Home › Utilities › Wisconsin › MGE

Investor-owned utility

MGE interconnection application

MGE is an investor-owned utility serving 148,482 residential customers in Wisconsin (EIA-861, 2025). Applications: PowerClerk (MGE DG PowerClerk). Gridpol files MGE interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from MGE’s official sources (see below).

MGE at a glance

Utility

Madison Gas & Electric Co (MGE Energy)

Type

Investor-owned utility

EIA utility ID

11479

Residential customers

148,482 (EIA-861, 2025)

Net-metered residential customers

2,677 (EIA-861, 2025)

Service territory

1 county in Wisconsin

How to apply

PowerClerk – MGE DG PowerClerk · official link

Who submits

Customer or installer; solar and/or storage ≤200 kW via PowerClerk; >200 kW and other technologies by email to mgeDGAdmin@mge.com. MGE advises contacting MGE early, before signing an installer contract.

Export compensation

NEM – Pg-2 Net Metering (≤100 kW)
Exports credited at same $/kWh as energy charges; Net Sellers (trailing 12 mo, after first year) paid buyback rate. Pg-1 >100 kW.

Review time (official)

Not stated on MGE page; PSC 119 timelines apply.

Documents MGE asks for

  • Interconnection application formWisconsin Standard DG Application Form 6031 Gridpol prepares this.
  • Other utility-specific documentSolar PV supplement and/or Energy Storage supplement
  • Single-line diagram (one-line)Line diagram (sample one-lines on MGE site) Gridpol prepares this.
  • Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
  • Inverter spec sheetSystem specifications
  • Proof of insuranceProof of insurance certificate
  • Photos (meter, main panel, equipment)Photo of electric meter showing clearances; proof-of-completion photos for ≤20 kW residential
  • Interconnection agreementE-signed in PowerClerk after commissioning (<200 kW solar/battery); Forms 6029/6030 otherwise

How the MGE process runs

  1. Gather materials (Form 6031, supplements, SLD, site plan, specs, insurance, meter photo)
  2. Submit in PowerClerk (≤200 kW solar/storage)
  3. Mail application fee check
  4. MGE approval → order/install equipment
  5. Commissioning: ≤20 kW residential solar/battery = MGE reviews proof-of-completion photos; others inspection/testing; pay commissioning fee
  6. E-sign Interconnection Agreement in PowerClerk after insurance verified
  7. Operate after receiving countersigned agreement (PTO)

Fees

FeeApplies toNote
$150 + $150 commissioningCategory 1, 1-8 kW exportCheck payable to MGE, installation address in memo, mail to Cash Processing PO Box 1231 Madison WI 53701-1231
$300 + $150 commissioningCategory 1, 9-20 kW
$300 + $10/kW; $250 commissioningCategory 2 >20-200 kW
$2,000 + $2/kW; $1,000 commissioningCategory 3 >200 kW-1 MW
$4,000 + $0.05/kW; $2,500 commissioningCategory 4 >1-15 MW

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Category 120 kWexternal lockable visible-break disconnect
Category 2200 kWwye-wye transformer required ≥50 kW
Category 31000 kWgross output monitoring
Category 415000 kW
Net metering cap100 kW

Downtown network: export prevented (MIR or <1/15 min daytime load)

Storage, EV and stamps

Battery storage

Storage ≤200 kW applies via PowerClerk with Energy Storage Supplement; same categories by export capacity.

Common issues the utility lists

  • Check without installation address in memo is returned
  • One check per installation address

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited