Electric cooperativeDunn County Electric Cooperative interconnection application
Dunn County Electric Cooperative is an electric cooperative serving 9,542 residential customers in Wisconsin (EIA-861, 2025). Gridpol files Dunn County Electric Cooperative interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Wisconsin’s commission rule (Wis. Admin. Code ch. PSC 119 (implements s. 196.496, Stats.)) does not bind electric cooperatives; Dunn County Electric Cooperative sets its own interconnection policy. We confirm its form on the first project. Municipal utilities are bound by PSC 119 and file PSC-approved tariffs. Electric cooperatives are not PSC-regulated public utilities and set their own interconnection and net metering/buyback policies.
Dunn County Electric Cooperative at a glance
Dunn County Electric Coop
TypeElectric cooperative
EIA utility ID5417
Residential customers9,542 (EIA-861, 2025)
Net-metered residential customers157 (EIA-861, 2025)
Service territory6 counties in Wisconsin
Wholesale supplier / associationDairyland Power Cooperative
Documents Dunn County Electric Cooperative asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Dunn County Electric Cooperative. We confirm Dunn County Electric Cooperative’s exact list on the first project.
Wisconsin interconnection rule
Public Service Commission of Wisconsin
Interconnection ruleWis. Admin. Code ch. PSC 119 (implements s. 196.496, Stats.) – Rules for Interconnecting Distributed Generation Facilities · source
Applies toAll electric public utilities (investor-owned and municipal utilities, which are public utilities under ch. 196) for DG facilities <=15 MW on their distribution systems. Electric cooperatives are not public utilities under ch. 196 and are not covered.
Application formStatewide standard forms: Form 6031 Wisconsin Standard Distributed Generation Application (+ technology supplements: solar PV, wind, energy storage, generator, change of ownership); Form 6029 Interconnection Agreement (<=20 kW), Form 6030 (20 kW-15 MW); pre-application Forms 6032/6033 (all dated 2024-05-01)
TimelinesUtility furnishes guidelines and standard form within 5 working days of request; completeness notice within 10 working days of application + fee; application review within 10 working days of completeness (if no engineering review needed, applicant may install); applicant has 15 working days to accept engineering review estimate; engineering review 10/15/20/40 working days for Cat. 1/2/3/4; distribution study 10/15/20 working days (Cat. 1-3). Modifications: advance notice 20/40/60 working days; utility response 20/40/60/60 working days or deemed approved.
FeesTable PSC 119.08-1: Cat. 1 $150 (1-8 kW) or $300 (9-20 kW); Cat. 2 $300 + $10/kW; Cat. 3 $2,000 + $2/kW; Cat. 4 $4,000 + $0.50/kW; engineering review and distribution study cost-based; commissioning fee $150/$250/$1,000/$2,500. Utility may waive.
InsuranceMinimum liability insurance per occurrence: Cat. 1 $300,000; Cat. 2 $1,000,000; Cat. 3 $2,000,000; Cat. 4 negotiated. Cat. 2-4 must name the utility as additional insured. Alternative financial responsibility by mutual agreement.
External disconnectUtility may require a lockable, visible-break interconnection disconnect switch opening all ungrounded poles, accessible at all times and labeled 'Interconnection Disconnect Switch' (PSC 119.20(3)-(4)); one-line diagram and site plan must show the switch location.
Export compensationUtility-specific – No statewide net metering statute; PSC-approved parallel generation / net metering tariffs of each utility
PSC: net metering available to customers of investor-owned and municipal utilities below a utility-specific size threshold; buyback rates set in each utility's parallel generation tariff.
Municipal utilities are bound by PSC 119 and file PSC-approved tariffs. Electric cooperatives are not PSC-regulated public utilities and set their own interconnection and net metering/buyback policies.
- Wis. Admin. Code ch. PSC 119 (archive.org copy, Register Jan. 2025 No. 829): https://web.archive.org/web/20260113134928/https://docs.legis.wisconsin.gov/code/admin_code/psc/119.pdf (retrieved 2026-11-13)
- PSC of Wisconsin - Customer-Owned Generation (forms 6029-6033): https://psc.wi.gov/Pages/ForConsumers/MoreResources/CustomerOwnedGeneration.aspx (retrieved 2026-11-13)
Other utilities in Wisconsin
- We Energies1,056,086
- Alliant Energy (Wisconsin)440,746
- Wisconsin Public Service (WPS)415,643
- Xcel Energy (Wisconsin/Michigan)222,746
- MGE148,482
- Adams-Columbia Electric Cooperative36,159
- Polk-Burnett Electric Cooperative20,584
- Barron Electric Cooperative19,395
- Riverland Energy Cooperative19,120
- Oakdale Electric Cooperative17,139
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.