Investor-owned utilityCenterPoint Energy Houston Electric interconnection application
CenterPoint Energy Houston Electric is an investor-owned utility serving 2,529,039 residential customers in Texas (EIA-861, 2025). Applications: Third-party portal (CenterPoint Energy Distribution Interconnection Portal for installers (hosted by anbetrack)). Gridpol files CenterPoint Energy Houston Electric interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from CenterPoint Energy Houston Electric’s official sources (see below). Portal and steps from official CenterPoint Houston page; documents from tariff application form only (no portal checklist/requirements PDF found, photo requirements unknown). Do not confuse with CenterPoint Indiana 'customer-generation' page (Indiana net metering). Verify on first project: portal document checklist, photo/inspection requirements, battery handling. Contact Residential.DG@CenterPointEnergy.com.
CenterPoint Energy Houston Electric at a glance
CenterPoint Energy (CenterPoint Energy)
TypeInvestor-owned utility
EIA utility ID8901
Residential customers2,529,039 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory12 counties in Texas
How to applyThird-party portal – CenterPoint Energy Distribution Interconnection Portal for installers (hosted by anbetrack) · official link
Who submitsCustomer's installer applies online through the interconnection portal; installer secures all applications and permits. Tariff form allows information to be supplied by the Customer or Customer's designated representative; customer signs application (with Authorized Release of Information list) and the Interconnection Agreement.
Review time (official)No CenterPoint-specific timeline found on the page. 16 TAC §25.211(m): interconnection within 4 weeks of receipt of a completed application for pre-certified equipment, 6 weeks for other facilities (longer if substantial capital upgrades). §25.211(g)/(i): pre-interconnection studies max 4 weeks.
Documents CenterPoint Energy Houston Electric asks for
- Interconnection application formApplication for Interconnection and Parallel Operation of Distributed Generation (Tariff 6.3.2): generator type, kW/kVA at 95F, export yes/no + max export, report excess to REP yes/no, pre-certification (UL 1741 / IEEE 1547.1), energization date Gridpol prepares this.
- Single-line diagram (one-line)One-line diagram attached (application checkbox) Gridpol prepares this.
- Site plan / site layoutLayout sketch showing lockable, visible disconnect device Gridpol prepares this.
- Inverter spec sheet (when applicable)Pre-certification label; non-pre-certified systems must provide dynamic modeling values
- Customer signatureCustomer signs application and Interconnection Agreement (Tariff 6.3.3)
- Interconnection agreementICA issued by CenterPoint, signed by all parties
- Other utility-specific document'As built' design plans confirmed by installer after construction (final review)
How the CenterPoint Energy Houston Electric process runs
- Customer inquiry and application: installer applies online through the Distribution Interconnection Portal.
- CenterPoint design review and acceptance of design plans.
- Installer constructs the system (with AHJ permits).
- CenterPoint final review after construction; installer confirms 'as built' design plans.
- Interconnection Agreement (ICA) signed by all parties; Permission to Operate (PTO) issued.
- Meter remotely reprogrammed to capture excess generation export readings; REP handles billing/buyback.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Pre-certified ≤500 kW exporting ≤15% feeder load and ≤25% short-circuit on radial feeder | Rate DGS, Tariff 6.1.2.4, rev. 7, eff. 04/28/25 |
| $75 | Exporting, 0-10 kW, pre-certified, not on network | Rate DGS (unless exempt above) |
| $272 | 0-10 kW, not pre-certified, not on network (exporting or non-exporting) | Rate DGS |
| $312 / $525 | 0-10 kW on network (pre-certified / not pre-certified) | Rate DGS |
| $621-$1,793 | Exporting 10+ to 500 kW | Rate DGS: $621 pre-cert not network, $864 non-pre-cert, $1,402 pre-cert network, $1,793 non-pre-cert network (non-exporting $0-$1,563) |
| As calculated | DC.18 Distributed Generation Meter Installation Charge | Tariff 6.1.2 |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| 0-10 kW | 10 kW | Fee tier |
| 10+ to 500 kW | 500 kW | Fee tier; pre-certified radial units may be fee-exempt |
| 500+ to 2,000 kW / 2,000+ to 10,000 kW | 10000 kW | Pre-screen $350/$500 + study fees |
Transfer trip may be required > 300 kW to 2 MW; required > 2 MW (Construction Services Policy Section 5).
Storage, EV and stamps
Battery storage
Not separately documented on the CenterPoint solar page; application covers all DG types (inverter, synchronous, induction). Portable generator with transfer switch (ATS) must be registered with the ATS team (ATS.Approvals@CenterPointEnergy.com).
Sources
- CenterPoint Energy - Connecting Your System to the Grid (Houston Electric): https://www.centerpointenergy.com/en-us/our-services/electric-utility/technology/solar-energy (retrieved 2026-11-13)
- CenterPoint Energy Houston Electric Tariff for Retail Delivery Service (Rate DGS 6.1.2.4; forms 6.3.2/6.3.3): https://assets.centerpointenergy.com/api/public/content/houston-electric-tariff-for-retail-delivery-service.pdf (retrieved 2026-11-13)
- 16 TAC §25.211 Interconnection of On-Site Distributed Generation (LII reprint of Texas Administrative Code; PUCT site puc.texas.gov returns HTTP 403 to this server): https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-211 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.