Investor-owned utilityPepco interconnection application
Pepco is an investor-owned utility serving 883,572 residential customers in District of Columbia, Maryland (EIA-861, 2025). Applications: Own online portal (Connect the Grid Interconnection Portal (Green Power Connection)). Gridpol files Pepco interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from Pepco’s official sources (see below). DC timelines (DCMR Title 15 Ch. 40) not checked; EV charger process not documented on GPC pages.
Pepco at a glance
Potomac Electric Power Co (Exelon (Pepco Holdings))
TypeInvestor-owned utility
EIA utility ID15270
Residential customers883,572 (EIA-861, 2025)
Net-metered residential customers61,215 (EIA-861, 2025)
Service territory1 county in District of Columbia, 2 counties in Maryland
How to applyOwn online portal – Connect the Grid Interconnection Portal (Green Power Connection) · official link
Who submitsContractor registers in portal and submits on behalf of customer; customer can also apply; customer and contractor both track status.
Export compensationNEM – MD net energy metering; D.C. Customer Net Energy Metering Contract
DC requires the NEM contract for Levels 1-4
COMAR 20.50.09.09 Level 1: complete/incomplete notice within 5 business days; safety verification within 15 business days after completeness; approval and permission-to-operate notice within 20 business days of receiving acceptable documents. Invoice emailed within four business days after submission (Pepco MD page); fees paid before technical review.
Documents Pepco asks for
- Interconnection application formUtility Level 1 (or Level 2-4) Interconnection Application/Agreement uploaded in Connect the Grid Gridpol prepares this.
- Recent electric billcustomer's recent bill
- PV module spec sheetmanufacturer spec sheets of proposed system
- Inverter spec sheetmanufacturer spec sheets
- Single-line diagram (one-line)electronic single-line drawing Gridpol prepares this.
- Site plan / site layoutelectronic site plan Gridpol prepares this.
- Customer signaturesignatures on application/agreement
- Battery spec sheet (when applicable)Energy Storage Supplemental Form when storage is included
- Final inspection sign-offApplication Part 2 / Certificate of Completion after install with local electrical inspection
- Net metering / net billing agreement (when applicable)DC: D.C. Customer Net Energy Metering Contract; MD ANEM rider for aggregated NEM
- Other utility-specific document (when applicable)MD Site Control form, Pre-Application form (optional), Change Notice for new homeowners
How the Pepco process runs
- Contractor registers and logs in to the Connect the Grid portal
- Contractor completes online application, uploads utility interconnection form/agreement, technical documents and signatures, submits
- System calculates fee and emails invoice; fees must be paid before technical review
- Application proceeds through approval steps; customer and contractor track status in dashboard
- Contractor installs the system (after approval)
- Contractor completes Application Part 2 in the portal (completion/inspection)
- After final review the utility emails Permission to Operate to customer and contractor
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | MD/DC Level 1 (<=20 kW inverter-based) | |
| $50 + $1/kW AC | MD Level 2 (<=2 MW) | |
| $100 + $2/kW AC | MD Level 3/4 | |
| $237.86 per application ($231 + $6.86 admin) | MD MCAM-S residential (secondary <=600 V), from 2026-05-01 | commercial secondary: $151/kW + $0.15/kW admin |
| $500 | DC Level 2 (<=5 MW) and Level 3 | |
| $1,000 | DC Level 4 | applied toward studies |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | inverter-based (MD and DC) |
| Level 2 | 2000 kW | MD; DC Level 2 up to 5 MW |
| Level 3 | 10000 kW | MD radial/area networks <=50 kW; DC <=20 MW |
| Level 4 | 10000 kW | MD <10 MW; DC <20 MW |
Storage, EV and stamps
Battery storage
Energy Storage Supplemental Form required with application when storage is included. Maryland Energy Storage Supplemental Form submitted with the interconnection application: stand-alone vs. paired, shared inverter, whether it can charge from the grid (and how prevented), kW AC/kWh, operating intent (offset load/non-export, net meter, wholesale, backup), lockable visible AC disconnect, one-line diagram.
Sources
- Pepco Interconnection Application Process: https://www.pepco.com/smart-energy/my-green-power-connection/developers-contractors/applying-for-interconnection/interconnection-application-process (retrieved 2026-11-13)
- Pepco Maryland Applications and Forms: https://www.pepco.com/smart-energy/my-green-power-connection/developers-contractors/applying-for-interconnection/maryland-applications-and-forms (retrieved 2026-11-13)
- Pepco DC Applications Forms and Fees: https://www.pepco.com/smart-energy/my-green-power-connection/developers-contractors/applying-for-interconnection/dc-applications-forms-and-fees (retrieved 2026-11-13)
- Pepco MCAM: https://www.pepco.com/smart-energy/my-green-power-connection/developers-contractors/applying-for-interconnection/applying-for-interconnection-in-maryland (retrieved 2026-11-13)
- COMAR 20.50.09.09 Level 1 Review: https://regs.maryland.gov/us/md/exec/comar/20.50.09.09 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.