Home › Utilities › Indiana › AES Indiana

Investor-owned utility

AES Indiana interconnection application

AES Indiana is an investor-owned utility serving 469,634 residential customers in Indiana (EIA-861, 2025). Applications: PowerClerk (AES Indiana Interconnection (PowerClerk)). Gridpol files AES Indiana interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from AES Indiana’s official sources (see below). Verified 2026-11-13 from aesindiana.com/interconnections and the Level 1 reference application (docx). Note: the reference form still names ipl.interconnection@aes.com for email submittal, while the page directs applications to PowerClerk – use PowerClerk.

AES Indiana at a glance

Utility

AES Indiana (AES Corporation)

Type

Investor-owned utility

EIA utility ID

9273

Residential customers

469,634 (EIA-861, 2025)

Net-metered residential customers

1,019 (EIA-861, 2025)

Service territory

20 counties in Indiana

How to apply

PowerClerk – AES Indiana Interconnection (PowerClerk) · official link

Who submits

Customer is the applicant; form has contractor/installer section and the installer may submit in PowerClerk on the customer's behalf (AES Indiana Solar FAQ).

Export compensation

Net billing – Rider 16 Excess Distributed Generation (EDG)
Rider 16 effective 07-27-2026.

Review time (official)

Per AES Indiana interconnection page (170 IAC 4-4.3): completeness notice 10 business days after submission; approval decision 15 business days after completeness; inspection notice and agreement 10 business days after approval; Level 3 six months to a year.

Documents AES Indiana asks for

  • Interconnection application formLevel 1 (≤10 kW certified inverter) / Level 2 / Level 3 application, completed online in PowerClerk Gridpol prepares this.
  • Single-line diagram (one-line)Single-line diagram/sketch from service point to inverter: main panel, sub-panels, breaker/fuse sizes, transformers, disconnects (disconnect switch not required for Level 1) Gridpol prepares this.
  • UL 1741 / IEEE 1547 certificationDocumentation that a nationally recognized testing laboratory has listed the equipment
  • Proof of insuranceEvidence of homeowners/commercial insurance with ≥$100,000 comprehensive general liability and contractual liability
  • Battery spec sheet (when applicable)Battery model, kWh and operating mode (backup or peak shaving) entered on form if used
  • Interconnection agreementUtility sends inspection notice and agreement; customer signs and returns ≥10 business days before start date

How the AES Indiana process runs

  1. Create PowerClerk account and submit Level 1/2/3 application with SLD, equipment listing documentation and insurance evidence.
  2. AES Indiana sends completeness notice (10 business days).
  3. AES Indiana approves or denies (15 business days after completeness; Level 2 adds engineering review).
  4. AES Indiana sends inspection notice and interconnection agreement (10 business days after approval).
  5. Customer signs and returns agreement ≥10 business days before planned start date.
  6. Install; utility inspection/witness as noticed; begin parallel operation; Rider 16 EDG metering.

Fees

FeeApplies toNote
$0Level 1 (0-10 kW)
$60 + upgradesLevel 2 (10 kW-2 MW)
$100 + $2/kW + upgrades + studiesLevel 3 (>2 MW)

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 110 kW
Level 22000 kW
Level 3>2 MW
Net metering cap1000 kW

EDG Rider 16 for systems up to 1 MW.

Storage, EV and stamps

Battery storage

Level 1 form asks battery model, size (kWh) and whether operated in backup mode or peak shaving.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.