Home › Utilities › Wisconsin › We Energies
Investor-owned utilityWe Energies interconnection application
We Energies is an investor-owned utility serving 1,056,086 residential customers in Wisconsin (EIA-861, 2025). Applications: PDF + email (We Energies Central Group (customer-owned generation)). Gridpol files We Energies interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from We Energies’s official sources (see below). Category application fee amounts not stated on utility page; see PSC 119/Form 6031.
We Energies at a glance
Wisconsin Electric Power Co (WEC Energy Group)
TypeInvestor-owned utility
EIA utility ID20847
Residential customers1,056,086 (EIA-861, 2025)
Net-metered residential customers6,994 (EIA-861, 2025)
Service territory28 counties in Wisconsin
How to applyPDF + email – We Energies Central Group (customer-owned generation) · official link
Who submitsCustomer of record notifies the Company and submits the Wisconsin Standard DG Application (PSC Form 6031); installer may prepare it. Submit by email co-non-design-central@we-energies.com, mail (We Energies Central Group, PO Box 2046, Milwaukee WI 53201) or fax. Questions: customergen@we-energies.com.
Export compensationNet billing – CGS NM (net metered rate, <300 kW)
Monthly netting; excess credited at avoided energy cost ($0.03636/kWh flat from 1-1-2026)
Completeness notice within 10 working days; engineering-review determination within 10 working days (PSC 119).
Documents We Energies asks for
- Interconnection application formWisconsin Standard Distributed Generation Application Form 6031 (PSC) Gridpol prepares this.
- Other utility-specific documentSupplement form: Solar PV Form, Energy Storage Form, Wind, Generator, Micro-grid interconnect device as applicable
- Single-line diagram (one-line)Computer generated (no hand drawn), meets PSC 119.10; show max continuous output of each generator/ESS, existing vs new, backup generators, EV chargers incl. V2H; revision tracking Gridpol prepares this.
- Site plan / site layoutComputer generated, meets PSC 119.12; locations of generation, ESS, disconnects, meter Gridpol prepares this.
- Inverter spec sheetTechnical documents of generation equipment
- Battery spec sheet (when applicable)ESS must be UL 9540
- Photos (meter, main panel, equipment)Pictures of existing metering equipment, all sides, showing meter centerline height
- Proof of insuranceProof of liability insurance per PSC 119 category
- Other utility-specific documentWeatherproof onsite one-line posted near metering equipment
- Interconnection agreementDG Interconnection Agreement + Surplus Energy Agreement signed after commissioning
How the We Energies process runs
- Customer notifies We Energies
- Submit Form 6031 + supplements, SLD, site plan, specs, meter photos, insurance, fee
- Completeness review (10 working days); engineering review/study if required
- Pay any upgrade costs
- Install; AHJ inspection; disconnect left open until commissioning
- Company commissioning (anti-islanding, reconnect 5 min test); as-built if changes
- Sign Interconnection Agreement + Surplus Energy Agreement; written final acceptance = operate
Fees
| Fee | Applies to | Note |
|---|---|---|
| per PSC 119 category | Application review fee | amount not stated on page |
| $300 | Optional pre-application report | non-refundable |
| varies | Commissioning fee / engineering review | stated in notice |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Category 1 | 20 kW | PSC 119 |
| Category 2 | 200 kW | |
| Category 3 | 1000 kW | |
| Category 4 | 15000 kW | |
| Net metering cap | 300 kW |
Total single-phase generation at a site ≤150 kW; telemetry ≥300 kW
Storage, EV and stamps
Battery storage
ESS is customer-owned generation and needs the Energy Storage supplement form; UL 9540; no approved means to make ESS non-exporting yet – submit export-limiting design with test data for review. Contact Company for backup-only ESS / V2H systems.
EV chargers
EV chargers (incl. vehicle-to-home) must be shown on the one-line; service changes require a separate service change/modification/rewire application.
Common issues the utility lists
- Hand-drawn one-line or site plan not accepted
- One-line not distinguishing existing vs new equipment or missing EV chargers/backup gen
- Installed equipment differs from submitted documents (as-built required before operation)
- Existing metering/service code violations must be resolved
- Failed commissioning (islanding/reconnect test)
Gridpol’s pre-submission check covers these before we file.
Sources
- We Energies/WPS Customer-Owned Generation Manual 04/13/2026: https://www.we-energies.com/services/pdf/cog-manual.pdf (retrieved 2026-11-13)
- We Energies Systems 300 kW or less: https://www.we-energies.com/services/300kw-less-systems (retrieved 2026-11-13)
- We Energies CGS NM tariff: https://www.we-energies.com/pdfs/etariffs/wisconsin/cgs-nm.pdf (retrieved 2026-11-13)
- PSC Form 6031: https://psc.wi.gov/Documents/20240319_Form6031WisconsinStandardDistributedGenerationApplication.pdf (retrieved 2026-11-13)
Other utilities in Wisconsin
- Alliant Energy (Wisconsin)440,746
- Wisconsin Public Service (WPS)415,643
- Xcel Energy (Wisconsin/Michigan)222,746
- MGE148,482
- Adams-Columbia Electric Cooperative36,159
- Polk-Burnett Electric Cooperative20,584
- Barron Electric Cooperative19,395
- Riverland Energy Cooperative19,120
- Oakdale Electric Cooperative17,139
- Sun Prairie Utilities17,082
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.