Home › Utilities › Arizona › Gila River Indian Utility Authority (GRICUA)
Electric cooperativeGila River Indian Utility Authority (GRICUA) interconnection application
Gila River Indian Utility Authority (GRICUA) is an electric cooperative serving 2,707 residential customers in Arizona (EIA-861, 2025). Gridpol files Gila River Indian Utility Authority (GRICUA) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Arizona’s interconnection rule (A.A.C. R14-2-2601 through R14-2-2628 (Title 14, Ch. 2, Article 26)) applies to Gila River Indian Utility Authority (GRICUA). Levels, timelines and documents below come from that rule; Gila River Indian Utility Authority (GRICUA)’s own form and portal are confirmed on the first project.
Gila River Indian Utility Authority (GRICUA) at a glance
Gila River Indian Utility Authority (GRICUA)
TypeElectric cooperative
EIA utility ID65261
Residential customers2,707 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory2 counties in Arizona
Documents Gila River Indian Utility Authority (GRICUA) asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Interconnection agreementRequired by the state rule
- Final inspection sign-offRequired by the state rule
- Single-line diagram (one-line)Required by the state rule Gridpol prepares this.
- Site plan / site layoutRequired by the state rule Gridpol prepares this.
- Inverter spec sheetRequired by the state rule
- Other utility-specific documentRequired by the state rule
Documents required by the Arizona rule. Gila River Indian Utility Authority (GRICUA) may ask for more on its own form; we confirm on the first project.
Arizona interconnection rule
Arizona Corporation Commission (ACC)
Interconnection ruleA.A.C. R14-2-2601 through R14-2-2628 (Title 14, Ch. 2, Article 26) – Interconnection of Distributed Generation Facilities · source
Applies toGenerating facilities operating in parallel with the distribution system of an ACC-jurisdictional utility (public service corporations: IOUs such as APS, TEP, UNS Electric, and electric cooperatives; cooperatives may use Commission-approved Interconnection Manual timelines per R14-2-2627). Not SRP or municipal utilities (not ACC-jurisdictional).
Application formUtility-specific application 'on a form provided by the Utility, or according to a format provided by the Utility' (R14-2-2614); utility Interconnection Manuals required (R14-2-2628).
TimelinesCompleteness review 7 calendar days (applicant has 30 days to cure). Level 1 review 14 days, Level 2 review 21 days. Interconnection agreement sent within 7 days of approval; site inspection within 7 days of request; approval/failure notice within 3 days after inspection and signed documents; re-inspection within 14 days; application may be deemed withdrawn if not interconnected within 180 days of approval (R14-2-2614, -2617, -2618, -2621). Non-exporting storage and inadvertent-export systems <=20 kW exempt from R14-2-2614 application requirements; Expedited process in R14-2-2623.
FeesApplication/processing, additional-review, inspection and metering fees only if contained in a Commission-approved tariff (R14-2-2614, -2617, -2618, -2621). Customer pays required utility facility/equipment modifications.
InsuranceUtility shall not require general liability insurance as condition of interconnection, nor a particular insurer (R14-2-2607); exception: RUS-financed utilities (cooperatives) may require liability insurance to the extent needed for RUS obligations.
External disconnectIf required by the utility, customer installs a visual-open, manually operated, load-break disconnect switch isolating all ungrounded conductors (gang-operated for multi-phase); utility may add requirements in its Interconnection Manual (R14-2-2624). Inspection checks 24-hour utility access to disconnect (R14-2-2621).
Export compensationNet billing – A.A.C. R14-2-2301 et seq. (Net Metering rules, eff. 2009); ACC Decision No. 75859 (Jan. 3, 2017)
Decision 75859 replaced retail net metering for new customer-generators of ACC-regulated utilities with an export rate initially set by the Resource Comparison Proxy (RCP) methodology, changes limited to 10%/year; existing NEM customers grandfathered. Exact implementation is utility-tariff specific (APS, TEP, UNSE RCP riders). Details from secondary summaries; decision text not retrieved.
Electric cooperatives are bound by Article 26 but may substitute timelines via Commission-approved Interconnection Manuals and must use best reasonable efforts to meet deadlines (R14-2-2627). SRP and municipal utilities are not ACC-regulated and follow their own interconnection and export-rate policies.
- Ariz. Admin. Code Title 14, Ch. 2, Art. 26 (LII): https://www.law.cornell.edu/regulations/arizona/title-14/chapter-2/article-26 (retrieved 2026-11-13)
- R14-2-2614 Application requirements: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2614 (retrieved 2026-11-13)
- R14-2-2617 Level 1 Super Fast Track: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2617 (retrieved 2026-11-13)
- R14-2-2607 Insurance: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2607 (retrieved 2026-11-13)
- R14-2-2624 Disconnect Switch Requirements: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2624 (retrieved 2026-11-13)
- R14-2-2627 Electric Cooperatives: https://www.law.cornell.edu/regulations/arizona/Ariz-Admin-Code-SS-R14-2-2627 (retrieved 2026-11-13)
Other utilities in Arizona
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.