City of Holland is a municipal utility serving 27,007 residential customers in Michigan (EIA-861, 2025). Gridpol files City of Holland interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Michigan’s commission rule (Mich. Admin. Code R 460.901a - R 460.1016 (MIXDG: Interconnection and Distributed Generation Standards)) does not bind municipal utilitys; City of Holland sets its own interconnection policy. We confirm its form on the first project. Member-regulated cooperatives are covered by the interconnection rules (R 460.901a(v)). Municipal utilities are not covered and use their own policies.
City of Holland at a glance
City of Holland
TypeMunicipal utility
EIA utility ID8723
Residential customers27,007 (EIA-861, 2025)
Net-metered residential customers31 (EIA-861, 2025)
Service territory2 counties in Michigan
Documents City of Holland asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for City of Holland. We confirm City of Holland’s exact list on the first project.
Michigan interconnection rule
Michigan Public Service Commission
Interconnection ruleMich. Admin. Code R 460.901a - R 460.1016 (MIXDG: Interconnection and Distributed Generation Standards) – Michigan Interconnection and Distributed Generation Standards · source
Applies toRate-regulated electric utilities (IOUs and rate-regulated cooperatives), member-regulated cooperatives (for R 460.901a-460.992), and alternative electric suppliers; not municipal utilities
Application formUtility-specific interconnection application/procedures filed with MPSC per rule (online application allowed); Commission-approved standard Level 1-3 interconnection agreement (Case U-21543)
TimelinesAcknowledge receipt by end of 3rd business day; completeness determination within 10 business days; applicant 60 business days to cure (2 submissions), utility 10 BD per resubmission (R 460.936). Fast track initial review 10 BD (Levels 1-2) / 20 BD (Levels 3-5) (R 460.946). Facilities study 80 BD (R 460.962). DG-program customers must complete installation within 6 months of complete application (R 460.1006).
FeesPre-application report <=$300; non-export and fast track $100 + $1/kWac certified or $100 + $2/kWac non-certified; supplemental review <=$1,000; study scoping <=$300; SIS <=$10,000; facilities study <=$15,000 (R 460.926). DG program application fee <=$50 (R 460.1006).
InsuranceLevel 1 and 2: utility may not require additional liability insurance or being named additional insured. Minimum general liability: Level 3 $1,000,000; Level 4 $2,000,000; Level 5 $3,000,000 (R 460.986).
External disconnectNot found in reviewed rule sections; per utility interconnection procedures.
Export compensationNet billing – MCL 460.1173 et seq. (Distributed Generation Program); R 460.1001-460.1016
DG program (inflow/outflow billing) replaced legacy net metering; outflow credited at a rate below full retail set per utility. Category sizes/caps per statute; detail not verified here.
Member-regulated cooperatives are covered by the interconnection rules (R 460.901a(v)). Municipal utilities are not covered and use their own policies.
- R 460.901a Definitions A-I: https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-901a (retrieved 2026-11-13)
- R 460.901b Definitions J-Z (levels): https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-901b (retrieved 2026-11-13)
- R 460.926 Fees: https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-926 (retrieved 2026-11-13)
- R 460.936 Interconnection applications: https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-936 (retrieved 2026-11-13)
- R 460.946 Fast track initial review: https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-946 (retrieved 2026-11-13)
- R 460.1006 DG program application and fees: https://www.law.cornell.edu/regulations/michigan/Mich-Admin-Code-R-460-1006 (retrieved 2026-11-13)
- MPSC news release 2024-07-23: https://www.michigan.gov/mpsc/commission/news-releases/2024/07/23/mpsc-takes-next-steps-in-enabling-interconnection-and-distributed-energy-resources (retrieved 2026-11-13)
Other utilities in Michigan
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.