Home › Utilities › Georgia › Jackson EMC
Electric cooperativeJackson EMC interconnection application
Jackson EMC is an electric cooperative serving 245,849 residential customers in Georgia (EIA-861, 2025). Applications: PDF + mail (Interconnection Request (Application), Appendix B of DG Interconnection Procedure; mail with $100 fee to Jackson EMC, Attn: System Engineering, P.O. Box 38, Jefferson, GA 30549 (questions: interconnection@jacksonemc.com)). Gridpol files Jackson EMC interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Jackson EMC’s official sources (see below). jacksonemc.com blocks direct fetch; portal (paper application by U.S. mail), documents, fees and steps confirmed from archived official pages (2025 captures). Earlier 'online portal' claim not supported - none found. Minor gaps: confirm no change since 2025 capture; current avoided-cost credit value not published; Net Metering Rider read from 2023 capture.
Jackson EMC at a glance
Jackson Electric Member Corp
TypeElectric cooperative
EIA utility ID9601
Residential customers245,849 (EIA-861, 2025)
Net-metered residential customers1,253 (EIA-861, 2025)
Service territory12 counties in Georgia
How to applyPDF + mail – Interconnection Request (Application), Appendix B of DG Interconnection Procedure; mail with $100 fee to Jackson EMC, Attn: System Engineering, P.O. Box 38, Jefferson, GA 30549 (questions: interconnection@jacksonemc.com) · official link
Who submitsInterconnection Customer = Jackson EMC member (customer) who signs the application and DG Interconnection Agreement; application has a separate contact block (e.g. installer) if different. Third-party ownership only by special permission via Addendum. No LOA form published.
Export compensationNet billing – Net Metering Rider
Excess generation credited at avoided energy cost (base charge at generator + transmission and distribution line-loss avoided costs); credit balance applied to next bill; each December credit balance paid by check. $10/month incremental service cost. (Rider page via archive capture 2023-08-06.)
Receipt acknowledged within 3 business days; completeness notice within 10 business days; fast-track screens within 15 business days of complete request; executable agreement within 5 business days after approval; witness test within 10 business days of receiving Certificate of Completion (else deemed waived) (Procedure rev. Feb 22, 2023).
Documents Jackson EMC asks for
- Interconnection application formInterconnection Request (Application), Appendix B: customer/contact info, account no., prime mover, DC capacity, panel/inverter make-model-rating, battery make/kWh/kW, disconnect switch make/model/rating, certified components list, estimated install/in-service dates Gridpol prepares this.
- Single-line diagram (one-line)Detailed one-line diagram of proposed DG facility Gridpol prepares this.
- PV module spec sheetMajor equipment specifications (generators/panels, transformers, inverters, breakers, relays, disconnect switches)
- Inverter spec sheetInverter spec; if UL 1741 listed attach manufacturer cut-sheet showing listing. Non-certified inverters need PE certification of IEEE 1547 compliance
- UL 1741 / IEEE 1547 certification (when applicable)Cut-sheet showing UL 1741 listing (Certified Inverter = UL 1741/1741SA + IEEE 1547)
- Battery spec sheet (when applicable)Battery manufacturer, energy (kWh) and power (kW) on application if storage included
- Customer signatureInterconnection Customer certification signature on application
- Interconnection agreementDistributed Generation Facility Interconnection Agreement (Appendix C), executable after approval; must be signed before operating
- Final inspection sign-offCertificate of Completion from local electrical wiring inspector (or installer) returned to JEMC after installation
- Other utility-specific document (when applicable)Other drawings needed for interconnection design; relay settings for review; final design submission if Study Process
How the Jackson EMC process runs
- Review DG Interconnection Procedure; complete Interconnection Request with one-line diagram and equipment specs.
- Mail application with $100 processing fee to Jackson EMC System Engineering (P.O. Box 38, Jefferson, GA 30549); receipt acknowledged in 3 business days, completeness in 10 business days.
- Fast Track screening within 15 business days (certified inverter <=10 kW residential / <=100 kW commercial qualify); otherwise scoping meeting and Study Process with study fees, final design review.
- JEMC approves and provides executable DG Interconnection Agreement (within 5 business days); sign agreement and pay any interconnection costs.
- Install (design accepted by JEMC beforehand) with lockable visible-break disconnect accessible to JEMC; local electrical inspection.
- Return Certificate of Completion; JEMC witness test within 10 business days.
- JEMC written authorization for parallel operation; bidirectional meter installed.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Non-refundable application processing fee (all DG) | Sent with application by U.S. mail |
| $10.00/month | Net Metering Rider incremental service cost | MBS commercial customers case by case |
| per study | Study Process (>100 kW, non-certified, or failed fast-track screens) | Feasibility/system impact/facility study fees and interconnection costs identified at scoping meeting |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Fast Track - residential | 10 kW | Certified inverter-based |
| Fast Track - commercial | 100 kW | Certified inverter-based; larger/other systems via screens or Study Process |
| Procedure scope | 10000 kW | Procedure applies to generators < 10 MVA; monitoring/control may be required > 200 kW |
| Net metering cap | 10 kW |
Net Metering Rider: peak capacity <= 10 kW residential, <= 100 kW commercial (Georgia Cogeneration and DG Act); larger at cooperative's sole discretion. Storage capacity counts toward total DG capacity.
Storage, EV and stamps
Battery storage
DG definition includes energy storage; storage capacity is included in total DG capacity; application asks for battery manufacturer, kWh and kW. Interconnection Agreement 2.7: customer agrees not to increase capacity or add battery storage (after agreement) and not to change protection scheme without JEMC written permission.
PE stamp
Non-certified inverters must be certified by a professional engineer as compliant with IEEE 1547 and the procedure. – PE-stamped drawings are not included in Gridpol.
Common issues the utility lists
- Incomplete application (JEMC advises what material is missing)
- Failing fast-track screens (service transformer rating, 15% line-section minimum load, 10% fault current, 87.5% interrupting capability, 65% shared secondary, 20% 240 V imbalance, construction needed)
- Unsatisfactory witness test (JEMC states steps needed to pass)
Gridpol’s pre-submission check covers these before we file.
Sources
- Jackson EMC - Interconnection Agreement page (archive capture 2025-04-23): https://web.archive.org/web/20250423055255/https://www.jacksonemc.com/member-services/ev-and-renewable-energy/renewable-energy/commercial-onsite-solar (retrieved 2026-11-13)
- Jackson EMC Distributed Generation Interconnection Procedure, rev. Feb 22, 2023 (archive capture 2025-03-26): https://web.archive.org/web/20250326151729/https://www.jacksonemc.com/assets/uploads/pdfs/Interconnection-Procedure-Revised-Final.pdf (retrieved 2026-11-13)
- Jackson EMC - Rooftop Solar (archive capture 2025-10-03): https://web.archive.org/web/20251003043113/https://www.jacksonemc.com/member-services/ev-and-renewable-energy/renewable-energy/rooftop-solar (retrieved 2026-11-13)
- Jackson EMC - Net Metering Rider (archive capture 2023-08-06): https://web.archive.org/web/20230806143846/https://www.jacksonemc.com/my-cooperative/rates/residential-rates/net-metering-rider (retrieved 2026-11-13)
Other utilities in Georgia
- Georgia Power2,480,484
- Cobb EMC203,131
- Sawnee EMC182,849
- GreyStone Power142,841
- Walton EMC133,581
- Snapping Shoals El Member Corporation106,304
- North Georgia Electric Member Corporation90,932
- Flint Electric Membership Corporation85,358
- Coweta-Fayette El Member Corporation83,660
- Colquitt Electric Membership Corporation66,177
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.