Home › Utilities › Alaska › AP&T (Alaska Power Company)

Investor-owned utility

AP&T (Alaska Power Company) interconnection application

AP&T (Alaska Power Company) is an investor-owned utility serving 5,798 residential customers in Alaska (EIA-861, 2025). Applications: PDF + mail (Application Net Metering Facility Not Greater than 25 kW (tariff Appendix, TA822-2) via local AP&T office). Gridpol files AP&T (Alaska Power Company) interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from AP&T (Alaska Power Company)’s official sources (see below). Confirmed from current tariff PDF on aptalaska.com (application form, requirements, Section 13). Submission channel is local AP&T office (no email/portal published); fees not stated in net metering section; Rate C values for RG2/RG4 not recorded.

AP&T (Alaska Power Company) at a glance

Utility

Alaska Power and Telephone Co (Alaska Power & Telephone)

Type

Investor-owned utility

EIA utility ID

219

Residential customers

5,798 (EIA-861, 2025)

Net-metered residential customers

3 (EIA-861, 2025)

Service territory

5 counties in Alaska

How to apply

PDF + mail – Application Net Metering Facility Not Greater than 25 kW (tariff Appendix, TA822-2) via local AP&T office · official link

Who submits

Retail customer who owns or leases the system signs the application; a separate contact (e.g. installer) may be listed. Customers must contact their local AP&T office before installing any equipment (Electric Service Requirements §210).

Export compensation

NEM – Section 13 Net Metering Service / Schedule A-6 Net Metering Rate (Rate C)
Monthly netting; net excess credited at Rate C avoided cost per rate group (RG1 $0.1133/kWh eff. 06/01/2025), adjusted with quarterly COPA. Credits do not expire; paid out at termination.

Review time (official)

Rule 6.13: written application at least 45 days before connection. No net metering review timeline stated.

Documents AP&T (Alaska Power Company) asks for

  • Interconnection application formAPC Application Net Metering Facility Not Greater than 25 kW (4 pages incl. Level 1 terms); utility countersignature = interconnection agreement Gridpol prepares this.
  • UL 1741 / IEEE 1547 certification (when applicable)Evidence of UL 1741 listing if equipment is listed; certified interconnection components listed
  • Single-line diagram (one-line) (when applicable)One-line diagram if required by APC; equipment specs, protection arrangement and design drawings for written approval before installation (Interconnection Requirements §15) Gridpol prepares this.
  • Final inspection sign-offApproval by local electrical wiring inspector, documentation sent to APC
  • Proof of insuranceStandard general liability (homeowners) coverage with proof of insurance
  • Other utility-specific documentSigned attestation to APC Interconnection Requirements for Net Metering Power Producers

How the AP&T (Alaska Power Company) process runs

  1. Contact local AP&T office before installing; confirm net metering capacity is available in the rate group
  2. Submit net metering application (with UL 1741 evidence, one-line/specs as required) and signed interconnection requirements attestation
  3. APC signs application (executes Level 1 interconnection agreement); then customer may construct
  4. Local electrical wiring inspector approval sent to APC
  5. APC inspection/joint testing (or waiver); APC installs bi-directional meter; written approval before parallel operation

Size levels and limits

LevelUp toNote
Net metering (Section 13)25 kWNameplate per consumer premises; inverter required
QF interconnection (Rule 6.13)100 kWAlternate technology under 100 kW
Net metering cap25 kW

Net metering only in rate groups meeting 5 million kWh threshold: RG1 Skagway/Haines (cap 47.1 kW, 14.5 used), RG2 Prince of Wales (56.5 kW), RG4 Tok area (23.4 kW, fully used) per sheet 129 eff. 03/28/2025. Not available in all locations. One net metering facility per distribution transformer unless waived; single-phase >10 kW not on three-phase transformer.

Storage, EV and stamps

Battery storage

Rule 6.13 requires description of energy storage devices with the interconnection documentation; no specific battery rules in net metering section.

EV chargers

AP&T Amp-Up EV incentive program (incentives page); no EV interconnection process.

Common issues the utility lists

  • Net metering capacity limit (1.5% of average retail demand) reached in the rate group
  • Location not in a net-metering rate group (not available in all locations)

Gridpol’s pre-submission check covers these before we file.

Sources

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO