Home › Utilities › Ohio › Clyde Light & Power
Municipal utilityClyde Light & Power interconnection application
Clyde Light & Power is a municipal utility serving 2,785 residential customers in Ohio (EIA-861, 2025). Gridpol files Clyde Light & Power interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Ohio’s commission rule (Ohio Adm.Code Chapter 4901:1-22 (Interconnection Services), rules 4901:1-22-01 to -10; R.C. 4928.11, 4928.67) does not bind municipal utilitys; Clyde Light & Power sets its own interconnection policy. We confirm its form on the first project. Municipal electric systems and rural electric cooperatives are not EDUs under PUCO jurisdiction; they set their own interconnection and net metering policies.
Clyde Light & Power at a glance
Clyde Light & Power
TypeMunicipal utility
EIA utility ID3824
Residential customers2,785 (EIA-861, 2025)
Net-metered residential customersnone reported
Service territory1 county in Ohio
Documents Clyde Light & Power asks for
- Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
- Single-line diagram (one-line)Drawn by us from your equipment data: modules, strings, inverter, battery, disconnects, point of interconnection, meter. Gridpol prepares this.
- Site plan / site layoutDrawn by us from your roof sketch or photos: array, inverter, battery, disconnect, meter and main panel locations. Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Customer signatureThe account holder signs the application or authorization. We send the signature link.
- Recent electric billName, service address, account and meter number must match the application.
- Final inspection sign-offApproved electrical inspection from the authority having jurisdiction after installation.
Typical documents for US utilities – not yet verified for Clyde Light & Power. We confirm Clyde Light & Power’s exact list on the first project.
Ohio interconnection rule
Public Utilities Commission of Ohio (PUCO)
Interconnection ruleOhio Adm.Code Chapter 4901:1-22 (Interconnection Services), rules 4901:1-22-01 to -10; R.C. 4928.11, 4928.67 – Interconnection Services · source
Applies toElectric distribution utilities (EDUs: AEP Ohio, Duke Energy Ohio, AES Ohio, FirstEnergy's Ohio Edison/CEI/Toledo Edison), which must file uniform interconnection service tariffs (4901:1-22-02). Municipal utilities and cooperatives are not PUCO-regulated EDUs.
Application formUniform statewide approach: 'short form' application for DER <= 25 kW with IEEE 1547/UL 1741 certified equipment, standard application otherwise, filed with the EDU (4901:1-22-05); standard interconnection agreement per 4901:1-22-10.
TimelinesReceipt/completeness notice within 10 business days (4901:1-22-04); Level 1 review 15 BD, Level 2 20 BD after complete application; interconnection agreement within 5 BD of approval; interconnection within 10 BD after required upgrades complete. Pre-application report $300, within 10 BD.
FeesLevel 1 <= $50 (waivable); Level 2 <= $50 + $1/kW (+ $2,500 supplemental review deposit if elected); Level 3 <= $100 + $2/kW + actual study costs; pre-application report $300.
InsuranceEDU may not require liability insurance beyond proof of insurance or another financial instrument covering the applicant's responsibilities under the tariff, and may not require a particular agent/broker (4901:1-22-10(E)). No dollar amounts specified.
External disconnectRequired: DER must have a disconnect switch outside the equipment package, accessible to and lockable by EDU personnel, clearly labeled as DER disconnect, provided and paid for by the applicant (4901:1-22-05).
Export compensationNEM – R.C. 4928.67; Ohio Adm.Code 4901:1-10-28 (eff. Apr. 8, 2024)
No fixed kW cap: system may not exceed 120% of customer's requirements (3-year average). Monthly excess credited at the energy component of the EDU's standard service offer, carried forward; no cash-out required. EDUs must offer standard and hospital net metering tariffs; CRES providers optional.
Municipal electric systems and rural electric cooperatives are not EDUs under PUCO jurisdiction; they set their own interconnection and net metering policies.
- OAC 4901:1-22-02 Scope and application: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-02 (retrieved 2026-11-13)
- OAC 4901:1-22-04 General provisions: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-04 (retrieved 2026-11-13)
- OAC 4901:1-22-05 Application requirements: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-05 (retrieved 2026-11-13)
- OAC 4901:1-22-06 Level 1 review: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-06 (retrieved 2026-11-13)
- OAC 4901:1-22-07 Level 2 review: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-07 (retrieved 2026-11-13)
- OAC 4901:1-22-08 Level 3 review: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-08 (retrieved 2026-11-13)
- OAC 4901:1-22-10 Interconnection agreements: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-22-10 (retrieved 2026-11-13)
- OAC 4901:1-10-28 Net metering: https://www.law.cornell.edu/regulations/ohio/Ohio-Admin-Code-4901-1-10-28 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.