Home › Utilities › Washington › Clark Public Utilities

Public power district

Clark Public Utilities interconnection application

Clark Public Utilities is a public power district serving 223,119 residential customers in Washington (EIA-861, 2025). Applications: PDF + email (Net Metering Interconnection Application & Agreement to netmetering@clarkpud.com (or mail to Energy Resources, Customer Generation, PO Box 8900, Vancouver WA 98668)). Gridpol files Clark Public Utilities interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Clark Public Utilities’s official sources (see below). Check 'Net metering program status' page (state cap) on first project.

Clark Public Utilities at a glance

Utility

PUD No 1 of Clark County

Type

Public power district

EIA utility ID

3660

Residential customers

223,119 (EIA-861, 2025)

Net-metered residential customers

3,220 (EIA-861, 2025)

Service territory

1 county in Washington

How to apply

PDF + email – Net Metering Interconnection Application & Agreement to netmetering@clarkpud.com (or mail to Energy Resources, Customer Generation, PO Box 8900, Vancouver WA 98668) · official link

Who submits

Customer (installer contact listed on application); customer signs application and Net Metering Agreement.

Export compensation

NEM – Net metering (RCW 80.60)
Excess stored as credit for future use.

Documents Clark Public Utilities asks for

  • Interconnection application formInterconnection Application (Rev 2/2021), signed Gridpol prepares this.
  • Net metering / net billing agreementSigned Net Metering Agreement
  • Single-line diagram (one-line)Electrical schematic drawing Gridpol prepares this.
  • Site plan / site layoutWith proposed meter location(s) Gridpol prepares this.
  • PV module spec sheetManufacturer cut sheets showing UL listing
  • Inverter spec sheetUL 1741 cut sheet
  • Battery spec sheet (when applicable)Battery only / backup: kW, kWh, type, cut sheet
  • Final inspection sign-offApproved WA L&I or City of Vancouver electrical inspection
  • Other utility-specific document (when applicable)Visible-break lockable disconnect if required; electrical permit number on application

How the Clark Public Utilities process runs

  1. Read customer generation interconnection standards; use net metering checklist
  2. Email signed application, NMA and documents
  3. Receive written design approval
  4. Pay fees on pre-bill (construction account number)
  5. Obtain L&I or City of Vancouver electrical permit; install system and meter socket(s)
  6. Pass electrical inspection
  7. Utility installs net meter and production meter; start generating

Fees

FeeApplies toNote
$100Tier 1, <= 25 kW (non-refundable processing)Paid after pre-bill
$500Tier 2, 26-100 kW
$250 + taxProduction meter, single phase <= 240 V$550 + tax for single phase >240 V or three phase

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Tier 125 kW
Tier 2100 kW26-100 kW require additional information and approval
Net metering cap100 kW

Storage, EV and stamps

Battery storage

Application covers battery-only and battery-backup systems (UPS-only or for use with renewable generation).

Common issues the utility lists

  • Meters not installed until utility is notified of approved electrical inspection

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited