Home › Utilities › Virginia › Appalachian Power (APCo)
Investor-owned utilityAppalachian Power (APCo) interconnection application
Appalachian Power (APCo) is an investor-owned utility serving 815,235 residential customers in Virginia, West Virginia (EIA-861, 2025). Applications: PowerClerk (AEP PowerClerk). Gridpol files Appalachian Power (APCo) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Appalachian Power (APCo)’s official sources (see below). VA process verified from APCo package. Not verified: WV process details, storage-specific rules (TIIR), current PowerClerk program names.
Appalachian Power (APCo) at a glance
Appalachian Power Co (American Electric Power (AEP))
TypeInvestor-owned utility
EIA utility ID733
Residential customers815,235 (EIA-861, 2025)
Net-metered residential customers9,078 (EIA-861, 2025)
Service territory31 counties in Virginia, 21 counties in West Virginia
How to applyPowerClerk – AEP PowerClerk · official link
Who submitsProspective net metering customer submits Form NMIN (directly, by mail/email or online in PowerClerk); vendor signs to certify UL1741 inverter; licensed electrician signs installation certification (or signed final electrical inspection). Installers commonly submit in PowerClerk on the customer's behalf (not explicitly stated).
Export compensationNEM – VA Optional Rider N.M.S. (Net Metering Service Rider), VA SCC Tariff
Excess generation carried forward as kWh credit; optional PPA pays end-of-period excess at PJM AEP Zone day-ahead annual average LMP.
Customer may interconnect 31 days (residential) / 61 days (non-residential) after final notification unless APCo requests a waiver (Rider N.M.S. / 20VAC5-315-30). APCo web: most residential <30 days; commercial or >10 kW up to 60 days.
Documents Appalachian Power (APCo) asks for
- Interconnection application formSCC Form NMIN (2 pages): Sections 1-4 before purchase commitment for preliminary approval; fully completed form re-submitted after installation for final field review Gridpol prepares this.
- Customer signatureAll sections requiring Company review, including signatures, must be complete for notification to be valid
- Single-line diagram (one-line)One-line diagram Gridpol prepares this.
- Site plan / site layoutSketch layout Gridpol prepares this.
- Proof of insuranceEvidence of liability insurance per 20VAC5-315-60 ($100k <=10 kW AC; $300k >10 kW AC)
- UL 1741 / IEEE 1547 certificationInverter vendor signs NMIN certifying UL1741 compliance; inverters must be UL1741 SB and IEEE 1547-2018 compliant
- Final inspection sign-offLicensed electrician signature on NMIN, or signed final electrical inspection report from local inspection department
- Other utility-specific document (when applicable)$50 inspection fee for non-inverter systems or inverter systems >10 kW AC, submitted with Sections 1-4
How the Appalachian Power (APCo) process runs
- Submit Form NMIN Sections 1-4 (+ one-line, sketch, insurance, any $50 fee) by email/mail or aep.powerclerk.com before committing to purchase; receive preliminary approval.
- Install system with labeled, lockable, load-break disconnect outside near meter; keep generator OFF.
- Re-submit fully completed NMIN with licensed electrician signature (or signed final electrical inspection) and vendor UL1741 certification.
- APCo final field verification/review; inverter settings inspection for >10 kW AC.
- Meter exchange; operate only after APCo completes final review and meter is exchanged.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $50 | Per generator: inverter-based >10 kW AC or non-inverter based (settings inspection) | Rider N.M.S. Facilities Charges |
| $0 | Inverter-based <=10 kW AC | No application fee stated |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Residential net metering | 25 kW | 25 kW AC |
| Commercial net metering | 3000 kW | 3 MW AC |
| Net metering cap | 25 kW |
Generator annual output limited to previous 12 months' consumption (100%; APCo is a Phase I utility). WV: separate WV net metering guide/interconnection procedures - not reviewed.
Storage, EV and stamps
Battery storage
Not addressed in the VA customer package; inverters must meet AEP Technical Interconnection and Interoperability Requirements (TIIR).
Common issues the utility lists
- Notification invalid if any section requiring Company review or any signature is missing (Rider N.M.S. A.1)
- Generator sized above previous 12 months' consumption
Gridpol’s pre-submission check covers these before we file.
Sources
- APCo Virginia Net Metering Service Customer Information Package (Jan 17, 2024) incl. Rider N.M.S.: https://www.appalachianpower.com/lib/docs/business/builders/VANetMeteringPackage2024.pdf (retrieved 2026-11-13)
- 20VAC5-315-30 Company notification (VA SCC net metering rules): https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section30/ (retrieved 2026-11-13)
- 20VAC5-315-40 Conditions of interconnection: https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section40/ (retrieved 2026-11-13)
- 20VAC5-315-60 Liability insurance: https://law.lis.virginia.gov/admincode/title20/agency5/chapter315/section60/ (retrieved 2026-11-13)
Other utilities in Virginia
- Dominion Energy Virginia / Dominion Energy North Carolina2,408,901
- Rappahannock Electric Cooperative (REC)172,883
- NOVEC169,027
- Shenandoah Valley Electric Cooperative86,656
- Southside Electric Cooperative, Inc.57,305
- City of Danville38,226
- Central Virginia Electric Cooperative35,353
- A & N Electric Cooperative33,035
- Mecklenburg Electric Cooperative30,077
- KU22,759
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.