Home › Utilities › Michigan

Michigan

Michigan interconnection applications

58 electric utilities serve Michigan (EIA-861, 2025): 7 investor-owned utilitys, 11 electric cooperatives, 40 municipal utilitys. Together they serve 4,457,046 residential customers; 26,849 residential customers were on net metering at year-end 2025.

Largest utilities in Michigan

DTE EnergyProcess verified

Investor-owned utility · 2,078,328 residential customers · Michigan

Applications: PowerClerk – DTE Interconnection (PowerClerk)

Interconnection process and documents →
Consumers EnergyProcess verified

Investor-owned utility · 1,662,741 residential customers · Michigan

Applications: PowerClerk – Consumers Energy PowerClerk

Interconnection process and documents →
Great Lakes EnergyProcess verified

Electric cooperative · 123,277 residential customers · Michigan

Applications: PDF + email – GLE Renewables

Interconnection process and documents →
Indiana Michigan Power (I&M)Process verified

Investor-owned utility · 537,980 residential customers · Michigan

Applications: PowerClerk – AEP PowerClerk

Interconnection process and documents →
City of LansingState guidance

Municipal utility · 87,026 residential customers · Michigan

Interconnection process and documents →
UPPCOProcess verified

Investor-owned utility · 47,805 residential customers · Michigan

Applications: PDF + email – UPPCO Customer Generation

Interconnection process and documents →
Cloverland Electric Co-opState rule applies

Electric cooperative · 36,144 residential customers · Michigan

Interconnection process and documents →
Cherryland Electric Cooperative Inc.State rule applies

Electric cooperative · 35,548 residential customers · Michigan

Interconnection process and documents →
UMERC (We Energies)Process verified

Investor-owned utility · 33,339 residential customers · Michigan

Applications: PDF + email – UMERC-We Energies Central Group

Interconnection process and documents →
Presque Isle Electric & Gas CooperativeState rule applies

Electric cooperative · 32,519 residential customers · Michigan

Interconnection process and documents →
Midwest Energy CooperativeState rule applies

Electric cooperative · 30,545 residential customers · Michigan

Interconnection process and documents →
City of HollandState guidance

Municipal utility · 27,007 residential customers · Michigan

Interconnection process and documents →

Export compensation among the researched Michigan utilities: Net billing, NEM. Rules differ by utility – see each utility page.

Michigan interconnection rule

Commission

Michigan Public Service Commission

Interconnection rule

Mich. Admin. Code R 460.901a - R 460.1016 (MIXDG: Interconnection and Distributed Generation Standards) – Michigan Interconnection and Distributed Generation Standards · source

Applies to

Rate-regulated electric utilities (IOUs and rate-regulated cooperatives), member-regulated cooperatives (for R 460.901a-460.992), and alternative electric suppliers; not municipal utilities

Application form

Utility-specific interconnection application/procedures filed with MPSC per rule (online application allowed); Commission-approved standard Level 1-3 interconnection agreement (Case U-21543)

Timelines

Acknowledge receipt by end of 3rd business day; completeness determination within 10 business days; applicant 60 business days to cure (2 submissions), utility 10 BD per resubmission (R 460.936). Fast track initial review 10 BD (Levels 1-2) / 20 BD (Levels 3-5) (R 460.946). Facilities study 80 BD (R 460.962). DG-program customers must complete installation within 6 months of complete application (R 460.1006).

Fees

Pre-application report <=$300; non-export and fast track $100 + $1/kWac certified or $100 + $2/kWac non-certified; supplemental review <=$1,000; study scoping <=$300; SIS <=$10,000; facilities study <=$15,000 (R 460.926). DG program application fee <=$50 (R 460.1006).

Insurance

Level 1 and 2: utility may not require additional liability insurance or being named additional insured. Minimum general liability: Level 3 $1,000,000; Level 4 $2,000,000; Level 5 $3,000,000 (R 460.986).

External disconnect

Not found in reviewed rule sections; per utility interconnection procedures.

Export compensation

Net billing – MCL 460.1173 et seq. (Distributed Generation Program); R 460.1001-460.1016
DG program (inflow/outflow billing) replaced legacy net metering; outflow credited at a rate below full retail set per utility. Category sizes/caps per statute; detail not verified here.

Not bound by the rule

Member-regulated cooperatives are covered by the interconnection rules (R 460.901a(v)). Municipal utilities are not covered and use their own policies.

LevelUp toCriteria / review / fee
Level 120 kWCertified project <=20 kWac · Fast track initial review 10 business days after complete application · $100 + $1/kWac (fast track, certified); combined with DG program fee capped at $50 total for DG-program applicants (R 460.926(2))
Level 2150 kWCertified project >20 to 150 kWac · 10 business days initial review · $100 + $1/kWac
Level 3550 kWNon-certified <=150 kWac, or >150 to 550 kWac · 20 business days initial review · $100 + $1-2/kWac
Level 41000 kW>550 kWac to 1 MWac · 20 business days initial review · $100 + $1-2/kWac; pre-application report required
Level 5>1 MWac · 20 business days initial review · Study fees capped: SIS $10,000, facilities study $15,000

All 58 utilities in Michigan

Residential customers in Michigan per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited