Home › Utilities › Indiana › AGC Division of APGI Inc.

Investor-owned utility

AGC Division of APGI Inc. interconnection application

AGC Division of APGI Inc. is an investor-owned utility serving 2 customers in Indiana (EIA-861, 2025). Gridpol files AGC Division of APGI Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Indiana’s interconnection rule (170 IAC 4-4.3 (as amended by LSA #25-368, IURC RM #24-01)) applies to AGC Division of APGI Inc.. Levels, timelines and documents below come from that rule; AGC Division of APGI Inc.’s own form and portal are confirmed on the first project.

AGC Division of APGI Inc. at a glance

Utility

AGC Division of APGI Inc

Type

Investor-owned utility

EIA utility ID

261

Customers

2 (EIA-861, 2025, short form: all customer classes)

Net-metered residential customers

none reported

Service territory

1 county in Indiana

Documents AGC Division of APGI Inc. asks for

  • Interconnection application formRequired by the state rule Gridpol prepares this.
  • Interconnection agreementRequired by the state rule
  • Final inspection sign-offRequired by the state rule
  • UL 1741 / IEEE 1547 certificationRequired by the state rule
  • Proof of insuranceRequired by the state rule

Documents required by the Indiana rule. AGC Division of APGI Inc. may ask for more on its own form; we confirm on the first project.

Indiana interconnection rule

Commission

Indiana Utility Regulatory Commission (IURC)

Interconnection rule

170 IAC 4-4.3 (as amended by LSA #25-368, IURC RM #24-01) – Interconnection of customer facilities · source

Applies to

Investor-owned electric utilities subject to IURC jurisdiction (170 IAC 4-4.3-2). Municipal utilities and electric cooperatives are not covered.

Application form

Commission-approved interconnection application and interconnection agreement forms, used by each IOU (170 IAC 4-4.3-4(c)).

Timelines

Level 1/2: completeness notice 10 business days; determination 15 business days after complete; executable agreement 10 business days after approval; customer returns executed agreement at least 10 business days before operation; final approval after executed agreement and any inspection, conditioned on electrical code official approval (170 IAC 4-4.3-6, -7).

Fees

Level 1: no fee. Level 2: <= $50 + $1/kW nameplate (+ minor modifications/additional review, engineering <= $100/h). Level 3: <= $100 + $2/kW + study time (<= $100/h) (170 IAC 4-4.3-4(e)).

Insurance

Net metering facilities: liability coverage of at least $100,000 (homeowners, commercial or other); utility may not require higher limits or additional policies (170 IAC 4-4.2-8, referenced by 4-4.3-10(a)). Other customer facilities: only reasonable amounts of insurance against reasonably likely risks, mutual indemnification (170 IAC 4-4.3-10(b)).

External disconnect

Utility may require the applicant to include a disconnect switch as a supplement to the equipment package (170 IAC 4-4.3-4(d)).

Export compensation

Net billing – IC 8-1-40 (P.L.264-2017, SEA 309); 170 IAC 4-4.2 (net metering rule, legacy)
Net metering tariffs closed to new customers after June 30, 2022 (IC 8-1-40-11); legacy NEM customers continue per IC 8-1-40-13/-14. New distributed generation (<= lesser of 1 MW or average annual consumption, IC 8-1-40-3) is credited for excess distributed generation (instantaneous difference, IC 8-1-40-5) at 1.25 x the supplier's average marginal price of electricity of the prior year (IC 8-1-40-17). Applies to IURC-regulated public utilities; excludes municipally owned utilities and certain cooperatives (IC 8-1-40-4).

Not bound by the rule

Municipal utilities and REMC/electric cooperatives are not bound by 170 IAC 4-4.3 or IC 8-1-40 (IC 8-1-40-4 excludes them) and set their own interconnection and DG policies (many through Hoosier Energy / Wabash Valley Power member policies, not reviewed).

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.

Get started – $500/month unlimited