Investor-owned utilityPuget Sound Energy (PSE) interconnection application
Puget Sound Energy (PSE) is an investor-owned utility serving 1,104,338 residential customers in Washington (EIA-861, 2025). Applications: PowerClerk (PSE Net Metering Interconnection Application Portal). Gridpol files Puget Sound Energy (PSE) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Puget Sound Energy (PSE)’s official sources (see below). Review timelines (WAC 480-108) not extracted; confirm on first project.
Puget Sound Energy (PSE) at a glance
Puget Sound Energy Inc (Puget Energy)
TypeInvestor-owned utility
EIA utility ID15500
Residential customers1,104,338 (EIA-861, 2025)
Net-metered residential customers26,979 (EIA-861, 2025)
Service territory8 counties in Washington
How to applyPowerClerk – PSE Net Metering Interconnection Application Portal · official link
Who submitsInstaller (PSE Recommended Energy Professional or other contractor) typically leads the process for the customer; Interconnection Customer is party to the agreement.
Export compensationNEM – Schedule 150 Net Metering
Excess generation credited and banked; banked credits expire March 31 each year per state law. Not combinable with TOU Schedules 307/327 or non-communicating meter Schedule 171.
Documents Puget Sound Energy (PSE) asks for
- Interconnection application formElectronic Application in PowerClerk (Schedule 150 process for UL 1741 SB inverter systems <=100 kW AC incl. batteries); paper Attachment B (Tier 1) / C (Tier 2-3) otherwise Gridpol prepares this.
- Single-line diagram (one-line)System schematic per PSE System Diagram Guide; must be approved before installation Gridpol prepares this.
- UL 1741 / IEEE 1547 certificationUL 1741 (SB for electronic process) inverter
- Interconnection agreementTier 1 Interconnection Agreement (Attachment I) / Tier 2-3 (Attachment J)
- Final inspection sign-offNotice of Completion / Certificate of Completion (completed in portal) after electrical permit finaled
How the Puget Sound Energy (PSE) process runs
- Select installer
- Submit interconnection application in PowerClerk
- PSE review; Approval to Construct (applications and schematics must be approved before installation)
- Install per local codes and permits
- Submit Notice of Completion after electrical permit is finalized
- PSE inspects/tests and installs required meters
- PSE issues approval to energize and starts net metering
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Net metering 0-100 kW with UL 1741 inverter via electronic process | Schedule 152 6.c |
| $100 | 0-25 kW not net metered | |
| $500 | >25-500 kW not qualified for Schedule 150 | |
| $1,000 | >500 kW - 20 MW | |
| $300 | Pre-application site assessment |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Tier 1 | 25 kW | UL 1741 inverter, single-phase, secondary voltage, no upgrades, 15% line-section screen |
| Tier 2 | 500 kW | <=38 kV distribution |
| Tier 3 | 20000 kW | |
| Net metering cap | 100 kW |
Interconnected capacity includes aggregated nameplate plus energy storage capacity (Schedule 152, WAC 480-108).
Storage, EV and stamps
Battery storage
Batteries count toward interconnected capacity; electronic process allowed when combined generation + batteries <= 100 kW AC with UL 1741 SB inverters. Storage-only systems operating in parallel are not covered by the net metering process (Distributed Renewables / Energy Advisor).
Sources
- PSE Customer Connected Solar / Net Metering: https://www.pse.com/en/green-options/Renewable-Energy-Programs/customer-connected-solar (retrieved 2026-11-13)
- PSE Schedule 152 Interconnection with Electric Generators (eff. 2026-09-01): https://www.pse.com/-/media/Project/PSE/Portal/Rate-documents/Electric/elec_sch_152.pdf (retrieved 2026-11-13)
Other utilities in Washington
- Seattle City Light472,309
- Snohomish County PUD349,905
- Avista Utilities247,159
- Clark Public Utilities223,119
- Tacoma Power (Tacoma Public Utilities)177,554
- Rocky Mountain Power (UT, ID, WY) / Pacific Power (OR, WA, CA)114,998
- PUD No 1 of Benton County50,835
- PUD No 1 of Cowlitz County48,849
- PUD No 2 of Grant County43,160
- PUD No 1 of Chelan County42,571
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.