Home › Utilities › Texas › Bailey County Electric Cooperative Association
Electric cooperativeBailey County Electric Cooperative Association interconnection application
Bailey County Electric Cooperative Association is an electric cooperative serving 3,461 residential customers in Texas (EIA-861, 2025). Gridpol files Bailey County Electric Cooperative Association interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Bailey County Electric Cooperative Association is a member of Golden Spread Electric Cooperative, which publishes a model interconnection policy (see below); the Texas rule (16 TAC §25.211 (Interconnection of On-Site Distributed Generation) and §25.212 (Technical Requirements)) also applies where it covers electric cooperatives. Bailey County Electric Cooperative Association’s own form is confirmed on the first project.
Bailey County Electric Cooperative Association at a glance
Bailey County Elec Coop Assn
TypeElectric cooperative
EIA utility ID1169
Residential customers3,461 (EIA-861, 2025)
Net-metered residential customers8 (EIA-861, 2025)
Service territory5 counties in Texas
Wholesale supplier / associationGolden Spread Electric Cooperative · Small Generator Interconnection Request Application Form (Qualifying Facilities page)
Documents Bailey County Electric Cooperative Association asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Interconnection agreementRequired by the state rule
- Other utility-specific documentRequired by the state rule
Documents required by the Texas rule. Bailey County Electric Cooperative Association may ask for more on its own form; we confirm on the first project.
Texas interconnection rule
Public Utility Commission of Texas (PUCT)
Interconnection rule16 TAC §25.211 (Interconnection of On-Site Distributed Generation) and §25.212 (Technical Requirements) – Interconnection of On-Site Distributed Generation (DG) · source
Applies toElectric utilities under PUCT jurisdiction (incl. ERCOT transmission & distribution utilities such as Oncor, CenterPoint, AEP Texas, TNMP and non-ERCOT IOUs). Electric cooperatives only via §25.211(o) (distributed natural gas generation); municipal utilities not addressed.
Application formCommission-prescribed statewide application for interconnection and parallel operation (§25.211(q) figure) and prescribed interconnection agreement (§25.211(p)); utility must file DG tariff on prescribed form (§25.211(d)). Customer must submit application and execute agreement on these forms before interconnecting (§25.211(e)(5)).
TimelinesPre-certified: interconnect within 4 weeks of complete application; others 6 weeks; if substantial upgrades, within 2 weeks after upgrades complete (§25.211(m)); pre-interconnection studies <=4 weeks.
FeesNo separate application fee in rule; study fees in utility DG tariff; no study fee for pre-certified <=500 kW meeting (g)(1) or network inverter <20 kW; no distribution/O&M/transmission charges for exported energy (§25.211(d)).
External disconnect§25.212(b)(8): manual disconnect accessible to utility personnel, lockable open, with visible break; no small-inverter waiver in rule text, but parties may agree otherwise or seek good-cause exception (§25.212(a)(4)).
Export compensationNone statewide – 16 TAC §25.242(h) (QF purchase arrangements, integrated IOUs only)
No statewide net metering mandate found for ERCOT competitive areas; export compensation is set by retail electric providers. For integrated (non-unbundled) IOUs, §25.242(h) provides standard-rate purchase of QF output <=100 kW; single forward/backward meter option for renewable QFs <=50 kW closed to contracts after 2008-12-31. §25.242 excludes munis, river authorities, coops.
Municipal utilities and electric cooperatives are not bound by §25.211/§25.212 (except coop gas-DG under (o)) and set their own interconnection and net metering/buyback policies.
- 16 TAC §25.211: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-211 (retrieved 2026-11-13)
- 16 TAC §25.212: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-212 (retrieved 2026-11-13)
- 16 TAC §25.242: https://www.law.cornell.edu/regulations/texas/16-Tex-Admin-Code-SS-25-242 (retrieved 2026-11-13)
- PUCT §25.211 PDF (403 from fetch): https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.211/25.211.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.