Consumers Energy interconnection application

Consumers Energy is an investor-owned utility serving 1,662,741 residential customers in Michigan (EIA-861, 2025). Applications: PowerClerk (Consumers Energy PowerClerk). Gridpol files Consumers Energy interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Consumers Energy’s official sources (see below). Exact step order to PTO and review timelines not confirmed; check interconnection procedures Level 1&2 PDF.

Consumers Energy at a glance

Utility

Consumers Energy Co (CMS Energy)

Type

Investor-owned utility

EIA utility ID

4254

Residential customers

1,662,741 (EIA-861, 2025)

Net-metered residential customers

12,024 (EIA-861, 2025)

Service territory

60 counties in Michigan

How to apply

PowerClerk – Consumers Energy PowerClerk · official link

Who submits

Applications online via PowerClerk; customer or installer. Customers with an Alternate Energy Provider must also apply to the AEP for Distributed Generation.

Export compensation

Net billing – Distributed Generation program
Michigan DG program (inflow/outflow).

Review time (official)

Per Michigan MIXDG rules (2023); no timeline stated on Consumers page.

Documents Consumers Energy asks for

  • Interconnection application formForm 1219 (Levels 1-3, <=550 kW), also DG program application Gridpol prepares this.
  • Site plan / site layoutPanels shown on site plan; panel quantity must be clear (exporting solar checklist) Gridpol prepares this.
  • Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
  • PV module spec sheetManufacturer data sheet of the modules.
  • Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
  • Battery spec sheet (when applicable)Battery systems have additional checklist requirements
  • Interconnection agreementForm 1216 operating agreement (<=550 kW)
  • Other utility-specific documentCommissioning Test Report Form 1739
  • Recent electric bill (when applicable)Account number must match billing records

How the Consumers Energy process runs

  1. Submit Form 1219 application with drawings and fee in PowerClerk.
  2. Technical review per exporting checklist.
  3. Sign operating agreement (Form 1216).
  4. Install; submit commissioning test report (Form 1739).
  5. Meter and approval to operate.

Fees

FeeApplies toNote
$50Distributed Generation program application reviewLegacy NEM/DG fee plus fast/study track fees capped at $50 total
$300 + $100 + $1/kWacNon-export / Fast Track certified (pre-application + application)
$100 + $2/kWacNon-certified equipment
$1,000Supplemental review (non-DG)

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 120 kW
Level 2150 kW
Level 3550 kW
Level 41000 kW
Level 5>1 MW

Levels by AC nameplate DER capacity including existing systems on site.

Storage, EV and stamps

Battery storage

Battery systems have additional requirements in the Level 1-3 technical review checklist; storage is DER under MIXDG rules.

Common issues the utility lists

  • Solar panels not shown on site plan / panel quantity unclear
  • Account number not matching billing records

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited