Public power districtCrisp County Power Comm interconnection application
Crisp County Power Comm is a public power district serving 9,210 residential customers in Georgia (EIA-861, 2025). Gridpol files Crisp County Power Comm interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Georgia’s commission rule (O.C.G.A. 46-3-50 to 46-3-56 (Georgia Cogeneration and Distributed Generation Act of 2001)) does not bind public power districts; Crisp County Power Comm sets its own interconnection policy. We confirm its form on the first project. EMCs and municipal utilities are covered by the Act; rates set by their governing bodies instead of PSC; each publishes own DG interconnection policy (e.g. Altamaha EMC, Carroll EMC, City of Cartersville).
Crisp County Power Comm at a glance
Crisp County Power Comm
TypePublic power district
EIA utility ID4538
Residential customers9,210 (EIA-861, 2025)
Net-metered residential customers6 (EIA-861, 2025)
Service territory5 counties in Georgia
Documents Crisp County Power Comm asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Crisp County Power Comm. We confirm Crisp County Power Comm’s exact list on the first project.
Georgia interconnection rule
Georgia Public Service Commission
Interconnection ruleO.C.G.A. 46-3-50 to 46-3-56 (Georgia Cogeneration and Distributed Generation Act of 2001) – Cogeneration and Distributed Generation · source
Applies toAll electric service providers: electric utilities (Georgia Power), electric membership corporations and municipal electric utilities (O.C.G.A. 46-3-52)
Application formNo statewide form; written agreement between provider and customer generator (46-3-54); each provider uses own interconnection application/agreement (e.g. Georgia Power DG Interconnection Guidelines, EMC DG policies)
TimelinesNo statutory or PSC review timelines found.
FeesFees limited to direct costs of interconnecting/administering metering; no standby, capacity, interconnection or other fees beyond monthly service charge unless customer agrees or commission/governing body approves (46-3-54).
InsuranceProvider may not require additional liability insurance from a facility meeting NEC, NESC, IEEE and UL requirements (46-3-56).
External disconnectNot addressed in statute; utility-specific (e.g. Georgia Power DG construction guidelines).
Export compensationUtility-specific – O.C.G.A. 46-3-55, 46-3-56
Bidirectional metering with excess credited at rate filed with commission; providers must buy first-come first-served until 0.2% of prior-year annual peak demand, at not more than avoided energy cost. Georgia Power offers monthly netting/buyback per PSC-approved tariffs.
EMCs and municipal utilities are covered by the Act; rates set by their governing bodies instead of PSC; each publishes own DG interconnection policy (e.g. Altamaha EMC, Carroll EMC, City of Cartersville).
- O.C.G.A. 46-3-52 Definitions: https://codes.findlaw.com/ga/title-46-public-utilities-and-public-transportation/ga-code-sect-46-3-52/ (retrieved 2026-11-13)
- O.C.G.A. 46-3-54: https://codes.findlaw.com/ga/title-46-public-utilities-and-public-transportation/ga-code-sect-46-3-54/ (retrieved 2026-11-13)
- O.C.G.A. 46-3-55: https://codes.findlaw.com/ga/title-46-public-utilities-and-public-transportation/ga-code-sect-46-3-55/ (retrieved 2026-11-13)
- O.C.G.A. 46-3-56: https://codes.findlaw.com/ga/title-46-public-utilities-and-public-transportation/ga-code-sect-46-3-56/ (retrieved 2026-11-13)
Other utilities in Georgia
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.