Duke Energy Indiana is an investor-owned utility serving 808,572 residential customers in Indiana (EIA-861, 2025). Gridpol files Duke Energy Indiana interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Partly researched from official sources. Only the 2019 IURC filing could be read (application package needed for a Project Number, contacts). duke-energy.com blocks our server/WebFetch and archive captures lack Indiana content; Indiana Admin. Code site not machine-readable. Verify on first project: current portal (online vs e-mail), Level 2/3 fees (170 IAC 4-4.3), insurance, review timelines, storage rules, EDG rider terms and PTO/meter steps.
Duke Energy Indiana at a glance
Duke Energy Indiana, LLC (Duke Energy)
TypeInvestor-owned utility
EIA utility ID15470
Residential customers808,572 (EIA-861, 2025)
Net-metered residential customers4,228 (EIA-861, 2025)
Service territory71 counties in Indiana
Who submitsCustomer or installer submits Level 1 or Level 2/3 interconnection application to Duke Energy's Renewables Service Center (866-233-2290, CustomerOwnedGeneration@duke-energy.com, Mon-Fri 8-5). Agent/LOA rules not confirmed.
Export compensationNet billing – Excess Distributed Generation (EDG)
Net metering tariff closed to new customers (Indiana SEA 309).
Documents Duke Energy Indiana asks for
- Interconnection application formLevel 1 (inverter-based <=10 kW) or Level 2-3 (Standard Contract Rider No. 80 / 80-A) Gridpol prepares this.
- Single-line diagram (one-line)Legible one-line diagram Gridpol prepares this.
- Site plan / site layoutLegible site map Gridpol prepares this.
- PV module spec sheetManufacturer data sheet of the modules.
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Proof of insurance (when applicable)At least $100,000 liability coverage per tariff (not confirmed from current official page)
- Other utility-specific document (when applicable)Non-inverter systems: control drawings and protective relay settings (not confirmed from current official page)
How the Duke Energy Indiana process runs
- Submit complete Interconnection Application with fee (Levels 2 and 3 only), legible one-line diagram, legible site map, inverter and panel spec sheets.
- Duke issues a Project Number once the application is complete; projects are studied in order of Project Number.
- Technical review; fully executed Interconnection Agreement.
- Install, inspection and meter set (details not confirmed).
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Level 1 (<=10 kW inverter-based) | |
| Fee applies | Level 2 and 3 | amount not confirmed |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 10 kW | inverter-based |
| Level 2-3 | 1000 kW | EDG behind-the-meter max 1 MW |
| Net metering cap | 1000 kW |
Sources
- Duke Energy Indiana response to IURC net metering questions (March 27, 2019) (read): https://secure.in.gov/iurc/files/Duke-Energy-Indiana-Response-to-IURC-Net-Metering-questions-March-27-2019.pdf (retrieved 2026-11-13)
- Duke Energy - Introduction to Renewable Energy Generation (not readable: blocked/location-gated): https://www.duke-energy.com/home/products/renewable-energy/generate-your-own/renewable-energy-generation (retrieved 2026-11-13)
- Duke Energy Indiana IURC-15 tariff (not readable: blocked, no archive capture): https://www.duke-energy.com/home/billing/rates/electric-tariff/iurc-15 (retrieved 2026-11-13)
Indiana interconnection rule
Indiana Utility Regulatory Commission (IURC)
Interconnection rule170 IAC 4-4.3 (as amended by LSA #25-368, IURC RM #24-01) – Interconnection of customer facilities · source
Applies toInvestor-owned electric utilities subject to IURC jurisdiction (170 IAC 4-4.3-2). Municipal utilities and electric cooperatives are not covered.
Application formCommission-approved interconnection application and interconnection agreement forms, used by each IOU (170 IAC 4-4.3-4(c)).
TimelinesLevel 1/2: completeness notice 10 business days; determination 15 business days after complete; executable agreement 10 business days after approval; customer returns executed agreement at least 10 business days before operation; final approval after executed agreement and any inspection, conditioned on electrical code official approval (170 IAC 4-4.3-6, -7).
FeesLevel 1: no fee. Level 2: <= $50 + $1/kW nameplate (+ minor modifications/additional review, engineering <= $100/h). Level 3: <= $100 + $2/kW + study time (<= $100/h) (170 IAC 4-4.3-4(e)).
InsuranceNet metering facilities: liability coverage of at least $100,000 (homeowners, commercial or other); utility may not require higher limits or additional policies (170 IAC 4-4.2-8, referenced by 4-4.3-10(a)). Other customer facilities: only reasonable amounts of insurance against reasonably likely risks, mutual indemnification (170 IAC 4-4.3-10(b)).
External disconnectUtility may require the applicant to include a disconnect switch as a supplement to the equipment package (170 IAC 4-4.3-4(d)).
Export compensationNet billing – IC 8-1-40 (P.L.264-2017, SEA 309); 170 IAC 4-4.2 (net metering rule, legacy)
Net metering tariffs closed to new customers after June 30, 2022 (IC 8-1-40-11); legacy NEM customers continue per IC 8-1-40-13/-14. New distributed generation (<= lesser of 1 MW or average annual consumption, IC 8-1-40-3) is credited for excess distributed generation (instantaneous difference, IC 8-1-40-5) at 1.25 x the supplier's average marginal price of electricity of the prior year (IC 8-1-40-17). Applies to IURC-regulated public utilities; excludes municipally owned utilities and certain cooperatives (IC 8-1-40-4).
Municipal utilities and REMC/electric cooperatives are not bound by 170 IAC 4-4.3 or IC 8-1-40 (IC 8-1-40-4 excludes them) and set their own interconnection and DG policies (many through Hoosier Energy / Wabash Valley Power member policies, not reviewed).
- IURC Final Rulemaking RM #24-01 (LSA #25-368), amended 170 IAC 4-4.3: https://www.in.gov/iurc/files/ord_RM24-01_093025.pdf (retrieved 2026-11-13)
- 170 IAC 4-4.2-8 Insurance (net metering): https://www.law.cornell.edu/regulations/indiana/170-IAC-4-4.2-8 (retrieved 2026-11-13)
- 170 IAC 4-4.2-1 Definitions (net metering): https://www.law.cornell.edu/regulations/indiana/170-IAC-4-4.2-1 (retrieved 2026-11-13)
- IURC handout: IC 8-1-40 statute text: https://secure.in.gov/iurc/files/2017-07-20-IURC-Tech-Conf-Handout-re-IC-8-1-40.pdf (retrieved 2026-11-13)
Other utilities in Indiana
- AES Indiana469,634
- NIPSCO433,889
- Indiana Michigan Power (I&M)425,007
- CenterPoint Energy Indiana South134,700
- Hendricks County Rural E M C38,554
- South Central Indiana REMC35,216
- Northeastern Rural E M C31,034
- City of Anderson29,600
- Tipmont Rural Electric Member Corporation29,540
- Johnson County Rural E M C29,132
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.