Home › Utilities › Wisconsin › Northwestern Wisconsin Electric Co (NWE)

Investor-owned utility

Northwestern Wisconsin Electric Co (NWE) interconnection application

Northwestern Wisconsin Electric Co (NWE) is an investor-owned utility serving 13,050 residential customers in Minnesota, Wisconsin (EIA-861, 2025). Applications: PDF + email (PSC Form 6031 + supplements + Form 6029/6030 submitted by installing contractor to NWE (contact form / DG contact)). Gridpol files Northwestern Wisconsin Electric Co (NWE) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Northwestern Wisconsin Electric Co (NWE)’s official sources (see below). Confirmed from nweco.com solar page, NWE tariffs and PSC forms. Open: PSC 119 review timelines (docs.legis.wisconsin.gov unreachable); MN service territory process not documented online.

Northwestern Wisconsin Electric Co (NWE) at a glance

Utility

Northwestern Wisconsin Elec Co

Type

Investor-owned utility

EIA utility ID

13815

Residential customers

13,050 (EIA-861, 2025)

Net-metered residential customers

97 (EIA-861, 2025)

Service territory

1 county in Minnesota, 2 counties in Wisconsin

How to apply

PDF + email – PSC Form 6031 + supplements + Form 6029/6030 submitted by installing contractor to NWE (contact form / DG contact) · official link

Who submits

NWE asks the customer's installing contractor to submit the Standard DG Application (Form 6031), fee and DG Interconnection Agreement; NWE notifies the contractor when PSC 119 requirements are met. Applicant on Form 6031 is the legally responsible person (owner/builder); designer/engineer also signs. PSC DG contact: John J. Richards, johnrichards@nweco.com, 715-463-1963.

Export compensation

Net billing – Pgs-1 Parallel Generation (20 kW or less) - Net Energy Billing; Pgs-2 Customer-Owned Generation (>20 kW)
Monthly netting; net excess credited at avoided cost (Net Generation Rate $0.0678/kWh eff. 12/5/2025). Systems before 4/19/2019 credited at retail until 4/8/2029. Credit >$50 refunded on request.

Review time (official)

Form 6029: utility testing completed within 10 working days after applicant notifies installation complete; revised applications approved/rejected within 20 working days. PSC 119 application review timelines not extracted (code site unreachable).

Documents Northwestern Wisconsin Electric Co (NWE) asks for

  • Interconnection application formPSC Form 6031 Wisconsin Standard DG Application (eff. 5/1/2024) Gridpol prepares this.
  • Other utility-specific documentTechnology supplement: Solar Photovoltaic Supplement (+ manufacturer data sheets); Energy Storage Supplement if battery
  • Single-line diagram (one-line)One-line diagram incl. disconnect, POI, meters, protection. NWE will not approve line-side taps from metering equipment or main breaker Gridpol prepares this.
  • Site plan / site layoutMajor equipment, service entrance, meters, DG and disconnect location, street address Gridpol prepares this.
  • Proof of insuranceProof of insurance: Cat 1 min $300,000; Cat 2+ name utility as additional insured; certificate with 30-day cancellation notice naming NWE as additional insured before agreement execution
  • UL 1741 / IEEE 1547 certificationProof of equipment certification (e.g. UL 1741) or PSC 119.27 compliance
  • Interconnection agreementPSC Form 6029 (≤20 kW) or 6030 (>20 kW-15 MW)
  • Final inspection sign-offWiring Affidavit signed by WI licensed master electrician (and certified inspector if municipality requires); from 1/1/2027 inspection by certified electrical inspector required before commissioning (SPS 316)
  • Other utility-specific document (when applicable)W-9 form (listed on NWE solar page, for buyback payments)

How the Northwestern Wisconsin Electric Co (NWE) process runs

  1. Review PSC 119; contact NWE (installing contractor) for forms
  2. Contractor submits Form 6031 + PV/storage supplements, one-line, site plan, proof of insurance, certification and fee
  3. NWE reviews per PSC 119 and notifies contractor when requirements are met; all fees paid before commissioning is scheduled
  4. Sign Form 6029/6030 interconnection agreement; install; submit wiring affidavit (inspection by certified inspector from 1/1/2027)
  5. Notify NWE installation complete; NWE commissioning test (within 10 working days) and net meter setup

Fees

FeeApplies toNote
$150 (1-8 kW) / $300 (9-20 kW) + $150 commissioningCategory 1 ≤20 kWPSC 119 Table 119.08-1; engineering/study cost-based
$300 + $10/kW + $250 commissioningCategory 2 >20-200 kWPSC 119 Table 119.08-1
$2,000 + $2/kW + $1,000 commissioningCategory 3 >200 kW-1 MWPSC 119 Table 119.08-1
$4,000 + $0.50/kW + $2,500 commissioningCategory 4 >1-15 MWPSC 119 Table 119.08-1

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Category 120 kWPSC 119, export capacity
Category 2200 kW
Category 31000 kW
Category 415000 kW
Net metering cap20 kW

Net energy billing (Pgs-1) for systems 20 kW or less; >20 kW under Pgs-2 avoided cost.

Storage, EV and stamps

Battery storage

PSC Energy Storage Supplement required (operating modes, export yes/no, grid charging yes/no, DC/AC coupled, transfer switch location). No NWE-specific storage rules found.

Common issues the utility lists

  • Line-side taps from metering equipment or main breaker on one-line diagram not approved

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.