Electric cooperativeWREC interconnection application
WREC is an electric cooperative serving 231,677 residential customers in Florida (EIA-861, 2025). Applications: PDF + email (Application for Operation of Renewable Generation System (RGS) + Net Metering Agreement, emailed to rgs@wrec.net). Gridpol files WREC interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from WREC’s official sources (see below). Fees and size tiers not published; confirm with WREC engineering (352) 567-5133.
WREC at a glance
Withlacoochee River Elec Coop (Seminole Electric Cooperative (wholesale supplier))
TypeElectric cooperative
EIA utility ID20885
Residential customers231,677 (EIA-861, 2025)
Net-metered residential customers5,637 (EIA-861, 2025)
Service territory5 counties in Florida
How to applyPDF + email – Application for Operation of Renewable Generation System (RGS) + Net Metering Agreement, emailed to rgs@wrec.net · official link
Who submitsContractor and/or WREC member completes fillable PDF; contractor signs and certifies UL 1741/IEEE 1547 compliance.
Export compensationNEM – Net Metering Agreement
Annual excess bought at Seminole Electric Cooperative avoided cost.
Seminole Electric Cooperative, Inc.
Documents WREC asks for
- Interconnection application formFillable PDF (no handwritten or image copies) incl. 7-digit account number Gridpol prepares this.
- Interconnection agreementNet Metering Agreement
- Single-line diagram (one-line)Engineering-quality one-line PDF (permit set), panel count/size, battery interconnect/size/qty; no hand-drawn Gridpol prepares this.
- PV module spec sheetModule and inverter specifications PDF
- Inverter spec sheetManufacturer data sheet (string inverter, microinverter or hybrid inverter).
- Proof of insurance (when applicable)$1,000,000 liability for RGS >10 kW AC
How the WREC process runs
- Complete application PDF and Net Metering Agreement.
- Email single multipage PDF package to rgs@wrec.net (mail is slower).
- WREC may inspect array and verify equipment.
- After inspection and size verification, net meter installed.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $100 | Tampering charge if meter seal removed by non-WREC personnel | Not an application fee; no application fee found |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|
Insurance threshold 10 kW AC; no other size limits published.
Storage, EV and stamps
Battery storage
Battery backup must be IEEE 1547/UL 1741 compliant; number and wattage of batteries on application and one-line.
Common issues the utility lists
- Handwritten/picture applications rejected; incomplete packages delay net meter installation.
- Contact WREC to remove meter seal ($100 tampering charge otherwise).
Gridpol’s pre-submission check covers these before we file.
Sources
- WREC - Solar Energy: https://wrec.net/solar-energy (retrieved 2026-11-13)
- WREC Application for Operation of RGS: https://wrec.net/sites/default/files/wrec-application_for_renewable_generation_system_0-1.pdf (retrieved 2026-11-13)
- WREC Net Metering Agreement: https://wrec.net/sites/default/files/net_metering_agreement_102219.pdf (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.