Investor-owned utilityDominion Energy Virginia / Dominion Energy North Carolina interconnection application
Dominion Energy Virginia / Dominion Energy North Carolina is an investor-owned utility serving 2,517,958 residential customers in North Carolina, Virginia, West Virginia (EIA-861, 2025). Applications: Own online portal (Dominion Energy Net Metering Customer Self-Service Portal (online NMIN form, Salesforce)). Gridpol files Dominion Energy Virginia / Dominion Energy North Carolina interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Dominion Energy Virginia / Dominion Energy North Carolina’s official sources (see below). VA portal, steps and signatures confirmed on Dominion pages. Not verified: NC net metering rider details, WV process (small WV footprint), exact NMIN attachment list (SCC form PDF geo-blocked).
Dominion Energy Virginia / Dominion Energy North Carolina at a glance
Virginia Electric & Power Co (Dominion Energy)
TypeInvestor-owned utility
EIA utility ID19876
Residential customers2,517,958 (EIA-861, 2025)
Net-metered residential customers55,340 (EIA-861, 2025)
Service territory25 counties in North Carolina, 103 counties in Virginia, 2 counties in West Virginia
How to applyOwn online portal – Dominion Energy Net Metering Customer Self-Service Portal (online NMIN form, Salesforce) · official link
Who submitsVA: customer and vendor (installer) - vendor selected in NMIN Section 4 ('Vendor same as applicant' for self-installers); new vendors request portal setup via net.metering@dominionenergy.com. Both vendor and customer e-sign the NMIN (Adobe Sign). NC: Interconnection Customer signs NCIP form; submitted by mail/email to Generator Interconnections.
Export compensationNEM – VA Net Metering (20VAC5-315, Terms & Conditions Sec. XXIV-type net metering provisions); compatible rates Schedules 1, 1S, 1G, GS-1..GS-4, 6TS
Monthly excess carried forward; optional PPA pays net excess at end of 12-month period at PJM DOM zone day-ahead annual average LMP. NC: Dominion NC net metering on compatible schedules (1, 1P, 1T, 5C, 5P) - NC tariff details not verified.
VA rule 20VAC5-315-30: residential - utility has 30 days from notification to determine compliance; customer may interconnect on day 31 unless utility requests a waiver; non-residential 60/61 days. Notification date = 3rd day after mailing. NC: NCIP timelines (completeness 10 business days, 20 kW screening 15 business days, witness test 10 business days).
Documents Dominion Energy Virginia / Dominion Energy North Carolina asks for
- Interconnection application formVA: Net Metering Interconnection Notification (NMIN, SCC form) online, or PDF Sections 1-4 by email (net.metering@dominionenergy.com) or USPS. NC: NCIP Attachment 6 (<=20 kW certified inverter) or Attachment 2 (all other). Gridpol prepares this.
- Customer signatureCustomer and vendor Adobe Sign signatures required before contingent approval (VA)
- Proof of insuranceLiability insurance >= $100,000 for <=10 kW AC; >= $300,000 for >10 kW AC (20VAC5-315-60)
- UL 1741 / IEEE 1547 certificationVendor certifies on the NMIN form that the generator complies with UL/IEEE 1547 (20VAC5-315-40 A 4)
- Final inspection sign-offLicensed electrician certifies on the SCC notification form (NMIN) that installation meets NEC/manufacturer specs, or signed final electrical inspection if installed by customer or Class A/B contractor (20VAC5-315-40 A 3)
- Other utility-specific document (when applicable)Non-residential VA applications: Section 3 facility data and uploads required; residential: no Section 3 uploads. Generator DC/AC kW and battery backup yes/no entered online.
- Single-line diagram (one-line) (when applicable)NC: one-line diagram, site plan, inverter spec sheets and site control letter required per NCIP 1.5.1 Gridpol prepares this.
- Site plan / site layout (when applicable)NC only (NCIP 1.5.1.4) Gridpol prepares this.
- Inverter spec sheet (when applicable)NC only (NCIP 1.5.1.6)
How the Dominion Energy Virginia / Dominion Energy North Carolina process runs
- Apply: submit NMIN online via Self-Service Portal (fastest), or PDF by email/USPS; customer and vendor get request ID by email.
