Public power districtSRP interconnection application
SRP is a public power district serving 1,074,095 residential customers in Arizona (EIA-861, 2025). Applications: PowerClerk (SRP Interconnect (PowerClerk)). Gridpol files SRP interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from SRP’s official sources (see below). Fees and solar price plan not confirmed in this research; process doc dated 11/2022.
SRP at a glance
Salt River Project
TypePublic power district
EIA utility ID16572
Residential customers1,074,095 (EIA-861, 2025)
Net-metered residential customers63,437 (EIA-861, 2025)
Service territory3 counties in Arizona
How to applyPowerClerk – SRP Interconnect (PowerClerk) · official link
Who submitsInstaller applies via PowerClerk; property owner signs Distribution Interconnection Agreement electronically.
Review time (official)Customer has six months to complete IA, installation and commissioning after application.
Documents SRP asks for
- Interconnection application formPowerClerk Program Application Gridpol prepares this.
- Interconnection agreementDistribution IA sent to property owner for e-signature; based on kW-AC
- Three-line diagramThree-line drawing reviewed by SRP design consultant; as-builts for modifications Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- Final inspection sign-offCity Clearance (CC) from AHJ, or Certificate In-lieu of Electrical Clearance (CILC) to CCDESK@srpnet.com where AHJ doesn't permit
- Other utility-specific document (when applicable)Meter Pull form in PowerClerk if de-rate required
How the SRP process runs
- Apply online via PowerClerk
- SRP reviews for completeness
- SRP sends Distribution Interconnection Agreement to property owner
- Design review by SRP design consultant (schedule SES upgrade/meter pull first if needed)
- Install after design approval and AHJ permits
- AHJ inspection - CC sent to SRP or CILC
- Request SRP Final Inspection via PowerClerk (revisions ≥5 days before)
- SRP sets new meters; energize within 24 h
- SRP issues Permission to Operate letter
Storage, EV and stamps
Battery storage
Battery included in DER process; battery must be charged for SRP Final Inspection.
PE stamp
Three-line drawings must be stamped by AZ-registered PE if the jurisdiction does not issue permits. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Failed final inspection - reasons emailed to installer
Gridpol’s pre-submission check covers these before we file.
Sources
- SRP Residential DER Interconnection Process Checklist (11/22): https://www.srpnet.com/assets/srpnet/pdf/energy-savings-rebates/home/solar-residential-interconnection-process.pdf (retrieved 2026-11-13)
Other utilities in Arizona
- APS1,287,097
- TEP416,268
- UniSource Energy Services95,288
- Trico Electric Cooperative Inc.53,721
- Sulphur Springs Valley E C Inc.46,398
- Mohave Electric Cooperative, Inc.41,741
- Navopache Electric Cooperative, Inc.40,795
- Electrical District No3 Pinal County32,951
- Navajo Tribal Utility Authority26,978
- City of Mesa15,507
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.