Toledo Edison interconnection application

Toledo Edison is an investor-owned utility serving 279,678 residential customers in Ohio (EIA-861, 2025). Applications: Own online portal (FirstEnergy Interconnection Portal). Gridpol files Toledo Edison interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from Toledo Edison’s official sources (see below). Level 1 fee ($50) taken from FE page as indexed; confirm in portal.

Toledo Edison at a glance

Utility

The Toledo Edison Co (FirstEnergy)

Type

Investor-owned utility

EIA utility ID

18997

Residential customers

279,678 (EIA-861, 2025)

Net-metered residential customers

788 (EIA-861, 2025)

Service territory

10 counties in Ohio

How to apply

Own online portal – FirstEnergy Interconnection Portal · official link

Who submits

Customer or installer via online portal (paper applications also accepted). Checks payable to FirstEnergy Corporation with customer name and account number. Contact: TE_interconnection@firstenergycorp.com.

Export compensation

NEM – Net Energy Metering Rider
OAC 4901:1-10-28

Review time (official)

Per PUCO schedule OAC 4901:1-22-04 / 4901:1-22-06; bi-directional meter may take several weeks after Approval to Operate.

Documents Toledo Edison asks for

  • Interconnection application formLevel 1 (<=25 kW inverter, UL1741) or Level 2/3 Gridpol prepares this.
  • Site plan / site layoutProperty layout, north arrow, cross streets, DER AC disconnect, generation/inverter/storage, service transformer; no overhead internet photos Gridpol prepares this.
  • Single-line diagram (one-line)DC/AC ratings, inverter AC rating, disconnect make/model, connection, meter, storage Gridpol prepares this.
  • PV module spec sheetManufacturer data sheet of the modules.
  • Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
  • Interconnection agreementLevel 1 Short Form Agreement / Standard Agreement (after installation)
  • Net metering / net billing agreementNet Energy Metering Rider Application
  • Final inspection sign-offThird-party (electrical inspector) inspection report / Certificate of Completion

How the Toledo Edison process runs

  1. Determine size/type per tariff.
  2. Submit application, one-line, site plan, spec sheets and fee (portal).
  3. Engineering review; notification of approval / upgrade / missing info.
  4. Install per approved application and FE requirements; local electrical inspection.
  5. Submit Interconnection Agreement, Net Metering Rider application and inspection report.
  6. Company final review, possible witness test, Approval to Operate (Certificate of Completion).
  7. Bi-directional meter installed; credits tracked only after meter install.

Fees

FeeApplies toNote
$50Level 1 (<=25 kW)per FirstEnergy search snippet; page lists Level 2/3 fees
$50 + $1/kW nameplateLevel 2
$100 + $2/kW nameplateLevel 3

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 125 kWinverter-based, certified
Level 22000 kW
Level 320000 kW

Ohio net metering per OAC 4901:1-10-28.

Storage, EV and stamps

Battery storage

Storage (battery) must be shown on site plan and one-line diagram.

Common issues the utility lists

  • Overhead internet photos instead of site plan
  • Missing drawings/documentation or unpaid fees
  • Information incorrect or missing in application

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited