Home › Utilities › Texas › TNMP
Investor-owned utilityTNMP interconnection application
TNMP is an investor-owned utility serving 237,930 residential customers in Texas (EIA-861, 2025). Applications: PowerClerk (TNMP DG Portal (PowerClerk)). Gridpol files TNMP interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from TNMP’s official sources (see below). Portal, documents, steps and PTO checklist confirmed from TNMP pages. TNMP tariff PDF (pre-interconnection study fee schedule) could not be located on tnmp.com - study fees unknown; verify in TNMP Tariff for Retail Delivery Service. Contact Vincent Herrera 972-353-5008.
TNMP at a glance
Texas-New Mexico Power Co (TXNM Energy)
TypeInvestor-owned utility
EIA utility ID40051
Residential customers237,930 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory42 counties in Texas
How to applyPowerClerk – TNMP DG Portal (PowerClerk) · official link
Who submitsInstaller submits the DG application via the TNMP DG Portal; customer then receives a PowerClerk 'Customer Confirmation' email and must affirm the installer is authorized to submit on their behalf and the information is correct before Application Review starts.
Review time (official)Load profile revised to DG status 30-45 days after DG meter installation. 16 TAC §25.211(m): interconnection within 4 weeks of receipt of a completed application for pre-certified equipment, 6 weeks for other facilities (longer if substantial capital upgrades). §25.211(g)/(i): pre-interconnection studies max 4 weeks.
Documents TNMP asks for
- Interconnection application formDG application in PowerClerk with equipment tab (manufacturer, model, quantity, voltages) Gridpol prepares this.
- Single-line diagram (one-line)One-line: service address, ESI ID, TNMP meter number, all equipment labeled, VLLD written out, VLLD-meter distance in feet; 1 page (2 if placards), flattened PDF < 2 MB Gridpol prepares this.
- Site plan / site layoutLayout sketch/site plan: ESI ID, TNMP meter number and location, AC disconnect location, North arrow; Google Earth/bird's-eye OK as PDF Gridpol prepares this.
- Inverter spec sheetSpecification of the proposed inverter
- Customer signatureCustomer email confirmation in PowerClerk + signed Interconnection Agreement
- Interconnection agreementSent by TNMP to customer after review/study
- Other utility-specific documentPlacard proofs (Class 1 within 10 ft; Class 2/3 otherwise); Notice of Installation form and Inspection Form in PowerClerk
- Photos (meter, main panel, equipment)5-photo limit: full PV array (countable), system overview meter-VLLD-panel, meter+VLLD locations if >10 ft, TNMP meter close-up with labels, inverter(s)
- Final inspection sign-off (when applicable)Installer records completion of local city/county inspection if required
How the TNMP process runs
- Installer submits DG application, site plan, one-line and inverter specification via TNMP DG Portal (PowerClerk).
- Customer affirms via Customer Confirmation email that installer is authorized and information is correct.
- TNMP reviews application and performs study.
- TNMP sends Interconnection Agreement; customer returns it signed.
- TNMP issues Letter of No Objection approving installation.
- Installer submits Notice of Installation/Notification of Completion and Inspection Form with photos (and local inspection if required).
- TNMP may inspect/test (TNMP's option); corrections returned to installer.
- TNMP installs DG meter ($227 meter change fee) = Permission to Operate; automated email to applicant.
- TNMP revises load profile (30-45 days after meter); REP handles any buyback.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $227 | DG meter change fee | Charged to customer for TNMP DG meter (TNMP Interconnecting page) |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|
No TNMP-specific thresholds found; §25.211 applies (fee-exempt pre-certified ≤500 kW radial meeting 15%/25% screens; DG ≤10 MW <60 kV). Separate transmission interconnection PowerClerk portal for large projects.
Storage, EV and stamps
Battery storage
Batteries listed as DG equipment and must appear on layout sketch and one-line; single VLLD (external handle, lockable; molded-case breaker not acceptable) between TNMP meter and ALL DG sources. No further battery-specific rules found.
Common issues the utility lists
- Photos not showing current NEC labeling (dual source, AC disconnect, rapid shutdown, nominal voltage, layout placard)
- Installation not matching one-line/layout sketch (upload corrected drawings)
- AC disconnect without physical handle, not labeled, or not open at inspection
- AC disconnect > 10 ft from meter without site-map placards at disconnect and meter
- Line and load crossed at meter box
- Service entrance inside covered patio/enclosed area
- Meter can/service riser condition (customer responsibility)
- Unsuitable/insufficient photo quality
Gridpol’s pre-submission check covers these before we file.
Sources
- TNMP - Interconnecting: https://www.tnmp.com/customers/interconnecting (retrieved 2026-11-13)
- TNMP DG Permission to Operate Guidelines for Installers: https://www.tnmp.com/sites/default/files/TNMP%20DG%20Permission%20to%20Operate%20Guidelines%20for%20Installers.pdf (retrieved 2026-11-13)
- TNMP Small Commercial and Residential Project Requirements: https://www.tnmp.com/sites/default/files/TNMP%20Small%20Commercial%20and%20Residential%20Project%20Requirements.pdf (retrieved 2026-11-13)
- 16 TAC §25.211 Interconnection of On-Site Distributed Generation (LII reprint of Texas Administrative Code; PUCT site puc.texas.gov returns HTTP 403 to this server): https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-211 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.