Home › Utilities › Texas › Austin Energy

Municipal utility

Austin Energy interconnection application

Austin Energy is a municipal utility serving 522,446 residential customers in Texas (EIA-861, 2025). Applications: PDF + email (Distributed Generation Planning Application (DGPA) + City of Austin AB+C permit portal). Gridpol files Austin Energy interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Austin Energy’s official sources (see below). Appendix C inspection checklist in guide lists inspection items; VoS rate value not captured.

Austin Energy at a glance

Utility

Austin Energy (City of Austin)

Type

Municipal utility

EIA utility ID

1015

Residential customers

522,446 (EIA-861, 2025)

Net-metered residential customers

none reported

Service territory

2 counties in Texas

How to apply

PDF + email – Distributed Generation Planning Application (DGPA) + City of Austin AB+C permit portal · official link

Who submits

Contractor fills out the DGPA and obtains City of Austin Auxiliary Power electrical permit; Master/Journeyman electrician must attend final inspection.

Export compensation

Buy-all/sell-all – Value of Solar (VoS) rate
Separate PV meter; customer credited for solar generation at VoS rate (not net metering); check current rate on AE tariff

Review time (official)

No AE approval needed <25 kW (DGPA); PV meter installed after final inspection passes.

Documents Austin Energy asks for

  • Interconnection application formDGPA (customer-side) or ESPA (utility-side interconnection, new service) Gridpol prepares this.
  • Site plan / site layoutPhysical layout drawing showing interconnection equipment (for CoA permit) Gridpol prepares this.
  • Single-line diagram (one-line)Electrical one-line diagram up to AE interface Gridpol prepares this.
  • PV module spec sheetList of major equipment: inverter, OCPD, modules
  • Other utility-specific documentInverter manufacturer string sizing calculation (PV)
  • Photos (meter, main panel, equipment) (when applicable)Photos of roof work / as-built may be required, uploaded to permit
  • Final inspection sign-offCoA permit + AE Solar Inspections final inspection
  • Battery spec sheet (when applicable)ESS: UL 9540/UL 1973; plans sealed by Texas PE; may need Austin Fire Dept review

How the Austin Energy process runs

  1. Contractor submits DGPA (ESPA for utility-side)
  2. Obtain City of Austin Auxiliary Power electrical permit (AB+C portal or DSD plan review)
  3. Optional pre-construction meeting with AE inspector (required for commercial)
  4. Rough inspection where required; install
  5. Request final inspection from AE Solar Inspections (licensed electrician attends)
  6. AE Distribution Metering installs PV meter; customer may operate once meter installed

Fees

FeeApplies toNote
Larger/utility-side projectsProcessing fee/deposit per AE Fee Schedule; none stated for residential DGPA

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
DGPA without AE approval25 kWDGPA required but AE approval not required <25 kW
AE review10000 kW50 kW to <10 MW and utility-side interconnections need AE review

Storage, EV and stamps

Battery storage

ESS equipment UL 9540/UL 1973; ESS inverters certified by battery manufacturer; ESS plans sealed by Texas-licensed PE; ESS >20 kWh per IFC, residential >1 kWh per IRC; Austin Fire Dept review may apply.

EV chargers

EV: ESPA (Electric Service Planning Application) required for upgrades to main electrical service; Level 2 >10 kW handled by AE Distribution Design; optional separate EV TOU sub-meter. CoA electrical permit for hardwired 240 V charger.

PE stamp

Energy storage system plans must be sealed by a Texas PE; larger/commercial and utility-side projects require PE-sealed drawings. – PE-stamped drawings are not included in Gridpol.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.