Home › Utilities › New Jersey

New Jersey

New Jersey interconnection applications

14 electric utilities serve New Jersey (EIA-861, 2025): 4 investor-owned utilitys, 9 municipal utilitys, 1 electric cooperative. Together they serve 3,718,585 residential customers; 219,395 residential customers were on net metering at year-end 2025.

Largest utilities in New Jersey

PSE&GPartly researched

Investor-owned utility · 2,072,339 residential customers · New Jersey

Applications: PDF + email – Email to CINETMETER@PSEG.com (Level 1)

Interconnection process and documents →
JCP&LProcess verified

Investor-owned utility · 1,047,687 residential customers · New Jersey

Applications: Own online portal – FirstEnergy Interconnection Portal

Interconnection process and documents →
Atlantic City ElectricProcess verified

Investor-owned utility · 509,015 residential customers · New Jersey

Applications: Own online portal – Connect the Grid Interconnection Portal (Green Power Connection)

Interconnection process and documents →
Rockland Electric (O&R New Jersey)Process verified

Investor-owned utility · 66,678 residential customers · New Jersey

Applications: PowerClerk – RECO DG Interconnection PowerClerk

Interconnection process and documents →
City of VinelandState guidance

Municipal utility · 22,866 residential customers · New Jersey

Interconnection process and documents →
Sussex Rural Electric Cooperative Inc.State guidance

Electric cooperative · 12,201 customers · New Jersey

Interconnection process and documents →
Borough of ButlerState guidance

Municipal utility · 11,849 customers · New Jersey

Interconnection process and documents →
Borough of MadisonState guidance

Municipal utility · 6,894 customers · New Jersey

Interconnection process and documents →
Borough of South RiverState guidance

Municipal utility · 6,547 customers · New Jersey

Interconnection process and documents →
Borough of Park RidgeState guidance

Municipal utility · 4,032 customers · New Jersey

Interconnection process and documents →
Seaside Heights Municipal Utility (NJ)State guidance

Municipal utility · 3,222 customers · New Jersey

Interconnection process and documents →
Borough of MilltownState guidance

Municipal utility · 3,181 customers · New Jersey

Interconnection process and documents →

Export compensation among the researched New Jersey utilities: NEM. Rules differ by utility – see each utility page.

New Jersey interconnection rule

Commission

New Jersey Board of Public Utilities (NJBPU)

Interconnection rule

N.J.A.C. 14:8-5 (Interconnection), as amended by R.2025 d.078 (57 N.J.R. 1420(b), eff. July 7, 2025) and R.2026 d.010 (58 N.J.R. 72(a), eff. Jan. 5, 2026) – Interconnection of customer-generator facilities (Grid Modernization rules) · source

Applies to

The four electric distribution companies (EDCs) regulated by NJBPU: PSE&G, JCP&L, Atlantic City Electric, Rockland Electric. Applications via each EDC's CIAP-compliant automated portal.

Application form

EDC standard Interconnection Application/Agreement form (Part 1 application signed by EDC as approval; Part 2 after construction-official approval) submitted through the EDC's CIAP automated portal (N.J.A.C. 14:8-5.2, 5.4).

Timelines

Level 1: completeness 3 BD; decision 10 BD after complete; EDC returns signed Part 1 and states inspection requirement within 3 BD of approval; after construction-official approval and Part 2: authorization to energize within 5 BD if inspection waived; if inspection required, appointments offered within 5 BD and held within 10 BD, authorization within 5 BD after successful inspection. EDC may not condition energizing on meter replacement (5.2(g)). PAVE report for > 500 kW (5.10).

Fees

Level 1: none. Level 2: <= $50 + $1/kW export capacity (+ actual cost of minor modifications/additional review). Level 3: <= $100 + $10/kW export capacity, max $10,000 (+ study costs) (N.J.A.C. 14:8-5.7 as amended 2026).

Insurance

EDC shall not require Level 1 or Level 2 customer-generators to purchase additional liability insurance, except at the EDC's discretion when required to maintain safety, power quality or reliability (N.J.A.C. 14:8-5.2(e), amended 2025).

External disconnect

EDC shall not require Level 1 or Level 2 customer-generators to install external disconnect switches not included in the interconnection equipment, except at EDC discretion when required for safety, power quality or reliability (N.J.A.C. 14:8-5.2(e)).

Export compensation

NEM – N.J.S.A. 48:3-87(e); N.J.A.C. 14:8-4 (Net metering)
Net metering for Class I renewable customer-generators of EDCs; system sized not to exceed annual on-site consumption (no fixed kW cap per older rule text); annualized period with excess at avoided cost. Rule text and 2025 amendment to 14:8-4.2 not re-read in detail.

Not bound by the rule

Municipal electric utilities (e.g., Vineland, Madison, Butler) and Sussex Rural Electric Cooperative are not EDCs under these BPU rules and follow their own interconnection/net metering policies (not reviewed).

LevelUp toCriteria / review / fee
Level 1 (14:8-5.4)50 kWInverter-based with smart inverter capability, certified (14:8-5.3), nameplate <= 50 kW AC AND export capacity <= 25 kW AC; screens: <=10% of max fault current, radial aggregate export <=100% of relevant minimum load, shared secondary <=30 kVA · Completeness 3 business days (applicant 15 BD to cure); RPA check 5 BD; decision 10 BD after complete (12 if RPA amended); signed Part 1 within 3 BD · No application or other fee
Level 2 (14:8-5.5)2000 kWCertified, export capacity <= 2 MW AC, or not qualifying/failing Level 1 · Completeness 3 BD; determination 15 BD after complete · Up to $50 + $1/kW export capacity, plus minor modifications/additional review at actual cost
Level 3 (14:8-5.6)> 2 MW AC or not qualifying/failing Level 2; impact and facilities studies · Up to $100 + $10/kW export capacity, max $10,000, plus actual study costs

All 14 utilities in New Jersey

Residential customers in New Jersey per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited