Electric cooperative

Garkane Energy Cooperative, Inc. interconnection application

Garkane Energy Cooperative, Inc. is an electric cooperative serving 13,379 residential customers in Arizona, Utah (EIA-861, 2025). Gridpol files Garkane Energy Cooperative, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Utah’s interconnection rule (Utah Admin. Code R746-312 (Electrical Interconnection)) applies to Garkane Energy Cooperative, Inc.. Levels, timelines and documents below come from that rule; Garkane Energy Cooperative, Inc.’s own form and portal are confirmed on the first project.

Garkane Energy Cooperative, Inc. at a glance

Utility

Garkane Energy Coop, Inc

Type

Electric cooperative

EIA utility ID

6957

Residential customers

13,379 (EIA-861, 2025)

Net-metered residential customers

251 (EIA-861, 2025)

Service territory

2 counties in Arizona, 7 counties in Utah

Documents Garkane Energy Cooperative, Inc. asks for

  • Interconnection application formRequired by the state rule Gridpol prepares this.
  • Interconnection agreementRequired by the state rule
  • UL 1741 / IEEE 1547 certificationRequired by the state rule

Documents required by the Utah rule. Garkane Energy Cooperative, Inc. may ask for more on its own form; we confirm on the first project.

Utah interconnection rule

Commission

Public Service Commission of Utah

Interconnection rule

Utah Admin. Code R746-312 (Electrical Interconnection) – Electrical Interconnection · source

Applies to

Public utilities providing electric service (Rocky Mountain Power). Rule also defines governing authority for distribution electrical cooperatives (board of directors) for net metering interconnections; fee limits apply to commission-regulated utilities, other utilities may set reasonable fees. Municipal utilities not covered.

Application form

Standard form application/interconnection agreement based on FERC SGIP forms, modified to match the rule (R746-312-2 'standard form')

Timelines

Date/time stamp on receipt; acknowledgment 3 business days; completeness 10 business days (10 business days to cure); Level 1/2 screens 15 business days after completeness; Level 1 deemed approved if no notice within 25 business days of receipt; final authorization/inspection within 10 business days of documentation, otherwise witness test waived.

Fees

Level 1: none. Level 2: <=$50 + $1/kW. Level 3: <=$100 + $2/kW + study costs; engineering <=$100/h (annual CPI adjustment).

Insurance

For net metering customers meeting Utah Code 54-15-106 standards, the utility may not require additional tests or additional liability insurance.

Export compensation

Net billing – Utah Code Title 54, Chapter 15 (54-15-102 to -106)
Customer generation system 1.2-25 kW residential, <=2 MW non-residential (inverter-controlled). Excess credited at least at avoided cost or as set by governing authority (PSC/co-op board); unused credits expire at end of annualized billing period (April-March) and go to low-income programs. Rocky Mountain Power uses a PSC-set export credit (cost-benefit determination under 54-15-105.1). Utilities may close program at 0.1% of 2007 peak or if <1,000 customers.

Not bound by the rule

Distribution electrical cooperatives fall under Utah Code 54-15 with their board of directors as governing authority (sets credits, extra requirements). Municipal utilities are not electrical corporations under 54-15 and set their own policies.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.