Investor-owned utilityBGE interconnection application
BGE is an investor-owned utility serving 1,220,644 residential customers in Maryland (EIA-861, 2025). Applications: Own online portal (Connect the Grid (Intellio) Interconnection Application Portal). Gridpol files BGE interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Process verified from BGE’s official sources (see below). Exact upload list in portal not published beyond application/COC; EV charger process not documented on GPC pages.
BGE at a glance
Baltimore Gas & Electric Co (Exelon)
TypeInvestor-owned utility
EIA utility ID1167
Residential customers1,220,644 (EIA-861, 2025)
Net-metered residential customers52,062 (EIA-861, 2025)
Service territory9 counties in Maryland
How to applyOwn online portal – Connect the Grid (Intellio) Interconnection Application Portal · official link
Who submitsDeveloper/contractor typically submits via portal; applicant must be the customer of record in BGE's billing system; the person who submits in the portal becomes the primary project contact.
Export compensationNEM – Maryland net energy metering
Interconnection application also serves net metering; MCAM fees do not affect bill credits
COMAR 20.50.09.09 Level 1: complete/incomplete notice within 5 business days; safety verification within 15 business days after completeness; approval and permission-to-operate notice within 20 business days of receiving acceptable documents. BGE: 5-day completeness check, 20-day technical review; BGE has 20 business days to issue PTO once Certificate of Completion package is complete (COMAR 20.50.29 per BGE). Agreement mailed within 5 business days of approval.
Documents BGE asks for
- Interconnection application formUtility Level 1 (or Level 2-4) Interconnection Application/Agreement uploaded in Connect the Grid Gridpol prepares this.
- Recent electric billcustomer's recent bill
- PV module spec sheetmanufacturer spec sheets of proposed system
- Inverter spec sheetmanufacturer spec sheets
- Single-line diagram (one-line)electronic single-line drawing Gridpol prepares this.
- Site plan / site layoutelectronic site plan Gridpol prepares this.
- Customer signaturesignatures on application/agreement
- Battery spec sheet (when applicable)Energy Storage Supplemental Form when storage is included
- Final inspection sign-offApplication Part 2 / Certificate of Completion after install with local electrical inspection
- Interconnection agreementBGE sends agreement after approval; must be signed and returned within 30 calendar days
- Other utility-specific document (when applicable)Aggregated Net Metering Addendum for ANM; Interconnection Agreement Change Notice for new owner of existing system
How the BGE process runs
- Submit interconnection application (Level 1-4) via Connect the Grid portal with storage form if applicable
- 5-day completeness check, technical review; BGE sends Interconnection Agreement (within 5 business days of approval)
- Customer signs and returns agreement within 30 calendar days
- Install system; obtain county electrical inspection
- Submit Certificate of Completion with electrical inspection certificate (DC size must match application; changes require modified application) to GPCTeam@bge.com
- BGE reviews package, notifies deficiencies, issues Permission to Operate letter; all funds due must be paid before interconnection
Fees
| Fee | Applies to | Note |
|---|---|---|
| $0 | Level 1 (<=20 kW) | COMAR application fee |
| $50 + $1/kW | Level 2 | |
| $100 + $2/kW | Level 3 and 4 | |
| $17 admin + $108 hosting capacity per application | MCAM-S residential (secondary <600 V), applications on/after 2026-05-01 | initial program year; recalculated annually |
Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.
Size levels and limits
| Level | Up to | Note |
|---|---|---|
| Level 1 | 20 kW | inverter-based, certified (COMAR 20.50.09.08B) |
| Level 2 | 2000 kW | radial circuit or spot network serving one customer |
| Level 3 | 10000 kW | non-export; area networks <=50 kW; net-metered systems not eligible (BGE) |
| Level 4 | 10000 kW | study process |
Maryland small generator rules cover up to 10 MW (COMAR 20.50.09)
Storage, EV and stamps
Battery storage
Maryland Energy Storage Supplemental Form submitted with the interconnection application: stand-alone vs. paired, shared inverter, whether it can charge from the grid (and how prevented), kW AC/kWh, operating intent (offset load/non-export, net meter, wholesale, backup), lockable visible AC disconnect, one-line diagram.
Common issues the utility lists
- Certificate of Completion system size differs from application size (final size may be smaller, never larger) - submit modified application
- Missing county electrical inspection certificate
- Unpaid funds due to BGE
Gridpol’s pre-submission check covers these before we file.
Sources
- BGE Choosing an Application: https://www.bge.com/smart-energy/my-green-power-connection/developers-contractors/choosing-an-application (retrieved 2026-11-13)
- BGE Applying for Interconnection: https://www.bge.com/smart-energy/my-green-power-connection/developers-contractors/applying-for-interconnection (retrieved 2026-11-13)
- BGE PTO Requirements for Solar Projects: https://www.bge.com/cdn/assets/v3/assets/blt71bfe6e8a1c2d265/blt348e14c8de2c55cd/64f6f458a91d4a000a138a9f/PTO_Requirements_for_Solar_Projects.pdf (retrieved 2026-11-13)
- BGE MCAM-S Overview for Residential Customers: https://www.bge.com/cdn/assets/v3/assets/blt71bfe6e8a1c2d265/blta66877b862ee4fe9/6a021e21c2a23f5a2b34046c/MCAM-S_Overview_for_Residential_Customers.pdf (retrieved 2026-11-13)
- BGE MD Energy Storage Supplemental Form: https://www.bge.com/cdn/assets/v3/assets/blt71bfe6e8a1c2d265/bltbd4babc3c910f80b/64f6f2b3a91d4a000a138a9b/BGEMDEnergyStorageForm.pdf (retrieved 2026-11-13)
- COMAR 20.50.09.09 Level 1 Review: https://regs.maryland.gov/us/md/exec/comar/20.50.09.09 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.