Municipal utilityEaston Utilities Comm interconnection application
Easton Utilities Comm is a municipal utility serving 8,884 residential customers in Maryland (EIA-861, 2025). Gridpol files Easton Utilities Comm interconnection applications for licensed installers – solar, storage and EV chargers – with single-line diagram and site plan, unlimited for $500 a month.
Get started Look up another ZIP
Maryland’s interconnection rule (COMAR 20.50.09 (.01-.14)) applies to Easton Utilities Comm. Levels, timelines and documents below come from that rule; Easton Utilities Comm’s own form and portal are confirmed on the first project.
Easton Utilities Comm at a glance
Easton Utilities Comm
TypeMunicipal utility
EIA utility ID5625
Residential customers8,884 (EIA-861, 2025)
Net-metered residential customers52 (EIA-861, 2025)
Service territory1 county in Maryland
Documents Easton Utilities Comm asks for
- Interconnection application formRequired by the state rule Gridpol prepares this.
- Inverter spec sheetRequired by the state rule
- Customer signatureRequired by the state rule
- Interconnection agreementRequired by the state rule
- Final inspection sign-offRequired by the state rule
- Other utility-specific documentRequired by the state rule
Documents required by the Maryland rule. Easton Utilities Comm may ask for more on its own form; we confirm on the first project.
Maryland interconnection rule
Maryland Public Service Commission (PSC)
Interconnection ruleCOMAR 20.50.09 (.01-.14) – Small Generator Facility Interconnection Standards · source
Applies toSmall generator facilities (incl. storage) interconnecting to a utility's distribution system in Maryland, under PSC jurisdiction (Subtitle 50 'Service Supplied by Electric Companies': BGE, Pepco, Delmarva, Potomac Edison, SMECO, Choptank and other PSC-regulated electric companies). PJM-jurisdictional wholesale requests follow PJM.
Application formUtility-specified interconnection request form (utilities must align forms with other MD utilities) with electronic signature/submission and status tracking on the utility website by applicant or authorized designee (20.50.09.04).
TimelinesLevel 1: 5 BD completeness, 15 BD verification, 20 BD approval/PTO; interconnection agreement signed within 30 calendar days. Conditional approval validity: <=100 kW must deliver certificate of completion within 6 months, >100 kW within 12 months (+6 months extension) (20.50.09.06N).
FeesNo fee for Level 1; Levels 2-4 fees specified in utility tariff (20.50.09.05); no fees for PJM-jurisdictional requests; pre-application report fee per tariff.
InsuranceCOMAR 20.50.09.06 contains no insurance requirement; PUA §7-306 bars electric companies from requiring net-metered systems meeting NEC/IEEE/UL to buy additional liability insurance.
External disconnectRequired: lockable, visible-break isolation device accessible to the utility, customer-owned, between facility and point of interconnection (20.50.09.06G); utility lockbox allowed (06H). No inverter waiver in rule text.
Export compensationNEM – Md. Code, Public Utilities §7-306; COMAR 20.50.10
Offered until earlier of 3,000 MW statewide or 2027-07-01; 5 MW for community solar/meter aggregation; excess credited 12 months valued at commodity rate, paid after April cycle; indefinite accrual option not for munis/coops; coops <250,000 may pay monthly. COMAR 20.50.10.01 still shows 1,500 MW (stale).
Net metering statute §7-306 contains specific provisions for municipal utilities and cooperatives, i.e. they offer net metering too; PSC-regulated coops (SMECO, Choptank) follow COMAR 20.50.09.
- COMAR 20.50.09: https://regs.maryland.gov/us/md/exec/comar/20.50.09 (retrieved 2026-11-13)
- COMAR 20.50.09.08 Levels: https://regs.maryland.gov/us/md/exec/comar/20.50.09.08 (retrieved 2026-11-13)
- COMAR 20.50.09.09 Level 1: https://regs.maryland.gov/us/md/exec/comar/20.50.09.09 (retrieved 2026-11-13)
- COMAR 20.50.09.06 General: https://regs.maryland.gov/us/md/exec/comar/20.50.09.06 (retrieved 2026-11-13)
- PUA §7-306: https://mgaleg.maryland.gov/mgawebsite/laws/StatuteText?article=gpu§ion=7-306 (retrieved 2026-11-13)
$500 / month
Unlimited interconnection applications. 12-month agreement, signed online. The agreement starts the day you sign; first invoice right away, then monthly.
- Unlimited interconnection applications
- Single-line diagram and site plan for every application
- Pre-submission check against the utility’s requirements
- Homeowner e-signature link for the authorization
- Filing in your utility portal accounts or by the utility’s method
- Utility questions, corrections and resubmissions
- Follow-up through approval, inspection and PTO
- Customer list, exports, API and webhooks
Applications are typically submitted within 2 business days after complete documents. Utility review times are set by each utility.