Home › Utilities › Michigan › Alpena Power
Investor-owned utilityAlpena Power interconnection application
Alpena Power is an investor-owned utility serving 13,754 residential customers in Michigan (EIA-861, 2025). Applications: PDF + email (APC Interconnection Application emailed to APC Interconnection Coordinator (mrc@alpenapower.com)). Gridpol files Alpena Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Alpena Power’s official sources (see below). Verified 2026-11-13 from APC DER Interconnection Procedures (MPSC-approved) and alpenapower.com interconnection page. DG tariff credit terms not reviewed – see Customer Generated Electricity page.
Alpena Power at a glance
Alpena Power Co
TypeInvestor-owned utility
EIA utility ID392
Residential customers13,754 (EIA-861, 2025)
Net-metered residential customers12 (EIA-861, 2025)
Service territory4 counties in Michigan
How to applyPDF + email – APC Interconnection Application emailed to APC Interconnection Coordinator (mrc@alpenapower.com) · official link
Who submitsApplicant (customer or developer/installer) downloads the application and emails it; for Level 1-2 site control is shown by the site owner's signature and contact information on the application.
Export compensationNet billing – Michigan DG program
Review time (official)Receipt notice 13 business days; complete/conforming decision 20 business days; Fast Track initial review 20 business days (Level 1-2) after Accepted Date; agreement issued within 13 business days; applicant returns within 20; APC countersigns within 20; commissioning visit scheduled within 20 business days (Level 1); acceptance report 15 business days; written parallel-operation authorization within 15 business days.
Documents Alpena Power asks for
- Interconnection application formAPC Interconnection Application incl. expected annual kWh output (PVWatts or other approved model) Gridpol prepares this.
- Site plan / site layoutSite diagram Gridpol prepares this.
- Single-line diagram (one-line)1-line diagram per MI Rule 460.936; Level 1 no seal/signature required; Level 2-3 MI PE seal or signed by MI-licensed electrical contractor with license number; Level 4-5 MI PE seal Gridpol prepares this.
- Customer signatureSite owner signature/contact on application = site control for Level 1-2
- Interconnection agreementStandard Level 1/2/3 Interconnection Agreement, sign and return within 20 business days of receipt
- Final inspection sign-offAfter install: confirmation of approved electrical inspection by AHJ, as-built site and 1-line diagrams if changed, test reports
- Proof of insurance (when applicable)None for Level 1-2; Level 3 $1M GL, Level 4 $2M, Level 5 $3M with APC as additional insured
How the Alpena Power process runs
- Optional pre-application report ($300).
- Email APC Interconnection Application with site diagram, 1-line diagram, expected annual kWh and fee to mrc@alpenapower.com.
- APC confirms receipt (13 BD) and completeness/track (20 BD); fix deficiencies within 60 BD.
- Fast Track / Non-Export screens; APC sends standard Level 1-3 Interconnection Agreement; applicant signs and returns within 20 BD.
- Install; pass AHJ electrical inspection; notify APC with inspection confirmation and as-builts.
- APC witnesses commissioning tests and issues acceptance report.
- APC issues written Parallel Operation Authorization (permission to operate).
Fees
| Fee | Applies to | Note |
|---|---|---|
| $50 | Distributed Generation Program application fee | |
| $100 + $1/kWac | Fast Track or Non-Export Track initial review, certified DER | $100 + $2/kWac non-certified |
| $300 | Pre-application report / scoping meeting | Optional for Level 1-3 |
| up to $1,000 / $10,000 / $15,000 | Supplemental review / system impact study / facilities study | Actual cost up to cap |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | Certified, kWac |
| Level 2 | 150 kW | Certified |
| Level 3 | 550 kW | Or ≤150 kWac non-certified |
| Level 4 | 1000 kW | |
| Level 5 | >1 MWac |
MIXDG (Mich. Admin. Code R 460.901 ff.), APC procedures approved by MPSC Jan 23, 2025.
Storage, EV and stamps
Battery storage
Storage counts as DER (capacity in kW/kVA and kWh, AC/DC coupling stated on application). Storage may be used to limit export to meet a lower level. Legacy net metering customers may add storage charged only by existing generation and keep their 10-year grandfathering.
PE stamp
Level 2-3: MI PE seal or signature of MI-licensed electrical contractor on 1-line; Level 4-5: MI PE seal required. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Unverified annual generator output estimate may be rejected
- Incomplete or non-conforming application (written deficiency list; 60 business days to cure)
- Commissioning test report rejected or site unsatisfactory
Gridpol’s pre-submission check covers these before we file.
Sources
- Alpena Power Interconnection Process: https://www.alpenapower.com/interconnection-process/ (retrieved 2026-11-13)
- APC DER Interconnection Procedures: https://www.alpenapower.com/wp-content/uploads/2025/05/APC-DER-Interconnection-Procedures.pdf (retrieved 2026-11-13)
- APC Interconnection Application: https://www.alpenapower.com/wp-content/uploads/2025/01/APC-Interconnection-Application.pdf (retrieved 2026-11-13)
Other utilities in Michigan
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.