Home › Utilities › Indiana › NIPSCO
Investor-owned utilityNIPSCO interconnection application
NIPSCO is an investor-owned utility serving 433,889 residential customers in Indiana (EIA-861, 2025). Applications: PDF + email (NIPSCO New Business Department (Rider 679 Application for Interconnection)). Gridpol files NIPSCO interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from NIPSCO’s official sources (see below). Portal (email), attachment list and steps confirmed from NIPSCO page, Rider 679 application and 170 IAC 4-4.3-6. Rider 689 credit rate not re-read.
NIPSCO at a glance
Northern Indiana Pub Serv Co (NiSource)
TypeInvestor-owned utility
EIA utility ID13756
Residential customers433,889 (EIA-861, 2025)
Net-metered residential customers1,414 (EIA-861, 2025)
Service territory20 counties in Indiana
How to applyPDF + email – NIPSCO New Business Department (Rider 679 Application for Interconnection) · official link
Who submitsCustomer: must be an existing NIPSCO electric customer and owner of the system (generator cannot be leased for EDG). Application lists engineering firms/contractors involved; customer signs New Applicant DG Customer Letter.
Export compensationNet billing – Rider 689 Excess Distributed Generation
Excess credited at 125% of market price.
170 IAC 4-4.3-6 Level 1: completeness notice within 10 business days; approval/denial within 15 business days after complete; agreement (and inspection notice) within 10 business days after approval. Level 2: completeness 10 BD, initial review 15 BD.
Documents NIPSCO asks for
- Interconnection application formRider 679 Application for Interconnection (Level 1 <=25 kW, or Level 2/3 >25 kW); AC nameplate output, inverter model, operating modes, export kW Gridpol prepares this.
- Other utility-specific documentSigned New Applicant DG Customer Letter
- Single-line diagram (one-line)Single-line diagram from facility to point of interconnection incl. inverters, storage, Utility AC Generator Disconnect, panels, breakers Gridpol prepares this.
- Other utility-specific document (when applicable)Control drawings for relays and breakers
- Site plan / site layoutLocation of generators, inverters, storage, disconnect, service panels and utility meter Gridpol prepares this.
- Inverter spec sheetManufacturer, model, AC full-load nameplate rating, operating manual or link
- Other utility-specific document (when applicable)Protective relay / inverter operating-mode settings applicable to interconnection
- UL 1741 / IEEE 1547 certificationDocumentation that an NRTL has listed the equipment (IEEE 1547-2018 / UL 1741)
- Interconnection agreementLevel 1 interconnection agreement executed and returned at least 10 business days before operation
- Proof of insurance (when applicable)Proof of reasonable insurance upon NIPSCO request (170 IAC 4-4.3-10); larger-facility agreement specifies CGL/umbrella limits
How the NIPSCO process runs
- Email application, attachments and signed New Applicant DG Customer Letter to cnb@nisource.com (or mail to NIPSCO New Business, 801 E. 86th Ave., Merrillville, IN 46410); Level 2/3 fee with application.
- NIPSCO completeness notice (10 BD) and technical review; possible additional study.
- Approval notice; NIPSCO sends interconnection agreement and states whether inspection is required.
- Customer signs agreements and returns them at least 10 business days before operation, stating anticipated start date; construction may begin once agreements are complete.
- Install; local electrical code approval; NIPSCO inspection if required.
- NIPSCO approves interconnection and installs new meter per NIPSCO standards; do not operate before.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Level 1 (inverter-based, certified, <=25 kW) | Rider 679 |
| $50 + $1/kW | Level 2 (certified, >25 kW to 2 MW) | Non-refundable, with application |
| $100 + $2/kW | Level 3 (>2 MW or not qualifying for L1/L2) | Plus $100/hour engineering for impact/facilities studies; required utility facilities at applicant cost |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 25 kW | Inverter-based, certified (170 IAC 4-4.3-6 as amended by RM 24-01, 2025) |
| Level 2 | 2000 kW | Certified |
| Level 3 | All others | |
| Net metering cap | 1000 kW |
EDG: nameplate <1 MW or average annual consumption. >500 kW requires direct transfer trip (costs from $125,000). Software output limiting not accepted to reduce applied nameplate.
Storage, EV and stamps
Battery storage
Energy storage systems are a listed power source on the application and must appear on SLD and site plan; total AC nameplate counts (software limitation not accepted). EDG page lists only wind, solar, hydro as eligible EDG sources.
Common issues the utility lists
- Incomplete application: NIPSCO returns a list of missing information (170 IAC 4-4.3-6(i))
- Level 1 screens failed (circuit penetration 5%/10%, fault current, shared secondary 20 kVA, 240 V imbalance, network/transmission PCC) -> denied; may resubmit under Level 2/3
Gridpol’s pre-submission check covers these before we file.
Sources
- NIPSCO Excess Distributed Generation Tariff: https://www.nipsco.com/services/renewable-energy-programs/excess-distributed-generation-tariff (retrieved 2026-11-13)
- NIPSCO Rider 679 Application for Interconnection Level 1/2/3 (eff. 02/27/2026): https://www.nipsco.com/docs/librariesprovider11/services/renewable-energy-programs/renewable-energy-program/applications/level-1/net-metering-interconnection-application-level-1.pdf?sfvrsn=2eaa6f51_8 (retrieved 2026-11-13)
- NIPSCO Rider 679 Interconnection Standards (fees, agreements): https://www.nipsco.com/docs/librariesprovider11/rates-and-tariffs/electric-rates/2023-to-current/nipsco-electric-service-tariff-rider-679.pdf (retrieved 2026-11-13)
- IURC Final Rulemaking RM 24-01 amending 170 IAC 4-4.3 (Level 1 to 25 kW, timelines): https://www.in.gov/iurc/files/ord_RM24-01_093025.pdf (retrieved 2026-11-13)
Other utilities in Indiana
- Duke Energy Indiana808,572
- AES Indiana469,634
- Indiana Michigan Power (I&M)425,007
- CenterPoint Energy Indiana South134,700
- Hendricks County Rural E M C38,554
- South Central Indiana REMC35,216
- Northeastern Rural E M C31,034
- City of Anderson29,600
- Tipmont Rural Electric Member Corporation29,540
- Johnson County Rural E M C29,132
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.