Home › Utilities › Ohio

Ohio

Ohio interconnection applications

117 electric utilities serve Ohio (EIA-861, 2025): 7 investor-owned utilitys, 25 electric cooperatives, 85 municipal utilitys. Together they serve 4,977,494 residential customers; 29,999 residential customers were on net metering at year-end 2025.

Largest utilities in Ohio

AEP OhioProcess verified

Investor-owned utility · 1,348,588 residential customers · Ohio

Applications: PowerClerk – AEP PowerClerk

Interconnection process and documents →
Ohio EdisonProcess verified

Investor-owned utility · 961,084 residential customers · Ohio

Applications: Own online portal – FirstEnergy Interconnection Portal

Interconnection process and documents →
Duke EnergyPartly researched

Investor-owned utility · 700,265 residential customers · Ohio

Interconnection process and documents →
The Illuminating CompanyProcess verified

Investor-owned utility · 677,581 residential customers · Ohio

Applications: Own online portal – FirstEnergy Interconnection Portal

Interconnection process and documents →
AES OhioProcess verified

Investor-owned utility · 469,317 residential customers · Ohio

Applications: PowerClerk – AES Ohio Interconnection (PowerClerk)

Interconnection process and documents →
Toledo EdisonProcess verified

Investor-owned utility · 279,678 residential customers · Ohio

Applications: Own online portal – FirstEnergy Interconnection Portal

Interconnection process and documents →
South Central PowerPartly researched

Electric cooperative · 118,458 residential customers · Ohio

Applications: PDF + email – Utility-prepared interconnection application via Energy Advisors

Interconnection process and documents →
City of ClevelandState guidance

Municipal utility · 64,905 residential customers · Ohio

Interconnection process and documents →
City of HamiltonState guidance

Municipal utility · 27,209 residential customers · Ohio

Interconnection process and documents →
Licking Rural Electric Inc.State guidance

Electric cooperative · 26,038 residential customers · Ohio

Interconnection process and documents →
City of Cuyahoga FallsState guidance

Municipal utility · 24,256 residential customers · Ohio

Interconnection process and documents →
Consolidated CooperativeAssociation model policy

Electric cooperative · 17,091 residential customers · Ohio

Interconnection process and documents →

Export compensation among the researched Ohio utilities: NEM, Net billing. Rules differ by utility – see each utility page.

Ohio interconnection rule

Commission

Public Utilities Commission of Ohio (PUCO)

Interconnection rule

Ohio Adm.Code Chapter 4901:1-22 (Interconnection Services), rules 4901:1-22-01 to -10; R.C. 4928.11, 4928.67 – Interconnection Services · source

Applies to

Electric distribution utilities (EDUs: AEP Ohio, Duke Energy Ohio, AES Ohio, FirstEnergy's Ohio Edison/CEI/Toledo Edison), which must file uniform interconnection service tariffs (4901:1-22-02). Municipal utilities and cooperatives are not PUCO-regulated EDUs.

Application form

Uniform statewide approach: 'short form' application for DER <= 25 kW with IEEE 1547/UL 1741 certified equipment, standard application otherwise, filed with the EDU (4901:1-22-05); standard interconnection agreement per 4901:1-22-10.

Timelines

Receipt/completeness notice within 10 business days (4901:1-22-04); Level 1 review 15 BD, Level 2 20 BD after complete application; interconnection agreement within 5 BD of approval; interconnection within 10 BD after required upgrades complete. Pre-application report $300, within 10 BD.

Fees

Level 1 <= $50 (waivable); Level 2 <= $50 + $1/kW (+ $2,500 supplemental review deposit if elected); Level 3 <= $100 + $2/kW + actual study costs; pre-application report $300.

Insurance

EDU may not require liability insurance beyond proof of insurance or another financial instrument covering the applicant's responsibilities under the tariff, and may not require a particular agent/broker (4901:1-22-10(E)). No dollar amounts specified.

External disconnect

Required: DER must have a disconnect switch outside the equipment package, accessible to and lockable by EDU personnel, clearly labeled as DER disconnect, provided and paid for by the applicant (4901:1-22-05).

Export compensation

NEM – R.C. 4928.67; Ohio Adm.Code 4901:1-10-28 (eff. Apr. 8, 2024)
No fixed kW cap: system may not exceed 120% of customer's requirements (3-year average). Monthly excess credited at the energy component of the EDU's standard service offer, carried forward; no cash-out required. EDUs must offer standard and hospital net metering tariffs; CRES providers optional.

Not bound by the rule

Municipal electric systems and rural electric cooperatives are not EDUs under PUCO jurisdiction; they set their own interconnection and net metering policies.

LevelUp toCriteria / review / fee
Level 1 (4901:1-22-06)25 kWInverter-based, certified to IEEE 1547 / UL 1741, nameplate <= 25 kW, meeting approval criteria in (B)(1) · 15 business days after complete application; agreement within 5 business days · Up to $50 (may be waived)
Level 2 (4901:1-22-07)5000 kWCertified inverter-based; nameplate limits by line voltage: <=5 kV 500 kW (<2 MW on 600 A line within 2.5 feeder mi); 5-15 kV 2 MW (<3 MW); 15-30 kV 3 MW (<4 MW); 30-69 kV 4 MW (<5 MW) · 20 business days after complete; supplemental review 25 business days after $2,500 deposit · Up to $50 + $1/kW; supplemental review deposit $2,500 trued-up to actual
Level 3 (4901:1-22-08)20000 kWNot qualifying for or failing Level 1/2, or non-certified equipment, nameplate <= 20 MW; scoping meeting, feasibility/system impact/facilities studies · Agreement within 5 business days after studies complete and costs collected · Up to $100 + $2/kW plus actual study and modification costs

All 117 utilities in Ohio

Residential customers in Ohio per EIA-861 (2025). Customer counts = bundled + delivery-only service (EIA-861 Part A + Part D). Service territory is reported by county; a county can be served by several utilities.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.