CPS Energy interconnection application

CPS Energy is a municipal utility serving 888,946 residential customers in Texas (EIA-861, 2025). Applications: Own online portal (CPS Energy Solar Application Site / DG Review Portal). Gridpol files CPS Energy interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from CPS Energy’s official sources (see below). Net metering/billing credit terms not retrieved; residential step detail in 'Residential Interconnection Process' PDF.

CPS Energy at a glance

Utility

City of San Antonio (City of San Antonio)

Type

Municipal utility

EIA utility ID

16604

Residential customers

888,946 (EIA-861, 2025)

Net-metered residential customers

48,818 (EIA-861, 2025)

Service territory

8 counties in Texas

How to apply

Own online portal – CPS Energy Solar Application Site / DG Review Portal · official link

Who submits

Registered contractor submits on customer's behalf (customer contacts registered solar contractor who manages application). Contractor registration: TDLR electrical contractor license, CGL insurance certificate.

Review time (official)

Pre-application review 15 business days (optional); screening 25-60 business days where required; standard review 90 business days (larger systems).

Documents CPS Energy asks for

  • Interconnection application formApplication for Interconnection of Distributed Generation (DG Manual App. D); <25 kWac: section 2, signed Gridpol prepares this.
  • Single-line diagram (one-line)Detailed operational one-line diagram, to scale, PDF Gridpol prepares this.
  • Site plan / site layoutSite plan, to scale Gridpol prepares this.
  • Other utility-specific documentMeter loop drawing (elevation)/equipment layout; visible disconnect ratings; protective devices
  • PV module spec sheetManufacturer spec sheets for panels and inverters (solar program)
  • Photos (meter, main panel, equipment) (when applicable)Photos of existing equipment on wall and profile view (solar program process)
  • Proof of insurance (when applicable)>50 kWac: certificate of liability insurance
  • Other utility-specific documentSolar Disclosure Form listed in contractor resources

How the CPS Energy process runs

  1. Customer selects registered contractor
  2. Contractor submits application + drawings via Solar Application Site/DG Review Portal
  3. Technical review (screening as needed)
  4. Interconnection agreement / approval
  5. Construction, City of San Antonio permit/inspection
  6. CPS inspection/commissioning
  7. Permission to Operate / meter

Fees

FeeApplies toNote
$01 to <50 kWacStudy fee bracket per DG Manual
$50050 kWac to <1 MWac

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
<25 kWac25 kWSimplified application section 2
>=25 kWac10000 kWSections 3-6; Texas PE sealed drawings

DG Manual covers <10 MWac

Storage, EV and stamps

Battery storage

Storage in a net-metered installation may not export to grid; may power essential loads during outages. DG Manual (May 2024) being revised for BESS.

PE stamp

>=25 kWac (or Downtown Network): Texas PE sealed one-line and site plan. – PE-stamped drawings are not included in Gridpol.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.