Home › Utilities › Utah › Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA)
Investor-owned utilityRocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) interconnection application
Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) is an investor-owned utility serving 1,867,246 residential customers in California, Idaho, Oregon, Utah, Washington, Wyoming (EIA-861, 2025). Applications: PowerClerk (PacifiCorp Net Metering / Customer Generation PowerClerk (all six states)). Gridpol files Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA)’s official sources (see below). Fees/size limits researched for Utah only; for OR/WA/CA/ID/WY projects check the state tariff linked on the customer generation page.
Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) at a glance
PacifiCorp (Berkshire Hathaway Energy)
TypeInvestor-owned utility
EIA utility ID14354
Residential customers1,867,246 (EIA-861, 2025)
Net-metered residential customers110,944 (EIA-861, 2025)
Service territory4 counties in California, 14 counties in Idaho, 25 counties in Oregon, 26 counties in Utah, 6 counties in Washington, 15 counties in Wyoming
How to applyPowerClerk – PacifiCorp Net Metering / Customer Generation PowerClerk (all six states) · official link
Who submitsOnline application by installer or customer ('Apply & review status'); customer signs electronic signature request after inspection. Utah net billing requires executed Interconnection Agreement for Net Billing Service.
Export compensationNet billing – Utah Schedule 137 Net Billing Service (Sch 135/136 closed)
Utah export credit 4.855 c/kWh Jun-Sep, 4.033 c/kWh Oct-May. ID Sch 136 net billing; OR/WA net metering; CA net billing tariff (NEM closed).
Typical timeline per PacifiCorp: some projects take longer than 70 business days depending on design/upgrades; meter installed 7-10 days after inspection upload and e-signature.
Documents Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) asks for
- Interconnection application formOnline Customer Generation application with proposed system Gridpol prepares this.
- Photos (meter, main panel, equipment)Picture of the meter with application; after install, photo of required safety signs/labels
- Single-line diagram (one-line)One-line drawing (PacifiCorp example provided) Gridpol prepares this.
- Site plan / site layoutSite plan (example provided) Gridpol prepares this.
- Other utility-specific document (when applicable)Meter-mounted device (MMD) form if MMD used (5-jaw meter mounts / ConnectDER '5' models not permitted); inverter settings per Policy 378; required labeling per examples; meter aggregation form if aggregating
- Final inspection sign-offUpload electrical inspection after installation
- Interconnection agreementElectronic signature request after inspection upload
How the Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA) process runs
- Choose installer; submit online application in PowerClerk incl. meter photo
- Wait for review and confirmation authorizing interconnection
- Get permits and install; do not energize
- Electrical inspection; upload inspection and photo of safety signs
- Sign electronic signature request (interconnection agreement)
- Meter installed within 7-10 days; utility notifies when system may be turned on
Fees
| Fee | Applies to | Note |
|---|---|---|
| $60 | Utah Level 1 interconnection review | Non-refundable, Schedule 137 / PSC Rule R746-312-13 |
| $75 + $1.50/kW | Utah Level 2 | |
| $150 + $3.00/kW | Utah Level 3 |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Utah Level 1/2/3 | Per Utah PSC R746-312 | |
| Net metering cap | 25 kW |
Utah Schedule 137: up to 25 kW residential, 2 MW non-residential. Other states follow their own net metering tariffs (OR net metering, WA tariff, CA NB tariff, ID Sch 136 net billing, WY tariff).
Storage, EV and stamps
Battery storage
Batteries are a listed eligible resource under UT Schedule 137. Wattsmart Batteries program offers incentives for utility-managed batteries paired with onsite solar. All inverter-based applications must use Policy 378 settings.
Common issues the utility lists
- Inverter settings not per Policy 378
- Non-approved meter-mounted devices (5-jaw meter mounts)
Gridpol’s pre-submission check covers these before we file.
Sources
- Rocky Mountain Power Customer Generation: https://www.rockymountainpower.net/savings-energy-choices/customer-generation.html (retrieved 2026-11-13)
- Pacific Power Customer Generation: https://www.pacificpower.net/savings-energy-choices/customer-generation.html (retrieved 2026-11-13)
- Rocky Mountain Power Utah Schedule 137 Net Billing Service: https://www.rockymountainpower.net/content/dam/pcorp/documents/en/rockymountainpower/rates-regulation/utah/rates/137_Net_Billing_Service.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.