AES Ohio interconnection application

AES Ohio is an investor-owned utility serving 469,317 residential customers in Ohio (EIA-861, 2025). Applications: PowerClerk (AES Ohio Interconnection (PowerClerk)). Gridpol files AES Ohio interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from AES Ohio’s official sources (see below). Exact PTO step not described; verify on first project.

AES Ohio at a glance

Utility

Dayton Power & Light Co (AES Corporation)

Type

Investor-owned utility

EIA utility ID

4922

Residential customers

469,317 (EIA-861, 2025)

Net-metered residential customers

474 (EIA-861, 2025)

Service territory

24 counties in Ohio

How to apply

PowerClerk – AES Ohio Interconnection (PowerClerk) · official link

Who submits

Online application in PowerClerk (customer/installer).

Export compensation

NEM – Net metering (tariff D5 section D)

Review time (official)

Level 1: 10 business days notice of receipt, 10 approval, 5 agreement. Level 2: 10/20/5. Incomplete application notice within 10 business days.

Documents AES Ohio asks for

  • Interconnection application formFilled in by us from your project data in the utility’s portal or on its form. Gridpol prepares this.
  • Site plan / site layoutSame content as FE-style list incl. storage and transformer Gridpol prepares this.
  • Single-line diagram (one-line)DC/AC ratings, disconnect make/model, storage Gridpol prepares this.
  • Inverter spec sheetIEEE 1547 / UL 1741

How the AES Ohio process runs

  1. Submit online application in PowerClerk.
  2. Completeness notice (10 business days).
  3. Approval notice.
  4. Interconnection agreement.
  5. Install, inspection, bidirectional meter ($95).

Fees

FeeApplies toNote
$50Level 1 (0-25 kW)
$50 + $1/kW + upgradesLevel 2 (25 kW-2 MW)
$100 + $2/kW + upgrades + studiesLevel 3 (>2 MW)
$95Bidirectional residential meter upgrade

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 125 kW
Level 22000 kW
Level 3>2 MW

Size not to exceed 120% of previous year's usage (OAC 4901:1-10-28).

Storage, EV and stamps

Battery storage

Storage must be shown on site plan and one-line.

PE stamp

Only Level 2 >50 kW and all Level 3; Level 1 no PE stamp. – PE-stamped drawings are not included in Gridpol.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.