Home › Utilities › Maryland › BGE

Investor-owned utility

BGE interconnection application

BGE is an investor-owned utility serving 1,220,644 residential customers in Maryland (EIA-861, 2025). Applications: Own online portal (Connect the Grid (Intellio) Interconnection Application Portal). Gridpol files BGE interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.

Get started Look up another ZIP

Process verified from BGE’s official sources (see below). Exact upload list in portal not published beyond application/COC; EV charger process not documented on GPC pages.

BGE at a glance

Utility

Baltimore Gas & Electric Co (Exelon)

Type

Investor-owned utility

EIA utility ID

1167

Residential customers

1,220,644 (EIA-861, 2025)

Net-metered residential customers

52,062 (EIA-861, 2025)

Service territory

9 counties in Maryland

How to apply

Own online portal – Connect the Grid (Intellio) Interconnection Application Portal · official link

Who submits

Developer/contractor typically submits via portal; applicant must be the customer of record in BGE's billing system; the person who submits in the portal becomes the primary project contact.

Export compensation

NEM – Maryland net energy metering
Interconnection application also serves net metering; MCAM fees do not affect bill credits

Review time (official)

COMAR 20.50.09.09 Level 1: complete/incomplete notice within 5 business days; safety verification within 15 business days after completeness; approval and permission-to-operate notice within 20 business days of receiving acceptable documents. BGE: 5-day completeness check, 20-day technical review; BGE has 20 business days to issue PTO once Certificate of Completion package is complete (COMAR 20.50.29 per BGE). Agreement mailed within 5 business days of approval.

Documents BGE asks for

  • Interconnection application formUtility Level 1 (or Level 2-4) Interconnection Application/Agreement uploaded in Connect the Grid Gridpol prepares this.
  • Recent electric billcustomer's recent bill
  • PV module spec sheetmanufacturer spec sheets of proposed system
  • Inverter spec sheetmanufacturer spec sheets
  • Single-line diagram (one-line)electronic single-line drawing Gridpol prepares this.
  • Site plan / site layoutelectronic site plan Gridpol prepares this.
  • Customer signaturesignatures on application/agreement
  • Battery spec sheet (when applicable)Energy Storage Supplemental Form when storage is included
  • Final inspection sign-offApplication Part 2 / Certificate of Completion after install with local electrical inspection
  • Interconnection agreementBGE sends agreement after approval; must be signed and returned within 30 calendar days
  • Other utility-specific document (when applicable)Aggregated Net Metering Addendum for ANM; Interconnection Agreement Change Notice for new owner of existing system

How the BGE process runs

  1. Submit interconnection application (Level 1-4) via Connect the Grid portal with storage form if applicable
  2. 5-day completeness check, technical review; BGE sends Interconnection Agreement (within 5 business days of approval)
  3. Customer signs and returns agreement within 30 calendar days
  4. Install system; obtain county electrical inspection
  5. Submit Certificate of Completion with electrical inspection certificate (DC size must match application; changes require modified application) to GPCTeam@bge.com
  6. BGE reviews package, notifies deficiencies, issues Permission to Operate letter; all funds due must be paid before interconnection

Fees

FeeApplies toNote
$0Level 1 (<=20 kW)COMAR application fee
$50 + $1/kWLevel 2
$100 + $2/kWLevel 3 and 4
$17 admin + $108 hosting capacity per applicationMCAM-S residential (secondary <600 V), applications on/after 2026-05-01initial program year; recalculated annually

Utility fees are paid by the installer or customer; they are not part of the Gridpol plan.

Size levels and limits

LevelUp toNote
Level 120 kWinverter-based, certified (COMAR 20.50.09.08B)
Level 22000 kWradial circuit or spot network serving one customer
Level 310000 kWnon-export; area networks <=50 kW; net-metered systems not eligible (BGE)
Level 410000 kWstudy process

Maryland small generator rules cover up to 10 MW (COMAR 20.50.09)

Storage, EV and stamps

Battery storage

Maryland Energy Storage Supplemental Form submitted with the interconnection application: stand-alone vs. paired, shared inverter, whether it can charge from the grid (and how prevented), kW AC/kWh, operating intent (offset load/non-export, net meter, wholesale, backup), lockable visible AC disconnect, one-line diagram.

Common issues the utility lists

  • Certificate of Completion system size differs from application size (final size may be smaller, never larger) - submit modified application
  • Missing county electrical inspection certificate
  • Unpaid funds due to BGE

Gridpol’s pre-submission check covers these before we file.

Gridpol Unlimited

$500 / month

Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.

  • Unlimited interconnection applications
  • Single-line diagram and site plan for every application
  • Pre-submission check against the utility’s requirements
  • Homeowner e-signature link for the authorization
  • Filing in your utility portal accounts or by the utility’s method
  • Utility questions, corrections and resubmissions
  • Follow-up through approval, inspection and PTO
  • Customer list, exports, API and webhooks
Get started

Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.