Electric cooperativeMedina Electric Cooperative, Inc. interconnection application
Medina Electric Cooperative, Inc. is an electric cooperative serving 30,778 residential customers in Texas (EIA-861, 2025). Gridpol files Medina Electric Cooperative, Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Texas’s commission rule (16 TAC §25.211 (Interconnection of On-Site Distributed Generation) and §25.212 (Technical Requirements)) does not bind electric cooperatives; Medina Electric Cooperative, Inc. sets its own interconnection policy. We confirm its form on the first project. Municipal utilities and electric cooperatives are not bound by §25.211/§25.212 (except coop gas-DG under (o)) and set their own interconnection and net metering/buyback policies.
Medina Electric Cooperative, Inc. at a glance
Medina Electric Coop, Inc
TypeElectric cooperative
EIA utility ID12268
Residential customers30,778 (EIA-861, 2025)
Net-metered residential customers348 (EIA-861, 2025)
Service territory17 counties in Texas
Wholesale supplier / associationSouth Texas Electric Cooperative
Documents Medina Electric Cooperative, Inc. asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Medina Electric Cooperative, Inc.. We confirm Medina Electric Cooperative, Inc.’s exact list on the first project.
Texas interconnection rule
Public Utility Commission of Texas (PUCT)
Interconnection rule16 TAC §25.211 (Interconnection of On-Site Distributed Generation) and §25.212 (Technical Requirements) – Interconnection of On-Site Distributed Generation (DG) · source
Applies toElectric utilities under PUCT jurisdiction (incl. ERCOT transmission & distribution utilities such as Oncor, CenterPoint, AEP Texas, TNMP and non-ERCOT IOUs). Electric cooperatives only via §25.211(o) (distributed natural gas generation); municipal utilities not addressed.
Application formCommission-prescribed statewide application for interconnection and parallel operation (§25.211(q) figure) and prescribed interconnection agreement (§25.211(p)); utility must file DG tariff on prescribed form (§25.211(d)). Customer must submit application and execute agreement on these forms before interconnecting (§25.211(e)(5)).
TimelinesPre-certified: interconnect within 4 weeks of complete application; others 6 weeks; if substantial upgrades, within 2 weeks after upgrades complete (§25.211(m)); pre-interconnection studies <=4 weeks.
FeesNo separate application fee in rule; study fees in utility DG tariff; no study fee for pre-certified <=500 kW meeting (g)(1) or network inverter <20 kW; no distribution/O&M/transmission charges for exported energy (§25.211(d)).
External disconnect§25.212(b)(8): manual disconnect accessible to utility personnel, lockable open, with visible break; no small-inverter waiver in rule text, but parties may agree otherwise or seek good-cause exception (§25.212(a)(4)).
Export compensationNone statewide – 16 TAC §25.242(h) (QF purchase arrangements, integrated IOUs only)
No statewide net metering mandate found for ERCOT competitive areas; export compensation is set by retail electric providers. For integrated (non-unbundled) IOUs, §25.242(h) provides standard-rate purchase of QF output <=100 kW; single forward/backward meter option for renewable QFs <=50 kW closed to contracts after 2008-12-31. §25.242 excludes munis, river authorities, coops.
Municipal utilities and electric cooperatives are not bound by §25.211/§25.212 (except coop gas-DG under (o)) and set their own interconnection and net metering/buyback policies.
- 16 TAC §25.211: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-211 (retrieved 2026-11-13)
- 16 TAC §25.212: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-212 (retrieved 2026-11-13)
- 16 TAC §25.242: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-242 (retrieved 2026-11-13)
- PUCT §25.211 PDF (403 from fetch): https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.211/25.211.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.