Village of Merrillan interconnection application

Village of Merrillan is a municipal utility serving 414 customers in Wisconsin (EIA-861, 2025). Gridpol files Village of Merrillan interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Wisconsin’s interconnection rule (Wis. Admin. Code ch. PSC 119 (implements s. 196.496, Stats.)) applies to Village of Merrillan. Levels, timelines and documents below come from that rule; Village of Merrillan’s own form and portal are confirmed on the first project.

Village of Merrillan at a glance

Utility

Village of Merrillan

Type

Municipal utility

EIA utility ID

12336

Customers

414 (EIA-861, 2025, short form: all customer classes)

Net-metered residential customers

none reported

Service territory

1 county in Wisconsin

Documents Village of Merrillan asks for

  • Interconnection application formRequired by the state rule Gridpol prepares this.
  • Single-line diagram (one-line)Required by the state rule Gridpol prepares this.
  • Site plan / site layoutRequired by the state rule Gridpol prepares this.
  • Inverter spec sheetRequired by the state rule
  • UL 1741 / IEEE 1547 certificationRequired by the state rule
  • Interconnection agreementRequired by the state rule
  • Proof of insuranceRequired by the state rule

Documents required by the Wisconsin rule. Village of Merrillan may ask for more on its own form; we confirm on the first project.

Wisconsin interconnection rule

Commission

Public Service Commission of Wisconsin

Interconnection rule

Wis. Admin. Code ch. PSC 119 (implements s. 196.496, Stats.) – Rules for Interconnecting Distributed Generation Facilities · source

Applies to

All electric public utilities (investor-owned and municipal utilities, which are public utilities under ch. 196) for DG facilities <=15 MW on their distribution systems. Electric cooperatives are not public utilities under ch. 196 and are not covered.

Application form

Statewide standard forms: Form 6031 Wisconsin Standard Distributed Generation Application (+ technology supplements: solar PV, wind, energy storage, generator, change of ownership); Form 6029 Interconnection Agreement (<=20 kW), Form 6030 (20 kW-15 MW); pre-application Forms 6032/6033 (all dated 2024-05-01)

Timelines

Utility furnishes guidelines and standard form within 5 working days of request; completeness notice within 10 working days of application + fee; application review within 10 working days of completeness (if no engineering review needed, applicant may install); applicant has 15 working days to accept engineering review estimate; engineering review 10/15/20/40 working days for Cat. 1/2/3/4; distribution study 10/15/20 working days (Cat. 1-3). Modifications: advance notice 20/40/60 working days; utility response 20/40/60/60 working days or deemed approved.

Fees

Table PSC 119.08-1: Cat. 1 $150 (1-8 kW) or $300 (9-20 kW); Cat. 2 $300 + $10/kW; Cat. 3 $2,000 + $2/kW; Cat. 4 $4,000 + $0.50/kW; engineering review and distribution study cost-based; commissioning fee $150/$250/$1,000/$2,500. Utility may waive.

Insurance

Minimum liability insurance per occurrence: Cat. 1 $300,000; Cat. 2 $1,000,000; Cat. 3 $2,000,000; Cat. 4 negotiated. Cat. 2-4 must name the utility as additional insured. Alternative financial responsibility by mutual agreement.

External disconnect

Utility may require a lockable, visible-break interconnection disconnect switch opening all ungrounded poles, accessible at all times and labeled 'Interconnection Disconnect Switch' (PSC 119.20(3)-(4)); one-line diagram and site plan must show the switch location.

Export compensation

Utility-specific – No statewide net metering statute; PSC-approved parallel generation / net metering tariffs of each utility
PSC: net metering available to customers of investor-owned and municipal utilities below a utility-specific size threshold; buyback rates set in each utility's parallel generation tariff.

Not bound by the rule

Municipal utilities are bound by PSC 119 and file PSC-approved tariffs. Electric cooperatives are not PSC-regulated public utilities and set their own interconnection and net metering/buyback policies.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.