Home › Utilities › Virginia › Northern Neck Electric Cooperative, Inc.
Electric cooperativeNorthern Neck Electric Cooperative, Inc. interconnection application
Northern Neck Electric Cooperative, Inc. is an electric cooperative serving 18,199 residential customers in Virginia (EIA-861, 2025). Gridpol files Northern Neck Electric Cooperative, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Virginia’s interconnection rule (20VAC5-315 (Regulations Governing Net Energy Metering, incl. interconnection of net metering facilities); 20VAC5-314 (Interconnection of Small Electrical Generators and Storage, for non-net-metered)) applies to Northern Neck Electric Cooperative, Inc.. Levels, timelines and documents below come from that rule; Northern Neck Electric Cooperative, Inc.’s own form and portal are confirmed on the first project.
Northern Neck Electric Cooperative, Inc. at a glance
Northern Neck Elec Coop, Inc
TypeElectric cooperative
EIA utility ID13762
Residential customers18,199 (EIA-861, 2025)
Net-metered residential customers323 (EIA-861, 2025)
Service territory6 counties in Virginia
Wholesale supplier / associationOld Dominion Electric Cooperative · Virginia SCC Regulations Governing Net Energy Metering, 20VAC5-315 (state rule; not published by ODEC)
Documents Northern Neck Electric Cooperative, Inc. asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Customer signatureRequired by the state rule
- Final inspection sign-offRequired by the state rule
- UL 1741 / IEEE 1547 certificationRequired by the state rule
- Net metering / net billing agreementRequired by the state rule
Documents required by the Virginia rule. Northern Neck Electric Cooperative, Inc. may ask for more on its own form; we confirm on the first project.
Virginia interconnection rule
Virginia State Corporation Commission
Interconnection rule20VAC5-315 (Regulations Governing Net Energy Metering, incl. interconnection of net metering facilities); 20VAC5-314 (Interconnection of Small Electrical Generators and Storage, for non-net-metered) – Regulations Governing Net Energy Metering · source
Applies toElectric distribution companies: investor-owned (Dominion, Appalachian Power) and electric cooperatives; 20VAC5-314 does not apply to net metering customers (they follow 20VAC5-315)
Application formCommission-approved net metering notification form (or identical utility electronic system) signed by customer, licensed electrician and vendor (20VAC5-315-30/40); non-NEM: Level 1 Interconnection Request Form (Schedule 5) <=500 kW
TimelinesNet metering: residential customer must notify before construction and get approval before interconnecting; utility has 30 days (nonresidential 60 days) from notification (third day after mailing) to determine compliance (20VAC5-315-30).
FeesNet metering: no application fee in rule; up to $50 per generator for inverter-settings inspection (>10 kW) or protective settings inspection; standby charges only for Phase II utility residential >15 kW (20VAC5-315-40/50).
InsuranceNet metering: <=10 kW at least $100,000 liability (homeowners/commercial); >10 kW at least $300,000; no higher limits or additional policies may be required (20VAC5-315-60). Non-NEM (314-160): $100k <=10 kW, $300k <=500 kW, $2M >500 kW.
External disconnectLockable, utility-accessible, load-breaking manual disconnect switch only if required by the utility's tariff; electrician certifies installation on the notification form (20VAC5-315-40 A 2-3).
Export compensationNEM – Va. Code 56-594, 56-594.01, 56-594.2; 20VAC5-315
Monthly netting at retail rate under same tariff as non-NEM customers; 12-month net metering period. Recent SCC proceedings revising Dominion/APCo net metering not verified here.
Electric cooperatives are covered (20 kW residential / 1 MW nonresidential). Municipal utilities are not SCC-regulated and set their own policies.
- 20VAC5-315 Regulations Governing Net Energy Metering (full text): https://law.lis.virginia.gov/admincodefull/title20/agency5/chapter315 (retrieved 2026-11-13)
- 20VAC5-314 Interconnection of Small Electrical Generators and Storage (full text): https://law.lis.virginia.gov/admincodefull/title20/agency5/chapter314 (retrieved 2026-11-13)
Other utilities in Virginia
- Dominion Energy Virginia / Dominion Energy North Carolina2,408,901
- Appalachian Power (APCo)467,581
- Rappahannock Electric Cooperative (REC)172,883
- NOVEC169,027
- Shenandoah Valley Electric Cooperative86,656
- Southside Electric Cooperative, Inc.57,305
- City of Danville38,226
- Central Virginia Electric Cooperative35,353
- A & N Electric Cooperative33,035
- Mecklenburg Electric Cooperative30,077
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.