Home › Utilities › Washington › PUD No 1 of Grays Harbor County
Public power districtPUD No 1 of Grays Harbor County interconnection application
PUD No 1 of Grays Harbor County is a public power district serving 40,116 residential customers in Washington (EIA-861, 2025). Gridpol files PUD No 1 of Grays Harbor County interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Washington’s commission rule (WAC 480-108 (480-108-001 to -999)) does not bind public power districts; PUD No 1 of Grays Harbor County sets its own interconnection policy. We confirm its form on the first project. Consumer-owned utilities (PUDs, munis, coops) must offer net metering under RCW 80.60 (<=100 kW) and may adopt their own additional safety/power-quality/interconnection requirements by governing-body action after notice and comment (RCW 80.60.040(2)), but may not require extra standards, tests or liability insurance for compliant systems (80.60.040(3)).
PUD No 1 of Grays Harbor County at a glance
PUD No 1 of Grays Harbor County
TypePublic power district
EIA utility ID7548
Residential customers40,116 (EIA-861, 2025)
Net-metered residential customers343 (EIA-861, 2025)
Service territory5 counties in Washington
Documents PUD No 1 of Grays Harbor County asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for PUD No 1 of Grays Harbor County. We confirm PUD No 1 of Grays Harbor County’s exact list on the first project.
Washington interconnection rule
Washington Utilities and Transportation Commission (UTC)
Interconnection ruleWAC 480-108 (480-108-001 to -999) – Electric companies - Interconnection with electric generators · source
Applies toUTC-regulated electrical companies (investor-owned: PSE, Avista, PacifiCorp) for customer generating facilities up to 20 MW; excludes PURPA QFs under WAC 480-107. Not binding on PUDs, munis, coops.
Application formUtility-specific standard application form filed with the UTC and posted on the utility website, internet submission where practical (WAC 480-108-030(1)); must be signed and complete.
TimelinesReceipt notice 5 business days; completeness notice 10 business days; cure 15 business days (Tier 1-2) / 30 (Tier 3); Tier 1 decision 20 BD, Tier 2 30 BD; agreement with approval (Tier 1) or within 5 BD (Tier 2); operation within 1 year of approval (Tier 1-2). Completion requires certificate of completion with permits, electrical inspector approval; utility may witness test (WAC 480-108-050).
FeesNonrefundable application fee caps: $100 (0-25 kW), $500 (26-500 kW), $1,000 (>500 kW-20 MW) (WAC 480-108-030(5)).
InsuranceNo additional insurance necessary for generating facility under 100 kW (WAC 480-108-040(14)); RCW 80.60.040(3) bars utilities from requiring net-metering customers to buy additional liability insurance.
External disconnectTier 1: lockable disconnect not required for certified inverter systems on self-contained meter <=320 A unless L&I requires it (WAC 480-108-020(2)(a)(iv)). Tier 2: visible lockable AC disconnect required but utility may waive for inverter-based systems.
Export compensationNEM – RCW 80.60
Applies to all electric utilities incl. PUDs, munis, coops. Offer required until earlier of 2029-06-30 or 4% of utility's 1996 peak; utilities may then file successor tariff (UTC approval for IOUs).
Consumer-owned utilities (PUDs, munis, coops) must offer net metering under RCW 80.60 (<=100 kW) and may adopt their own additional safety/power-quality/interconnection requirements by governing-body action after notice and comment (RCW 80.60.040(2)), but may not require extra standards, tests or liability insurance for compliant systems (80.60.040(3)).
- WAC 480-108: https://app.leg.wa.gov/wac/default.aspx?cite=480-108&full=true (retrieved 2026-11-13)
- RCW 80.60 Net metering: https://app.leg.wa.gov/rcw/default.aspx?cite=80.60&full=true (retrieved 2026-11-13)
Other utilities in Washington
- Puget Sound Energy (PSE)1,104,338
- Seattle City Light472,309
- Snohomish County PUD349,905
- Avista Utilities247,159
- Clark Public Utilities223,119
- Tacoma Power (Tacoma Public Utilities)177,554
- Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA)114,998
- PUD No 1 of Benton County50,835
- PUD No 1 of Cowlitz County48,849
- PUD No 2 of Grant County43,160
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.