FPL is an investor-owned utility serving 5,337,118 residential customers in Florida (EIA-861, 2025). Applications: Own online portal (FPL Net Metering online application (My Account)). Gridpol files FPL interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from FPL’s official sources (see below). Tier 3 fee amount not published on web pages.
FPL at a glance
Florida Power & Light Co (NextEra Energy)
TypeInvestor-owned utility
EIA utility ID6452
Residential customers5,337,118 (EIA-861, 2025)
Net-metered residential customers119,537 (EIA-861, 2025)
Service territory42 counties in Florida
How to applyOwn online portal – FPL Net Metering online application (My Account) · official link
Who submitsCustomer or contractor ('You or your contractor must complete the application requirements'); application tied to the customer's FPL online account.
Export compensationNEM – Net Metering (Rule 25-6.065)
Monthly kWh netting; excess carried forward month to month; unused credits at year-end paid at COG-1 as-available energy rate.
Per FAC 25-6.065(7) (IOUs): within 10 business days utility confirms application complete or lists deficiencies; agreement executed by utility within 30 calendar days of completed application (90 days if Tier 3 study needed); utility inspections within 30 calendar days of request; customer must notify utility 10 days before initial parallel operation. FPL web pages state no timeline; status by automated email.
Documents FPL asks for
- Interconnection application formOnline net metering application; pre-approval of system size before installation Gridpol prepares this.
- Interconnection agreementSigned Interconnection Agreement for Customer-Owned Renewable Generation (Tier 1/2/3)
- PV module spec sheetSolar panel details
- Inverter spec sheetInverter details
- Final inspection sign-offCopy of approved permit or AHJ website screenshot showing electrical (and mechanical) inspection sign-off, description of work, address, permit number, building department
- Proof of insurance (when applicable)Tier 2: ≥$1M, Tier 3: ≥$2M general liability; customer name + site address, 1-year term, insurer NAIC number, representative signature
How the FPL process runs
- Start online application and get pre-approval of system size before installation.
- Install system; obtain AHJ inspection.
- Submit application: sign Interconnection Agreement, upload documents (final/completed permit).
- Pay application fee if >10 kW (check with invoice).
- FPL reviews/approves (status emails).
- Bi-directional meter installed = permission to operate; no operation before meter except testing/inspection.
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Tier 1 ≤10 kW AC | |
| $400 | Tier 2 >10-100 kW AC | Per FPL Tier 2 interconnection agreement; paid by check with FPL invoice |
| Tier 3 >100 kW-2 MW | Application fee required; amount not stated on web pages |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Tier 1 | 10 kW | |
| Tier 2 | 100 kW | |
| Tier 3 | 2000 kW | |
| Net metering cap | 2000 kW |
AC gross power rating = DC x 0.85. Expected production should not exceed 115% of annual kWh use; generation limited to 90% of service capacity; ≥50 kW requires three-phase wye service. Interconnection at utility transformer or in meter can not permitted.
Storage, EV and stamps
Battery storage
BTM battery must be NRTL-listed to UL 1741 (non-UL1741 batteries DC-coupled behind a UL 1741 device); placard 'Battery storage utilized in this facility.' on meter enclosure. Battery/V2H/V2G stored energy for customer use only - export to grid not currently allowed. Backup-only battery (no renewables) needs no agreement but must prevent backfeed. Grid-interconnected stand-alone battery goes through Small Generator Interconnection Application; not net metered.
EV chargers
Net metering customers currently cannot join FPL EVolution Home program.
Common issues the utility lists
- Applications may be returned for corrections (no list published).
- Manual disconnect (Tier 2/3) must be visible-break, adjacent to meter, lockable with single FPL padlock, not in meter room.
Gridpol’s pre-submission check covers these before we file.
Sources
- FPL Net metering application process: https://www.fpl.com/netmetering.html (retrieved 2026-11-13)
- FPL Net Metering Guidelines: https://www.fpl.com/clean-energy/net-metering/guidelines.html (retrieved 2026-11-13)
- FPL Net Metering FAQ: https://www.fpl.com/clean-energy/net-metering/faq.html (retrieved 2026-11-13)
- FPL Tier 2 Interconnection Agreement: https://www.fpl.com/content/dam/fplgp/us/en/clean-energy/net-metering/pdfs/net-metering-tier2.pdf (retrieved 2026-11-13)
- Florida Admin. Code Rule 25-6.065 Interconnection and Net Metering of Customer-Owned Renewable Generation: https://www.flrules.org/gateway/readFile.asp?sid=0&tid=5455200&type=1&file=25-6.065.doc (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.