Home › Utilities › Arizona › TEP
Investor-owned utilityTEP interconnection application
TEP is an investor-owned utility serving 416,268 residential customers in Arizona (EIA-861, 2025). Applications: PowerClerk (TEP PowerClerk). Gridpol files TEP interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from TEP’s official sources (see below). Fees and review timelines not stated on page.
TEP at a glance
Tucson Electric Power Co (UNS Energy (Fortis))
TypeInvestor-owned utility
EIA utility ID24211
Residential customers416,268 (EIA-861, 2025)
Net-metered residential customers54,718 (EIA-861, 2025)
Service territory2 counties in Arizona
How to applyPowerClerk – TEP PowerClerk · official link
Who submitsSolar installers must submit on customer's behalf via PowerClerk (installer login only; New Installer Packet to renewables@ address). Customer signs Interconnection Agreement.
Export compensationNet billing – Resource Comparison Proxy (RCP) export rate
Rate locked at application date (resets annually 1 Oct) for 20-year term; TOU or Demand TOU plan required.
Documents TEP asks for
- Interconnection application formInterconnection Application in PowerClerk with drawings (DG Drawing Checklist) Gridpol prepares this.
- Interconnection agreementCustomer signs; Level 1 via DocuSign, Level 2/3 by e-sign/email
- Photos (meter, main panel, equipment)As-built photos after installation
- Other utility-specific documentNotice of (Installation) Completion / Installer System Commissioning Form
- Other utility-specific document (when applicable)Modification Request Form for major changes; Landlord Authorization; Meter Socket Adapter Signature Form
- Final inspection sign-offInstaller secures permits, inspections and clearances
How the TEP process runs
- Installer submits application in PowerClerk
- Utility Renewables review and approval (no construction before approval)
- Customer signs Interconnection Agreement
- Installer obtains permits/inspections; schedule power kill in PowerClerk if needed
- Submit completion notice/commissioning form + photos
- Utility sets production/billing meter and leaves door hanger granting PTO
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | ≤20 kWac |
| Level 2/3 | >20 kWac |
Storage, EV and stamps
Battery storage
Battery systems per SR-710 Distributed Energy Storage Systems (single-phase).
Common issues the utility lists
- Missing material kit components -> meter set rejection
- Construction before approval
- More than one DG meter socket
- Major modification without approved Modification Request
- Wrong installation type (expansions must be flagged)
- No electrical inspection release for power kill
- Site access issues / electrician absent at power kill
- Missing #1 label on main service disconnect
Gridpol’s pre-submission check covers these before we file.
Sources
- TEP Residential Interconnection Application Process: https://www.tep.com/residential-interconnection/ (retrieved 2026-11-13)
Other utilities in Arizona
- APS1,287,097
- SRP1,074,095
- UniSource Energy Services95,288
- Trico Electric Cooperative Inc.53,721
- Sulphur Springs Valley E C Inc.46,398
- Mohave Electric Cooperative, Inc.41,741
- Navopache Electric Cooperative, Inc.40,795
- Electrical District No3 Pinal County32,951
- Navajo Tribal Utility Authority26,978
- City of Mesa15,507
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.