- Contingent approval review of grid compatibility; Adobe Sign emails to vendor then customer - process stops until both sign; contingent approval email sent.
- Install; bi-directional meter installed after contingent approval.
- Status 'Awaiting Electrical Inspection': vendor/self-installer logs into portal, completes NMIN Section 5 (licensed VA electrician certification) and/or uploads passed inspection.
- Metering and billing work completed; Permission To Operate (PTO) email to vendor and customer; status 'Permission to Operate Sent'.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 typical | VA small residential net metering | Dominion FAQ: often no charges for small residential systems; inverter settings inspection fee up to $50 per generator for >10 kW AC allowed by 20VAC5-315-40; upgrade costs paid by customer |
| $200 | NC <=20 kW (NCIP Attachment 6) | Non-refundable; Fast Track $750 (>20-100 kW) / $1,000 (>100 kW-2 MW) |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| VA residential net metering | 25 kW | IOU residential limit 25 kW AC; standby charge applies on Schedules 1/1S/1G above 20 kW AC |
| VA non-residential net metering | 3000 kW | 3 MW |
| NC 20 kW Inverter Process | 20 kW | NCIP |
| Net metering cap | 25 kW |
VA: system must not reasonably produce more than 150% of expected annual consumption (Dominion is a Phase II utility); VA program cap 6% of peak (5% all + 1% low-income). NC: residential <=20 kW, non-res <=1 MW.
Storage, EV and stamps
Battery storage
Batteries may be part of a renewable generation system but do not qualify as a renewable source by themselves (Dominion FAQ). Online NMIN asks 'Battery Backup Yes/No'. Interconnections must follow Dominion Blue Book and Net Metering/DER Interconnection Parameters Manual (approved disconnects).
Common issues the utility lists
- Application cannot proceed until both vendor and customer Adobe Sign signatures are received
- System sized above 150% of expected annual consumption
- Generator interconnected inside meter cabinet/CT compartment without prior approval
- Rate schedule not net-metering compatible (e.g. some TOU schedules)
Gridpol’s pre-submission check covers these before we file.
Sources
- Dominion Energy Virginia - Net Metering: https://www.dominionenergy.com/virginia/renewable-energy-programs/net-metering (retrieved 2026-11-13)
- Dominion VA Net Metering Self-Service Portal How-To Guide: https://cdn-dominionenergy-prd-001.azureedge.net/-/media/content/renewable-energy-programs/net-metering/pdfs/virginia/net-metering-self-service-portal-how-to-guide-va.pdf (retrieved 2026-11-13)
- Dominion Energy NC - Parallel Generation & Interconnection: https://www.dominionenergy.com/north-carolina/large-business-services/using-our-facilities/parallel-generation-and-interconnection (retrieved 2026-11-13)
- North Carolina Interconnection Procedures (Dominion copy): https://cdn-dominionenergy-prd-001.azureedge.net/-/media/content/large-business-services/pdfs/north-carolina/large-business/parallel-generation-and-interconnection/pdfs/north-carolina-interconnection-procedures-eff.pdf (retrieved 2026-11-13)
- 20VAC5-315-30 Company notification (VA SCC net metering rules): https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section30/ (retrieved 2026-11-13)
- 20VAC5-315-40 Conditions of interconnection: https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section40/ (retrieved 2026-11-13)
- 20VAC5-315-60 Liability insurance: https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section60/ (retrieved 2026-11-13)
- 20VAC5-315-20 Definitions (size limits): https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section20/ (retrieved 2026-11-13)
Other utilities in Virginia
- Appalachian Power (APCo)467,581
- Rappahannock Electric Cooperative (REC)172,883
- NOVEC169,027
- Shenandoah Valley Electric Cooperative86,656
- Southside Electric Cooperative, Inc.57,305
- City of Danville38,226
- Central Virginia Electric Cooperative35,353
- A & N Electric Cooperative33,035
- Mecklenburg Electric Cooperative30,077
- KU22,759
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.