Home › Utilities › Alaska › Homer Electric Association Inc.
Electric cooperativeHomer Electric Association Inc. interconnection application
Homer Electric Association Inc. is an electric cooperative serving 30,143 residential customers in Alaska (EIA-861, 2025). Gridpol files Homer Electric Association Inc. interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Alaska’s interconnection rule (3 AAC 50.900-50.949 (Net Metering Standards), interconnection in 3 AAC 50.940) applies to Homer Electric Association Inc.. Levels, timelines and documents below come from that rule; Homer Electric Association Inc.’s own form and portal are confirmed on the first project.
Homer Electric Association Inc. at a glance
Homer Electric Assn Inc
TypeElectric cooperative
EIA utility ID19558
Residential customers30,143 (EIA-861, 2025)
Net-metered residential customers565 (EIA-861, 2025)
Service territory1 county in Alaska
Documents Homer Electric Association Inc. asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Interconnection agreementRequired by the state rule
- Inverter spec sheetRequired by the state rule
Documents required by the Alaska rule. Homer Electric Association Inc. may ask for more on its own form; we confirm on the first project.
Alaska interconnection rule
Regulatory Commission of Alaska (RCA)
Interconnection rule3 AAC 50.900-50.949 (Net Metering Standards), interconnection in 3 AAC 50.940 – Net Metering Standards - Interconnection of eligible consumer generation systems · source
Applies toElectric utilities subject to RCA economic regulation (e.g. Chugach Electric, MEA, GVEA, HEA, Alaska Electric Light & Power, AVEC), except independent systems with <5,000,000 kWh prior-year retail sales, 100%-renewable independent systems, or distribution portions exempted for stability (3 AAC 50.900(b)).
Application formUtility-specific interconnection application of no more than two pages, in utility interconnection tariff filed with RCA (3 AAC 50.940(a)).
FeesNo extra standby, capacity, interconnection or other net-metering fees unless commission approves (3 AAC 50.930); disconnect switch cost may be charged per 50.940.
InsuranceUtility tariff may require liability insurance only if coverage is readily available at reasonable cost to the consumer (3 AAC 50.940(a)).
External disconnectTariff must address external disconnect switch unless utility finds it unnecessary; consumer may choose switch at utility-designated accessible location or agreement allowing utility to disconnect generation and load. Switch+wiring cost chargeable if within 5 ft of meter base/at main structure; elsewhere consumer pays switch, utility pays wiring (3 AAC 50.940(a)).
Export compensationNEM – 3 AAC 50.900-50.949
Monthly netting; net excess credited at utility's non-firm power rate (avoided-cost type), credits never expire (3 AAC 50.930). IEEE 1547 / UL 1741 may be used as technical standards.
Electric cooperatives under RCA economic regulation are covered. Municipal utilities and utilities exempt from RCA economic regulation (AS 42.05) are not bound and set their own policies.
- 3 AAC 50 Art. 3 Net Metering Standards (LII): https://www.law.cornell.edu/regulations/alaska/title-3/part-7/chapter-50/article-3 (retrieved 2026-11-13)
- 3 AAC 50.900: https://www.law.cornell.edu/regulations/alaska/3-AAC-50.900 (retrieved 2026-11-13)
- 3 AAC 50.940: https://www.law.cornell.edu/regulations/alaska/3-AAC-50.940 (retrieved 2026-11-13)
- 3 AAC 50.930: https://www.law.cornell.edu/regulations/alaska/3-AAC-50.930 (retrieved 2026-11-13)
Other utilities in Alaska
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.