New Mexico interconnection applications

32 electric utilities serve New Mexico (EIA-861, 2025): 3 investor-owned utilitys, 7 municipal utilitys, 20 electric cooperatives, 1 state power authority, 1 federal power agency. Together they serve 893,618 residential customers; 64,532 residential customers were on net metering at year-end 2025.

Largest utilities in New Mexico

PNMPartly researched

Investor-owned utility · 496,914 residential customers · New Mexico

Applications: PowerClerk – NMPRC/PNM PowerClerk portal for rooftop solar applications (separate pnmferc.powerclerk.com instance is for FERC pre-application/informal requests, not the rooftop program)

Interconnection process and documents →
Xcel Energy (SPS)Partly researched

Investor-owned utility · 324,888 residential customers · New Mexico

Applications: Own online portal – Xcel Energy DER Interconnection Portal (Salesforce)

Interconnection process and documents →
El Paso ElectricProcess verified

Investor-owned utility · 417,578 residential customers · New Mexico

Applications: Own online portal – EPE Distributed Generation online Standard / Expansion Interconnection Application (solarium3; e-signature, online fee payment, status link)

Interconnection process and documents →
City of FarmingtonState guidance

Municipal utility · 36,031 residential customers · New Mexico

Interconnection process and documents →
Jemez Mountains Electric Cooperative, Inc.State rule applies

Electric cooperative · 28,185 residential customers · New Mexico

Interconnection process and documents →
Kit Carson Electric Cooperative, Inc.State rule applies

Electric cooperative · 26,286 residential customers · New Mexico

Interconnection process and documents →
Continental Divide El Cooperative Inc.State rule applies

Electric cooperative · 20,474 residential customers · New Mexico

Interconnection process and documents →
Central New Mexico El Cooperative, Inc.State rule applies

Electric cooperative · 19,323 residential customers · New Mexico

Interconnection process and documents →
Otero County Electric Cooperative Inc.State rule applies

Electric cooperative · 16,517 residential customers · New Mexico

Interconnection process and documents →
Farmers Electric Cooperative, Inc.State rule applies

Electric cooperative · 10,310 residential customers · New Mexico

Interconnection process and documents →
Navajo Tribal Utility AuthorityState guidance

State power authority · 38,553 residential customers · New Mexico

Interconnection process and documents →
Los Alamos CountyState guidance

Municipal utility · 8,395 residential customers · New Mexico

Interconnection process and documents →

Export compensation among the researched New Mexico utilities: NEM. Rules differ by utility – see each utility page.

New Mexico interconnection rule

Commission

New Mexico Public Regulation Commission (PRC)

Interconnection rule

17.9.568 NMAC (Interconnection of Generating Facilities with a Rated Capacity up to and including 10 MW); >10 MW: 17.9.569 NMAC – Interconnection of generating facilities up to 10 MW · source

Applies to

Every electric utility under PRC jurisdiction, including investor-owned utilities (PNM, El Paso Electric, SPS/Xcel) and rural electric cooperatives (17.9.568.2.A); municipal utilities not named.

Application form

Standard application per utility with form interconnection agreement signed with the application for simplified process (17.9.568.20.A); net energy metering application.

Timelines

Receipt 3 BD, completeness 10 BD; simplified screens 7 BD; fast track 15 BD; supplemental 20 BD. Customer gives 10 BD notice of start; utility may inspect within 10 BD; PTO normally within 10 BD after required documents (simplified/fast track) (17.9.568.21). Pre-application report $300/$500, 20/30 BD.

Fees

Application (17.9.568.23.A): $150 up to 25 kW; $300 >25-100 kW; $300 + $1/kW >100 kW; non-export $150 (<100 kW) / $300; supplemental review $2,500.

Insurance

<=250 kW: general liability insurance only if commission orders it on utility petition showing good cause; >250 kW: utility may require insurance up to $1,000,000 or other evidence of financial responsibility (17.9.568.25.B).

External disconnect

Visible-open, lockable, load-break disconnect labeled 'generating facility generation disconnect' required, except systems <=10 kW with certified inverter and self-contained meter that have a utility-accessible AC load-break disconnect (or DC disconnect if no other source) (17.9.568.29.D).

Export compensation

NEM – 17.9.570 NMAC (eff. 2022-05-24), 17.9.570.14 and .15
<=10 kW: net metering - excess credited next bill at energy rate or as kWh, carried forward; >10 kW-10 MW: standard metering and billing agreement with net metering option (17.9.570.15). Applies to every PRC-jurisdictional utility incl. coops and munis.

Not bound by the rule

Rural electric cooperatives are bound by 17.9.568 and 17.9.570 (distribution coop service also per own bylaws/tariffs). Municipal utilities are within 17.9.570 scope for QF/net metering; their interconnection coverage under 17.9.568 not stated.

LevelUp toCriteria / review / fee
Simplified50 kWCertified inverter-based, nameplate <=50 kW and export <=25 kW · Receipt 3 BD; completeness 10 BD; screen results 7 BD after complete · $150 (<=25 kW); $300 (>25-100 kW)
Fast Track5000 kWUp to 5 MW by line voltage/export/distance from substation (e.g. 5 kV <500 kW; 31-69 kV <4 MW, <5 MW on 600 A mainline within 2.5 mi) · Initial review 15 BD; supplemental review 20 BD · $150/$300 or $300 + $1/kW (>100 kW); supplemental review $2,500
Detailed Study10000 kW<=10 MW not qualifying for/ failing simplified or fast track · Scoping meeting 10 BD; feasibility 30 BD; system impact 40 BD; facilities 30/45 BD · $300 + $1/kW; feasibility deposit lesser of 50% est. cost or $1,000
Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited