,398
- Mohave Electric Cooperative, Inc.41,741
- Navopache Electric Cooperative, Inc.40,795
- Electrical District No3 Pinal County32,951
- Navajo Tribal Utility Authority26,978
- City of Mesa15,507
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.